409 results found for 'formosa'

409 results found for 'formosa'
Order results by

A list of search results

  • 15 November 2024
    Authorities, Business & Finance, Fixed-Bottom, Planning & Permitting

    Formosa 4, Synera Renewable Energy’s (SRE) third offshore wind project in Taiwan, received the establishment permit from the Energy Administration, Ministry of Economic Affairs, in late October. According to SRE, Formosa 4 is the first project to reach this milestone among all successful bidders in the first auction for Phase 3 Zonal Development for Offshore […]

  • 9 July 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Scotland-headquartered Sulmara has completed a site characterization survey for the Formosa 4 offshore wind project in Taiwan, developed by Synera Renewable Energy (SRE). To overcome challenging environmental site conditions, Sulmara said it employed an industry-first, multi-platform approach running the sensors to meet the specified data coverage and data quality requirements. “When we began assessing the […]

  • 12 November 2024
    Authorities, Fixed-Bottom, Planning & Permitting

    Synera Renewable Energy Group (SRE Group) has submitted the administrative contract for the 800 MW Formosa 6 offshore wind project to Taiwan’s Energy Administration, Ministry of Economic Affairs. The submission of the administrative contract, which is said to be on schedule, comes at a critical juncture in addressing the export sector’s demands for renewable power […]

  • 6 August 2024
    Authorities, Business & Finance, Fixed-Bottom, Planning & Permitting

    Taiwan’s Ministry of Economic Affairs (MOEA) has released the list of the projects awarded capacity in the latest offshore wind tender round. Five projects have been selected, totalling 2.7 GW in generation capacity. The projects are the 700 MW Youde (Shinfox), the 800 MW Formosa 6 (Synera Renewable Energy), the 600 MW Fengmiao 2 (Copenhagen Infrastructure Partners), […]

  • 22 November 2024
    Business & Finance, Business development, Fixed-Bottom, Research & Development

    Taiwan-based Synera Renewable Energy (SRE) has joined forces with Moondo Wind Energy (MWE) to develop an offshore wind project in the South Sea of South Korea. The two companies have formed a joint venture called Moondo Offshore Wind Energy. This marks Synera’s entry into the South Korean market and its second expansion beyond Taiwan, following […]

  • 23 August 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    All transition pieces (TPs) have been installed at the 640 MW Yunlin offshore wind farm in Taiwan. With all 80 monopiles and 68 wind turbines now in place – 52 of which are already feeding clean electricity into the grid – the project has moved into its final installation phase. Major offshore construction work at […]

  • 30 April 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Operations & Maintenance, Supply Chain

    James Fisher and Sons plc (James Fisher) has been awarded a contract for the provision of high voltage (HV) specialist personnel and HV safety management services at the 298 MW Zhong Neng offshore wind farm in Taiwan. Under the contract, worth over GBP 1 million (approximately EUR 1.17 million), James Fisher’s renewables team will securely […]

  • 28 October 2024
    Cables, Fixed-Bottom, Floating Wind, Grid Connection, Manufacturing, Supply Chain

    At a North Seas Energy Cooperation (NSEC) Ministerial Meeting held on 24 October in Odense, Denmark, the energy ministers of nine North Sea countries signed a new declaration which, among other things, calls for a digital transparency tool for offshore wind tenders and supply chain capacities. NSEC ministers also issued recommendations for hybrid offshore wind […]

  • 13 August 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Vineyard Wind and GE Vernova have set out an action plan covering several main tasks following the blade incident at Vineyard Wind 1 offshore wind farm. The plan includes removing the remainder of the damaged blade on the turbine AW-38, continuing the collection of any debris, and resuming turbine installation and operations. The blade incident […]

  • 2 February 2024
    Vessels

    Seaway7 is saying goodbye to Seaway Yudin, one of the company’s founding vessels and one of the first vessels of its size to serve the offshore wind industry, having entered the offshore wind construction market in 2009. In a social media post published on 2 February, Seaway7 said that the company said farewell to the […]

  • 9 March 2020
    Wind Farm Update

    JERA has reached an agreement with Macquarie’s Green Investment Group (GIG) and EnBW Energie Baden-Württemberg AG (EnBW) to join the development of the Formosa 3 offshore wind farm in Taiwan. JERA now holds 43.75% of the project, with GIG holding 31.25% and EnBW 25%, retaining material stakes and remaining committed to the ongoing development. The […]

  • 15 October 2020
    Business & Finance, Contracts & Tenders, Operations & Maintenance

    CWind Taiwan has been awarded a balance of plant (BOP) contract for the Formosa 1 offshore wind farm. The company is providing inspection and maintenance services to the 22 turbines at Formosa 1 Phase 1 and Formosa 1 Phase 2 sites, including internal and external inspections and painting. Under the contract, signed with Formosa 1 […]

  • 12 November 2019
    Wind Farm Update

    Ørsted and project partners have held an inauguration ceremony for the Formosa 1 Phase 2 offshore wind project in Taiwan. Formosa 1 Phase 2 is an extension of the existing two-turbine Formosa 1 Phase 1 project, which was officially commissioned in April 2017. The 120MW project comprises 20 Siemens Gamesa 6MW turbines installed approximately 2 […]

