1409 results found for 'hai long 2'

1409 results found for 'hai long 2'
Order results by

A list of search results

  • 19 November 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    CSBC-DEME Wind Engineering (CDWE) has completed the first offshore installation campaign for the Hai Long offshore wind project in Taiwan, with all jacket foundations installed at Hai Long 2. The overall project includes two offshore wind farms, namely the 518 MW Hai Long 2 and the 504 MW Hai Long 3. Hai Long 2 is […]

  • 19 August 2024
    Fixed-Bottom, Foundations, Project Updates, Wind Farm Update

    The three-phased Hai Long offshore wind farm in Taiwan has reached several key offshore construction milestones over the past few months, including the installation of the jacket foundation for the offshore substation at Hai Long 3. There are now also 108 pin piles installed at 36 wind turbine locations, out of a total of 73 […]

  • 10 September 2024
    Fixed-Bottom, Grid Connection, Onshore Infrastructure, Project Updates, Supply Chain, Wind Farm Update

    Two people who remained hospitalised after the first person was pronounced dead following the CO2 leak at the Hai Long onshore substation in Taiwan have also passed away, a Hai Long Offshore Wind spokesperson confirmed to offshoreWIND.biz. On 20 August, several on-site workers at the Hai Long Changhua onshore substation, part of the 1,022 MW […]

  • 27 August 2024
    Fixed-Bottom, Foundations, Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    This article was updated at 10:15 CET on 28 August 2024 after a response from Hai Long Offshore Wind. The CO2 leak that hospitalised 17 people working at the Hai Long onshore substation site in Changhua, Taiwan, on 20 August has claimed at least one life. On 27 August, the Hai Long Offshore Wind consortium […]

  • 20 May 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The first offshore substation (OSS) topside has been installed at the Hai Long offshore wind farm by CSBC-DEME Wind Engineering’s (CDWE) Green Jade vessel in Taiwan. The 1,022 MW Hai Long comprises two offshore wind farms, the 532 MW Hai Long 2 and the 512 MW Hai Long 3 and is being developed in three phases as […]

  • 8 May 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The jacket foundation for the Hai Long 2 offshore substation has been installed by CSBC-DEME Wind Engineering’s (CDWE) Green Jade vessel in Taiwan. Hai Long comprises two offshore wind farms, the 532 MW Hai Long 2 and the 512 MW Hai Long 3 and is being developed in three phases as Hai Long 2 is […]

  • 24 April 2024
    Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The first of two offshore substations built for the Hai Long 2 and Hai Long 3 offshore wind projects has set sail from Vung Tau, Vietnam, and is en route to the Taiwan Strait. A consortium comprising Semco Maritime and PTSC Mechanical & Construction (PTSC M&C) is responsible for delivering the two offshore substations for […]

  • 9 October 2024
    Business & Finance, Grid Connection

    Energy and marine consultancy company, ABL, has been appointed as marine warranty surveyor (MWS) to support the marine transportation and installation (T&I) operations for the Centre Manche 1 and Centre Manche 2 offshore substations in France. Centre Manche 1 and Centre Manche 2 are part of two offshore wind projects – Appel d’Offre 4 (AO4) […]

  • 5 June 2024
    Business & Finance, Business development, Cables, Grid Connection, Infrastructure, Outlook & Strategy

    South Korean Taihan Cable & Solution has opened the first phase of its submarine cable plant that will supply the offshore wind industry. The submarine cable plant, covering around 44,800 square metres behind Godae Pier at Pyeongtaek’s Dangjin Port, is being constructed in two phases. The first phase, which focuses on producing inter-array cables, was […]

  • 22 August 2024
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    Polenergia and Equinor have received offshore and onshore construction permits for the Bałtyk 2 and Bałtyk 3 offshore wind farms the two companies will build together in Poland. The two projects, set to be built in the Polish sector of the Baltic Sea, approximately 37 and 22 kilometres from the coastline near Ustka and Łeba, […]

  • 12 April 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    Offshore construction has started at the Hai Long offshore wind farm site in Taiwan with the vessel Green Jade installing pin piles for the project’s jacket foundations. The Hai Long Offshore Wind Project joint venture (Northland Power, Yushan Energy, Mitsui & Co., and Gentari) announced the official start of offshore construction on 11 April. The […]

  • 27 September 2024
    Contracts & Tenders, Grid Connection, Offshore Platforms, Supply Chain

    SeaRenergy has been awarded a multi-year contract by Siemens Energy to provide offshore infrastructure services for a minimum of thirteen converter platforms – nine in the German Bight, starting with BorWin5, and four in the UK sector of the North Sea. The scope of work covers integrated onshore and offshore logistic and support services, which […]

  • 12 September 2024
    Grid Connection, Offshore Platforms

    A consortium of GE Vernova and Seatrium has held a steel-cutting ceremony to mark the start of construction work on TenneT’s IJmuiden Ver Beta offshore converter platform, one of the first Dutch 2 GW grid connection projects. The first steel was cut at Seatrium’s Tuas Boulevard shipyard in Singapore. The high voltage direct current (HVDC) […]

