716 results found for 'Triton offshore wind farm'

716 results found for 'Triton offshore wind farm'
Order results by

A list of search results

  • 3 June 2024
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The County Administrative Board of Gotland has suggested that the Government should issue a permit for the Aurora offshore wind farm, a project developed by OX2 and Ingka Investments, under the Act governing Sweden’s exclusive economic zone. If the government gives an approval, the first phase of the 5.5 GW offshore wind project could be […]

  • 24 June 2024
    Business & Finance, Infrastructure, Ports & Logistics

    The Titan Group has made the final investment decision (FID) to build a production facility for XXXL monopiles in Cuxhaven, Northern Germany. Up to EUR 300 million will be invested in the company, with production to ramp up next year. Titan Group said that more than 600 jobs will be created by the project. The […]

  • 4 November 2024
    Authorities, Floating Wind, Planning & Permitting

    The Swedish government has rejected 13 applications to build offshore wind farms in the Baltic Sea due to defence concerns while approving one project on the west coast, being developed by a joint venture between Vattenfall and Zephyr. On 4 November, the Swedish government announced that 13 submitted applications to build offshore wind farms in […]

  • 23 May 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    DEME Group’s heavy lift vessel, Orion, has installed the first monopile foundation for the 2.6 GW Coastal Virginia Offshore Wind (CVOW) project, the largest offshore wind farm under construction in the US. The first six monopiles were loaded onto DEME Group’s Orion this month, and the vessel headed to the offshore construction site approximately 43 […]

  • 10 October 2024
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Seaway7 has finished the full engineering, procurement, installation, and commissioning (EPIC) work for the cables at the 882 MW Moray West offshore wind farm in Scotland. Seaway7 has installed 118 kilometres of 66 kV inter-array cables, linking the wind farm’s 60 turbines to two offshore substations, along with an additional 15 kilometres of 66 kV […]

  • 13 August 2024
    Fixed-Bottom, Foundations, Project Updates, Wind Farm Update

    The 50th monopile foundation has been installed at the Coastal Virginia Offshore Wind (CVOW) project site off Virginia Beach in the US, according to Dominion Energy. The developer said on 12 August the 176-turbine project was on schedule to reach the goal of having 70-100 monopiles installed during the first installation season that runs through […]

  • 8 August 2024
    Fixed-Bottom, Green Hydrogen, Power-to-X, Project Updates, Wind Farm Update

    CrossWind, a joint venture between Shell and Eneco, has contracted Fores Engineering, a subsidiary of the Rosetti Marino Group, to assemble the 2.5 MW offshore electrolyser that Elogen will deliver for the now-operational Hollandse Kust Noord offshore wind project in the Netherlands. Fores Engineering’s scope includes detailed engineering, procurement, assembly, onshore yard integration, and commissioning […]

  • 28 October 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The DP3 installation vessel Orion, owned and operated by the Belgian offshore construction specialist DEME, is scheduled to begin installing the remaining monopile foundations at the Vineyard Wind 1 site in the US on or around 28 October, as disclosed in the project’s recent offshore wind mariner update. Prior to installation, the POLARIS and HOS RUGER […]

  • 7 June 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first transition pieces (TPs) destined for the Coastal Virginia Offshore Wind (CVOW) project have been loaded in at the Portsmouth Marine Terminal in the Commonwealth of Virginia, the US. In April, MV Sun Rise departed from the quayside of CS Wind Offshore in Aalborg, Denmark, loaded with six TPs for the 2.6 GW CVOW […]

  • 25 September 2024
    Collaboration, Floating Wind, Outlook & Strategy, R&D

    Five European offshore wind test sites have formed HiPoTeSis, a new alliance aiming to improve conditions for floating wind demonstration projects. BiMEP, CEO, Foundation Open-C, METCEntre and Plocan have created HiPoTeSis. This collaborative network of five operational offshore demonstration test sites aims to provide the European Union with the future high-power infrastructure for testing new […]

  • 12 September 2024
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    DEME Group has laid the first export cable for Dominion Energy’s 2.6 GW Coastal Virginia Offshore Wind (CVOW) project, while also reaching a milestone by installing the 70th monopile foundation at the site off Virginia Beach in the US. As previously reported, Dominion Energy selected the consortium of DEME Group and Prysmian as the Balance of Plant […]

  • 4 November 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Dominion Energy revealed that 78 monopile foundations and four offshore substations were installed at the 2.6 GW Coastal Virginia Offshore Wind (CVOW) project in the US during the first installation season. Dominion Energy said that it achieved its initial goal of installing at least 70 monopiles into the seafloor 27 miles off the coast of […]

  • 26 September 2024
    Contracts & Tenders, Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    RWE has awarded two contracts to Lamprell Energy Limited for the future supply of transition pieces to its two east coast UK offshore wind projects currently under development, Norfolk Vanguard West and Norfolk Vanguard East. RWE and Lamprell marked the signing of the contract with a small event at the WindEnergy Hamburg 2024 conference. The […]

