465 results found for 'Vineyard Wind'

465 results found for 'Vineyard Wind'
Order results by

A list of search results

  • 18 July 2024
    Project Updates, Wind Farm Update

    The US Bureau of Safety and Environmental Enforcement (BSEE) has issued an order instructing Vineyard Wind to halt electricity production from all wind turbines following a blade failure incident on 13 July. The 800 MW Vineyard Wind offshore wind farm is planned to feature 62 GE Vernova’s Haliade-X 13 MW wind turbines, each with a […]

  • 16 July 2024
    Project Updates, Wind Farm Update

    NOTE: The article was updated on 19 July with more information about the GE Vernova turbine blade incident at the Vineyard Wind project.  A turbine blade at the Vineyard Wind 1 offshore wind farm in the US has been damaged, leading to an investigation by the blade’s manufacturer, GE Vernova. Vineyard Wind, a joint venture […]

  • 14 August 2024
    Authorities, Fixed-Bottom, Project Updates, Wind Farm Update

    The US Bureau of Safety and Environmental Enforcement (BSEE) has allowed Vineyard Wind to resume certain limited additional activities at the Vineyard Wind 1 offshore wind farm site. These include the installation of towers and nacelles but not (yet) the installation of the wind turbine blades. BSEE issued an update to the Suspension Order the […]

  • 26 June 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The Vineyard Wind 1 project is now delivering more than 136 MW to the electric grid in Massachusetts, making it the largest operating offshore wind project in the US. Vineyard Wind 1, the first large-scale offshore wind project in the US, now has ten turbines in operation totalling approximately 136 MW, enough to power 64,000 […]

  • 24 October 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Following a July blade failure incident, GE Vernova plans to remove some blades and strengthen others at the Vineyard Wind 1 offshore wind farm in the US. The companies are implementing the incident and response action plan, which was announced in August. The plan outlined steps to safely remove the remainder of the damaged blade […]

  • 13 August 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Vineyard Wind and GE Vernova have set out an action plan covering several main tasks following the blade incident at Vineyard Wind 1 offshore wind farm. The plan includes removing the remainder of the damaged blade on the turbine AW-38, continuing the collection of any debris, and resuming turbine installation and operations. The blade incident […]

  • 1 August 2024
    Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Windar Renovables has manufactured and loaded the final batch of transition pieces (TPs) for the 806 MW Vineyard Wind 1 offshore wind farm in the United States. In 2019, Windar Renovables won a contract to manufacture, certify, assemble, inspect, store, and deliver TPs for the offshore wind project, being developed by Vineyard Wind, a joint […]

  • 17 July 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Following a blade damage incident that took place on 13 July at its 800 MW offshore wind project in Massachusetts, Vineyard Wind has revealed that it is mobilising debris recovery teams on Nantucket. Vineyard Wind, a joint venture between Iberdrola’s US subsidiary Avangrid and Denmark’s Copenhagen Infrastructure Partners (CIP), announced on 16 July that it […]

  • 28 October 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The DP3 installation vessel Orion, owned and operated by the Belgian offshore construction specialist DEME, is scheduled to begin installing the remaining monopile foundations at the Vineyard Wind 1 site in the US on or around 28 October, as disclosed in the project’s recent offshore wind mariner update. Prior to installation, the POLARIS and HOS RUGER […]

  • 25 July 2024
    Business & Finance, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The breakage of the blade on one of GE Vernova’s Haliade-X wind turbines at the Vineyard Wind 1 offshore wind farm in the US was caused by a manufacturing deviation, the company’s CEO Scott Strazik revealed during an earnings call on 24 July. Strazik also pointed out that a blade event that happened on a […]

  • 23 August 2024
    Fixed-Bottom, Manufacturing, Supply Chain, Wind Farm Update, Wind Turbines

    This article was updated at 15:05 CET on 23 August 2024 with a statement from GE Vernova. One of the already installed wind turbine blades at Dogger Bank A offshore wind farm, currently under construction in the UK, has sustained damage and failed. The blade failure occurred on the morning of 22 August and, according […]

  • 9 September 2024
    Authorities, Planning & Permitting

    Massachusetts and Rhode Island have published the results of their first multi-state offshore wind solicitation, selecting nearly 2.9 GW of offshore wind power. As a part of the procurement, Massachusetts selected 2,678 MW in total from three projects and Rhode Island awarded 200 MW to one project. Massachusetts selected 1,087 MW of the multi-state 1,287 […]

  • 18 July 2024
    Business & Finance, Business development, Collaboration, Outlook & Strategy, Research & Development

    EDF Renewables and Repsol have signed an exclusivity agreement to collaborate on future offshore wind tenders in Spain and Portugal. According to the press release, this collaboration combines Repsol’s commitment to multi-energy growth and its knowledge of the Spanish and Portuguese markets with EDF Renewables’ technological experience. Repsol said that it expects to have 9,000 […]

