1055 results found for 'dogger bank'

1055 results found for 'dogger bank'
Order results by

A list of search results

  • 8 November 2024
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Production of the last transition piece (TP) for the 3.6 GW Dogger Bank Wind Farm, the world’s largest offshore wind farm under construction, is underway at Smulders facility in Hoboken, Belgium. The consortium comprising Sif and Smulders was awarded contracts for the manufacture of all monopiles and transition pieces for the three-phased Dogger Bank Wind […]

  • 26 July 2024
    Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    More than a quarter of wind turbines at Dogger Bank A, the first phase of the UK’s 3.6 GW Dogger Bank Wind Farm, have been installed. So far, 27 of the 95 GE Haliade-X 13 MW wind turbines that Dogger Bank A will comprise are in place, according to information in Equinor’s results for the […]

  • 24 July 2024
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Delivery partners have completed the installation of over 328 kilometres of 66 kV inter-array cables for Dogger Bank A, the first phase of the UK’s Dogger Bank Wind Farm, marking the completion of all inter-array cable work for this phase. The 66 kV XLPE-insulated inter-array cables were manufactured by Hellenic Cables under a contract with […]

  • 12 July 2024
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    SSE and Equinor, the co-developers of the 2 GW Dogger Bank D project (DBD), and The Crown Estate have established commercial terms of a proposed variation of the existing Dogger Bank C seabed lease, within which the two partners plan to build the fourth phase of Dogger Bank Wind Farm. The fourth phase of already […]

  • 23 August 2024
    Fixed-Bottom, Manufacturing, Supply Chain, Wind Farm Update, Wind Turbines

    This article was updated at 15:05 CET on 23 August 2024 with a statement from GE Vernova. One of the already installed wind turbine blades at Dogger Bank A offshore wind farm, currently under construction in the UK, has sustained damage and failed. The blade failure occurred on the morning of 22 August and, according […]

  • 28 June 2024
    Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    NOTE: Updated on 12 July with information on the expected timeframe within which the developers could submit a DCO application. SSE and Equinor, co-owners/developers of the Dogger Bank D offshore wind project, have submitted a Scoping Report for the 2 GW project to the UK’s Planning Inspectorate. The report is filed in preparation for carrying […]

  • 3 October 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    SSE has revealed that the completion of Dogger Bank A, the first of the three phases of the UK’s Dogger Bank Wind Farm, is projected for the second half of 2025, which is later than the previously expected first half of the year. In its interim earnings report released on 3 October, SSE said that […]

  • 12 August 2024
    Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    A multibeam echosounder (MBES) geophysical survey of the Dogger Bank D offshore wind site, using several uncrewed surface vessels (USVs), is scheduled to start on 13 August. According to information in the project’s Notice to Mariners, XOCEAN will deploy multiple USVs to survey the wind turbine array site and the export cable route. The USVs will […]

  • 2 September 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The blade failure event at the Dogger Bank A offshore wind farm last month was not caused by an installation or manufacturing issue but happened during the commissioning process, according to an analysis conducted by GE Vernova. The blade failure occurred on the morning of 22 August and, according to an update from the Dogger […]

  • 30 July 2024
    Cables, Grid Connection

    Tekmar Group has completed its role in the Dogger Bank A offshore wind farm by supplying essential cable protection systems (CPS) for the project’s inter-array cables. This month, Dogger Bank A, the first phase of the UK’s 3.6 GW Dogger Bank Wind Farm, achieved a significant milestone with the installation of all inter-array cables at […]

  • 9 August 2024
    Contracts & Tenders, Fixed-Bottom, Supply Chain

    RWE has awarded a contract to CHC Helicopter for crew change support at the Sofia offshore wind farm, currently under construction on Dogger Bank, 195 kilometres from the North East coast of the UK. According to CHC Helicopter, this is the first time RWE has contracted a helicopter service during the construction phase of an […]

  • 17 May 2024
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Dutch offshore wind foundation manufacturer, Sif, has started the production of monopile foundations for the third phase of the Dogger Bank Wind Farm in the UK, the world’s biggest offshore wind farm under construction. According to a trading update Sif issued on 17 May, the company — which is delivering foundations for all three phases […]

  • 25 July 2024
    Business & Finance, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The breakage of the blade on one of GE Vernova’s Haliade-X wind turbines at the Vineyard Wind 1 offshore wind farm in the US was caused by a manufacturing deviation, the company’s CEO Scott Strazik revealed during an earnings call on 24 July. Strazik also pointed out that a blade event that happened on a […]