  • 8 September 2023
    Wind Farm Update

    The Formosa 2 offshore wind farm has officially entered commercial operation, becoming the first Round 2 offshore wind project in Taiwan to achieve commercial operation date (COD). This project, owned by JERA, Green Investment Group (supported by its portfolio company Corio Generation) and Synera Renewable Energy (SRE), has entered the operations & maintenance (O&M) phase […]

  • 7 January 2020
    Wind Farm Update

    The Formosa 1 offshore wind project in Taiwan started commercial operation on 27 December, according to JERA. The 128MW wind farm consists of the 8MW Formosa 1 Phase 1, inaugurated in May 2017, and the 120MW Formosa 1 Phase 2 which was officially commissioned in November. Formosa 1 comprises two Siemens Gamesa 4MW turbines from the first phase […]

  • 30 June 2022
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Japanese utility JERA and Corio Generation, the new specialist offshore wind business of Macquarie’s Green Investment Group (GIG), announced on 30 June that they were ready to bid for the third phase of Taiwan’s offshore wind zonal development with their Formosa 3 project. JERA and Corio (GIG at the time) have already partnered in Taiwan […]

  • 17 June 2019
    Contracts & Tenders

    Jan De Nul has secured the engineering, procurement, construction and installation contract (EPCI) for foundations and subsea cables at the Formosa 2 offshore wind project in Taiwan. Jan De Nul Group is responsible for the design, fabrication and installation of the jacket foundations, as well as for the design, supply and installation of subsea cables […]

  • 12 December 2018
    Authorities, Business & Finance, Wind Farm Update

    Swancor has signed a power purchase agreement (PPA) with Taipower for the Formosa 2 offshore wind farm.

  • 22 September 2020
    Business & Finance, Wind Farm Update

    Swancor Renewable Energy has revealed plans to develop the 4.4 GW Formosa 4 offshore wind project off the Miaoli County in Taiwan. The portfolio would consist of three sites, including Formosa 4-1, Formosa 4-2 and Formosa 4-3, which would cover a large maritime area located 18 to 20km offshore. Swancor Renewable Energy said it had […]

  • 29 October 2019
    Wind Farm Update

    Taiwan’s Formosa 2 offshore wind farm has reached financial close, Macquarie’s Green Investment Group (GIG) said. Formosa 2 has been jointly developed by Macquarie Capital (75%) and Swancor Renewable Energy (25%). GIG will now play a role in delivering the project through its construction phase. The 376MW offshore wind project located off the coast of Miaoli […]

  • 29 November 2019
    Business & Finance

    SeaPlanner, SeaRoc Group’s marine management system, has been selected to support the operations and maintenance phase of the Formosa 1 offshore wind farm in Taiwan. Under the 10-year contract, SeaPlanner will be deployed by the O&M team to coordinate all personnel and marine logistics for the 128MW wind farm. SeaPlanner also supported the construction of […]

  • 20 May 2019
    Operations & Maintenance, Vessels

    The construction of a Service Accommodation Transfer Vessel (SATV) and a Crew Transfer Vessel (CTV) which will service the Formosa 1 wind farm in Taiwan is well underway, BMT, the designer of the vessels, said. BMT has partnered with the Singapore-based Penguin Shipyard International (PSI) for the 36m SATV and the 26m CTV. The keel […]

  • 3 March 2020
    Vessels

    Penguin International Ltd. has delivered the service accommodation and transfer vessel (SATV) for the Formosa 1 offshore wind project to a Taiwanese operator. The 35m SATV Ventus Formosa was built by the Penguin Shipyard in Singapore and designed by the UK BMT. According to Penguin, the prototype vessel is purpose-built for 12 technicians to live […]

  • 23 April 2020
    Operations & Maintenance, Vessels

    Siemens Gamesa has inaugurated the world’s first Service Accommodation Transfer Vessel (SATV) in Taiwan. The 35-metre Ventus Formosa will operate from Taichung. The vessel will support Siemens Gamesa’s full service agreement for the Formosa 1 offshore wind project. Penguin International built the SATV at its shipyard in Singapore and delivered it at the beginning of […]

  • 6 July 2021
    Business & Finance, Wind Farm Update

    Swancor Renewable Energy (SRE) has partnered with Tien Li Offshore Wind Technology, Yeong Guan Energy, and J&V Energy Technology to establish a consortium named ‘Taiwan Team’, which will develop two wind farms off the Taiwanese coast: one with turbines installed on bottom-fixed foundations and one using floating wind technology. The Taiwan Team will focus on […]

  • 3 October 2019
    Business & Finance

    The European Commission has approved the acquisition of joint control by JERA, Macquarie and Swancor over the Formosa 2 offshore wind project in Taiwan. The 376MW Formosa 2 offshore wind project is currently owned by Macquarie and Swancor. The Commission concluded that the proposed acquisition would raise no competition concerns as Formosa 2 has no activity within the European Economic […]