  • 6 June 2024
    Business & Finance, Contracts & Tenders, Supply Chain

    Dutch offshore access provider, Ampelmann, has received an order from Seaway7 to supply an E5000 gangway, which will support the construction of a major US coast offshore wind project. The order not only marks the first collaboration of Seaway7 and Ampelmann in the Americas but will also see the first tour of duty of the […]

  • 29 July 2024
    Business & Finance, Equipment, Infrastructure, Supply Chain

    Twin Brothers Marine (TBM), a provider of heavy steel fabrication for the oil and gas, infrastructure, and renewable energy industries, has joined a major infrastructure development project to support multiple renewable energy initiatives, including offshore wind, along the Northeast Coast in the US. The project will involve the fabrication and delivery of 3,000 tonnes of […]

  • 10 July 2024
    Business & Finance, Industry, Market Outlooks, Outlook & Strategy, Supply Chain

    The American Clean Power Association (ACP) has projected there will be approximately 14 GW of offshore wind capacity deployed by 2030, falling short of the 30 GW goal set by the Biden Administration in 2021. ACP’s recent report also outlines USD 65 billion (approximately EUR 60 billion) in investments and 56,000 jobs in the US […]

  • 26 June 2024
    Business & Finance, Contracts & Tenders, Floating Wind, Supply Chain, Wind Turbines

    Denmark’s Floating Power Plant has purchased a wind turbine from Siemens Gamesa Renewable Energy for its flagship demonstrator project located off the coast of Gran Canaria. According to the company, the selected wind turbine, a 4.3 MW SWT-DD-120 from Siemens Gamesa, fits Floating Power Plant’s requirements for a well-established technology. The wind turbine generator will […]

  • 18 July 2024
    Business & Finance, Business development, Ports & Logistics, Research & Development

    NIRAS has been selected by the Asian Development Bank (ADB) to prepare pre-feasibility studies to assess the expansion of several ports for use as offshore wind ports. The Denmark-headquartered consultancy company has been commissioned by ADB on behalf of the Philippine government. Under the contract, NIRAS will prepare the pre-feasibility studies for the expansion of […]

  • 26 July 2024
    Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    More than a quarter of wind turbines at Dogger Bank A, the first phase of the UK’s 3.6 GW Dogger Bank Wind Farm, have been installed. So far, 27 of the 95 GE Haliade-X 13 MW wind turbines that Dogger Bank A will comprise are in place, according to information in Equinor’s results for the […]

  • 16 July 2024
    Business & Finance, Business development, Research & Development

    Energy and marine consultancy ABL has been selected by Germany’s Federal Maritime and Hydrographic Agency (BSH) to conduct a navigational risk assessment of offshore wind farm sites in the N-10 identified area of interest in the German North Sea. ABL’s scope of work is to provide a comprehensive navigational risk assessment, including recommendations for risk […]

  • 19 July 2024
    Contracts & Tenders, Grid Connection, Offshore Platforms, Onshore Infrastructure, Supply Chain

    The transmission system operator (TSO) 50Hertz has awarded the consortium comprising Dragados Offshore, a subsidiary of Cobra IS, and Siemens Energy a EUR 2.9 billion contract to design, build, and install two electrical conversion stations. The consortium’s scope of work consists of supplying an offshore converter for the LanWin3 grid connection project in the North […]

  • 2 September 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The blade failure event at the Dogger Bank A offshore wind farm last month was not caused by an installation or manufacturing issue but happened during the commissioning process, according to an analysis conducted by GE Vernova. The blade failure occurred on the morning of 22 August and, according to an update from the Dogger […]

  • 2 July 2024
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    Avangrid, a US renewable energy company majority-owned by Spanish Iberdrola, has received the authorisation to build and operate its New England Wind offshore wind farms from the Bureau of Ocean Energy Management (BOEM). This is the final approval needed from BOEM for the two projects offshore Massachusetts totalling 2.6 GW, following the federal agency’s Record […]

  • 19 August 2024
    Business & Finance, Fixed-Bottom, Foundations, Supply Chain

    Japan-based Sumitomo Corporation has acquired an equity stake in EEW Offshore Wind Holding, one of three new holding companies EEW Group founded to organise its business more efficiently, according to the German foundation manufacturer. According to EEW Group, Sumitomo’s stake has been in commercial effect since 1 July. The Group said on 19 August that, […]

  • 26 July 2024
    Authorities, Business & Finance, Business development, Floating Wind, Planning & Permitting, R&D, Research & Development

    The US Department of Energy’s (DOE’s) Wind Energy Technologies Office (WETO) has launched the Offshore Wind National and Regional Research and Development Funding Opportunity, allocating USD 48.6 million to projects designed to address several key needs in offshore wind development. The areas include accelerating research and development of floating offshore wind platforms; exploring innovations for […]

  • 1 August 2024
    Business & Finance, Business development, Contribution, Industry, Jobs & Recruitment, Supply Chain

    This is an op-ed piece by Sam Salustro, Vice President of Strategic Communication at Oceantic Network, the US offshore renewable energy industry organisation.  Six months occupied with questions about the upcoming election have muddied the waters, shifting the conversation about offshore wind energy away from the real groundwork being laid and progress already underway in […]