  • 24 July 2024
    Fixed-Bottom, R&D

    The Fugro Quest vessel, operated by Fugro, is en route to the northeast coast of England to begin geotechnical survey work on the site of the proposed Dogger Bank South (DBS) West, one of two proposed DBS offshore wind farms. Fugro Quest, launched in 2022, left Falmouth on 23 July 2024 to initiate geotechnical assessments […]

  • 14 May 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Seaway7’s vessels, Seaway Strashnov and Seaway Alfa Lift, have commenced the installation of monopile foundations and transition pieces (TPs) for Dogger Bank B, the second phase of the 3.6 GW Dogger Bank Wind Farm in the UK, which is set to become the world’s largest offshore wind farm once in operation. The monopiles and TPs, […]

  • 11 July 2024
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The UK Planning Inspectorate has accepted into the examination phase the Development Consent Order (DCO) application for the Dogger Bank South (DBS) Offshore Wind Farms developed by RWE and Masdar. The DBS East and DBS West offshore wind farms, which could provide electricity for up to three million typical UK homes, are located in shallow […]

  • 7 August 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Vessels, Wind Farm Update

    Heerema Marine Contractors’ semi-submersible crane vessel (SSCV) Sleipnir is expected to sail to the Sofia offshore wind farm site in the UK in a few days to install the project’s HVDC offshore converter platform. According to a recent Notice to Mariners from the project, Sleipnir will start the work on or around 10 August and […]

  • 4 November 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Van Oord, using its jack-up vessel Aeolus, has installed 34 of the total 100 monopiles at the Sofia offshore wind farm site in the UK, according to a Notice to Mariners issued on 29 October. Aeolus installed the first monopile at the Sofia project site, located on Dogger Bank in the central North Sea, in […]

  • 23 August 2024
    Vessels

    Norway’s Integrated Wind Solutions has taken delivery of its third Commissioning Service Operation Vessel (CSOV) in the Skywalker class series, named IWS Seawalker. IWS Fleet, a fully owned subsidiary of IWS, signed newbuild contracts with China Merchants Heavy Industry (CMHI) for two purpose-built, walk-to-work CSOVs in March 2021 through IWS’s then subsidiary Awind. In March 2022, IWS […]

  • 6 June 2024
    Business & Finance, Vessels

    UK-headquartered North Star has secured debt investment of up to GBP 425 million (approximately EUR 500 million) to accelerate its ambition to add 40 hybrid service operation vessels (SOV) to its fleet by 2040. The committed financial package of GBP 225 million includes term facilities from existing lenders, IFM investors, and committed capex and working […]

  • 3 October 2024
    Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    RWE has unveiled the first 108-metre turbine blade made at the Siemens Gamesa factory in Hull, which will be part of 100 wind turbines to be installed at the 1.4 GW Sofia offshore wind farm in the UK. Each of the 100 wind turbines, rated at 14 MW, will be equipped with 108-metre-long blades that […]

  • 7 November 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Vårgrønn has agreed to acquire a 27.4 per cent stake in the 288 MW Baltic 2 offshore wind farm from PGGM Infrastructure Fund, marking its entry into the German market. Following the deal closing, Vårgrønn and EnBW will own 27.4 per cent and 50.1 per cent, respectively, with EnBW responsible for operations and maintenance activities. […]

  • 29 August 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The high-voltage direct current (HVDC) offshore converter platform (OCP) has been installed at the Sofia offshore wind farm site in the UK. The installation was carried out by Heerema Marine Contractors, using its Sleipnir heavy-lift vessel as a subcontractor to the GE Vernova/Seatrium consortium responsible for the OCP. The platform, equivalent in height to an […]

  • 24 May 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain, Vessels

    North Star has secured a contract with Siemens Gamesa to build a hybrid service operations vessel (SOV) bound for long-term charter at the 1.4 GW East Anglia THREE offshore wind farm, located off the Suffolk coast, England. The construction project for the SOV of VARD 4 19 design has been awarded by North Star to […]

  • 23 May 2024
    Business & Finance, Collaboration, Outlook & Strategy

    Cyan Renewables, a portfolio company of Seraya Partners, and Ocean Infinity have teamed up to provide geophysical and geotechnical services for offshore wind projects in the Asia-Pacific region. The companies have formalized their partnership through the signing of a Memorandum of Understanding (MoU), underscoring their shared commitment to work together on delivering geophysical and geotechnical […]

  • 24 October 2024
    Cables, Grid Connection, Project Updates, Vessels, Wind Farm Update

    Van Oord’s new, next-generation cable-laying vessel (CLV) Calypso has begun installing cables at its first offshore wind project, marking its official debut. Calypso’s first project is RWE’s Sofia offshore wind farm, being constructed on Dogger Bank in the central North Sea, 195 kilometres from the North East coast of the UK, which, with a capacity […]