  • 21 May 2024
    Authorities, Business development, Floating Wind, Planning & Permitting, R&D, Research & Development, Technology

    The Japanese MODEC and Toyo Construction have jointly obtained approval in principle (AiP) from Nippon Kaiji Kyokai (ClassNK) for a floating structure and whether system and tether pile foundation for tension leg platform (TLP) type floating offshore wind turbine. In 2020, MODEC obtained AiP for the floating offshore wind turbines from DNV. This time, both […]

  • 13 May 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first six foundations for Dominion Energy’s Coastal Virginia Offshore Wind (CVOW) project have been loaded onto DEME Group’s installation vessel, Orion. In addition, work on the second offshore substation for the 2.6 GW project has started at CS Wind Offshore’s production site in Aalborg, Denmark. The first six monopiles, which are produced by EEW […]

  • 13 May 2024
    Contracts & Tenders, Supply Chain, Vessels

    Norway’s Vard has signed a contract with an undisclosed Taiwanese customer for the design and construction of two Commissioning Service Operation Vessels (CSOVs). The customer has appointed Vard to build two CSOVs of VARD 4 39 design which is a new design from the Fincantieri-owned company, envisioned as a highly versatile all-round platform for wind farm […]

  • 3 May 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    Dominion Energy has issued a statement in response to claims that the Coastal Virginia Offshore Wind (CVOW) project was delayed saying the project was on schedule and that the installation vessel Orion would start construction between 6 and 8 May. “On April 29, anti-wind groups filed a petition in the United States District Court for the District of Columbia seeking […]

  • 25 June 2024
    Business development, Industry, Innovation, Operations & Maintenance, Supply Chain, Technology

    Amid the global energy transition, offshore survey and inspection companies are working on decarbonising – but the industry is also going through a transition of its own. Bureau Veritas,  Terradepth and Sulmara are among a number of offshore survey companies that are increasingly using autonomous or remotely operated robotics, cloud systems and artificial intelligence (AI) […]

  • 3 May 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Macquarie Asset Management has reached an agreement to divest a 10 per cent stake in the 714 MW East Anglia One offshore wind farm to NTR, on behalf of the L&G NTR Clean Power (Europe) Fund and the Development Bank of Japan. Following this transaction, Macquarie Asset Management will retain a 10 per cent stake […]

  • 24 April 2024
    Authorities, Planning & Permitting, Project Updates, Wind Farm Update

    The UK Planning Inspectorate has accepted RWE’s application for the Five Estuaries offshore wind farm for examination. The final planning decision for the project is expected in the summer of 2025. The project now moves into the pre-examination phase of the consenting process, with the examination phase expected to commence later in the summer and […]

  • 15 April 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    Read the latest news on CVOW here: 2.6 GW US Project Receives Final Federal Permit, Monopile Installation to Start in May The DP3 installation vessel Orion, owned and operated by the Belgian offshore construction specialist DEME, has sailed out of Invergordon in Scotland and is now en route to the United States, where it will […]

  • 15 April 2024
    Equipment, Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Belgian offshore construction company DEME, using its vessel Orion, has completed the installation of monopiles at the Moray West offshore wind farm site in Scotland.  Monopile installation at Moray West started in October 2023, with Boskalis’s vessel Bokalift 2 deployed for the work and Orion taking over in February. DEME’s Orion installed 29 monopiles for Ocean […]

  • 17 April 2024
    Equipment, Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Dutch company CAPE Holland has secured a contract with DEME for foundation installation equipment that will be used at the Coastal Virginia Offshore Wind (CVOW) project site in the US. Under the contract, CAPE Holland, part of Venterra Group, has provided its CAPE VLT-640 Quad spread and a separate CAPE VLT-640 unit to the Belgian […]

  • 16 April 2024
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    Dominion Energy’s 2.6 GW Coastal Virginia Offshore Wind (CVOW) project has received an air quality permit from the US Environmental Protection Agency (EPA) – the final federal permit required to begin offshore construction. The installation of monopiles at the project site off the coast of Virginia Beach is scheduled to begin in May. Belgian offshore […]

  • 25 April 2024
    Business & Finance, Business development, Cables, Grid Connection, Outlook & Strategy, Transition, Vessels

    Subsea7 has reported a “robust” backlog of USD 10.4 billion in its financial results for the first quarter of 2024, with tendering activity high in both the subsea and offshore wind sectors. To remind, in the financial results for the full year of 2023, Subsea7 reported it had secured USD 7.4 billion of contract awards […]

  • 9 April 2024
    Equipment, Grid Connection, Offshore Platforms, Supply Chain

    Axess Technologies has signed a contract for the supply of an export cable pull-in system that will be mounted on the offshore substation at the Empire Wind 1 offshore wind farm in the US. The offshore substation will be delivered by the Singapore-based company Seatrium. Under the contract with Seatrium, a wholly-owned subsidiary of Sembcorp Marine […]