  • 16 August 2024
    Authorities, Business & Finance, Fixed-Bottom, Planning & Permitting, Project Updates

    The New Jersey Board of Public Utilities (BPU) has granted a motion submitted by Ørsted on 1 July, requesting the BPU vacate the orders issued for the two Ocean Wind projects offshore New Jersey after the developer cancelled the projects last year. On 14 August, the BPU accepted Ørsted’s motions to vacate the BPU order […]

  • 23 July 2024
    Business & Finance, Vessels

    Norway’s Vard has signed a contract with its compatriot Rem Offshore to design and construct another commissioning service operation vessel (CSOV). The VARD 4 19 design CSOV, developed by Vard Design in Ålesund, will be the third vessel Vard delivers to Rem Offshore. The first two, REM Power and REM Wind, were delivered in 2023 […]

  • 7 November 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Vårgrønn has agreed to acquire a 27.4 per cent stake in the 288 MW Baltic 2 offshore wind farm from PGGM Infrastructure Fund, marking its entry into the German market. Following the deal closing, Vårgrønn and EnBW will own 27.4 per cent and 50.1 per cent, respectively, with EnBW responsible for operations and maintenance activities. […]

  • 26 September 2024
    Contracts & Tenders, Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    RWE has awarded two contracts to Lamprell Energy Limited for the future supply of transition pieces to its two east coast UK offshore wind projects currently under development, Norfolk Vanguard West and Norfolk Vanguard East. RWE and Lamprell marked the signing of the contract with a small event at the WindEnergy Hamburg 2024 conference. The […]

  • 2 August 2024
    Authorities, Business development, Contracts & Tenders, Planning & Permitting, Research & Development, Supply Chain

    The Netherlands Enterprise Agency (RVO) has awarded Fugro and Ocean Infinity AB contracts to carry out geotechnical investigations at the Doordewind zone, one of the three new areas designated by the Dutch Government in 2022 to increase offshore wind capacity. RVO launched the tender for offshore geotechnical investigations at the Investigation Area in the Doordewind […]

  • 5 August 2024
    Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update

    PGE Group has contracted Polish company Energoprojekt-Katowice to prepare a conceptual design for the Baltica 1 offshore wind farm. The 900 MW Baltica 1 is the third project in PGE’s Baltica Offshore Wind Farm portfolio. The first two, Baltica 2 and Baltica 3, are being developed by PGE and Ørsted and are in an advanced development […]

  • 26 August 2024
    Business & Finance, Fixed-Bottom

    Denmark-headquartered Ramboll has signed a multi-year agreement with PGE Baltica to provide wide-ranging technical advisory services to the company’s 7+ GW offshore wind farm portfolio in the Baltic Sea. Ramboll’s support will cover every aspect of offshore wind farm progression, ensuring technical robustness, financial efficiency, and secure operation throughout the lifecycle of the projects, the […]

  • 30 October 2024
    Business & Finance, Project Updates, Wind Farm Update

    Global investment firm Brookfield has bought minority stakes in four UK offshore wind farms owned and operated by Ørsted for around GBP 1.75 billion (approximately EUR 2.1 billion). The buy-in, which Brookfield is pursuing through Brookfield Infrastructure Fund V, will see the investment firm acquiring 12.45 per cent in Hornsea 1, Hornsea 2, Walney Extension, […]

  • 29 August 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    Vattenfall has signed a long-term electricity supply contract with the steel producer Salzgitter for 75 MW of electricity to come from the Nordlicht 1 offshore wind farm in the German North Sea. With this power purchase agreement (PPA), Salzgitter secures the supply of green electricity for 15 years from the 980 MW offshore wind farm […]

  • 6 August 2024
    Authorities, Planning & Permitting

    Azerbaijan will soon start wind measurement campaigns to assess offshore wind resources at two locations, according to a recent update from the Azerbaijan Renewable Energy Agency (AREA), part of the country’s Ministry of Energy. In a press release on 2 August, AREA said that work on starting measurements was about to be completed, with two […]

  • 10 September 2024
    Authorities, Contracts & Tenders, Planning & Permitting, Supply Chain

    The European Investment Bank (EIB) has issued a tender notice for technical assistance to conduct a feasibility study in an area off Morocco’s Atlantic coast for the country’s first offshore wind project. According to the Moroccan Agency for Sustainable Energy (MASEN), studies have shown that the country has a high potential to exploit offshore wind, […]

  • 30 October 2024
    Business & Finance, Cables, Contracts & Tenders, Grid Connection, Supply Chain

    Ørsted has awarded Seaway7, part of the Subsea7 Group, a contract for the transport and installation (T&I) of the inter-array cables at the Hornsea 3 offshore wind project in the UK. Seaway7’s scope of work covers the transportation and installation of 192 66 kV inter-array cables, measuring approximately 500 kilometres in length, with offshore activities […]

  • 23 July 2024
    Authorities, Floating Wind, Planning & Permitting

    The California Public Utilities Commission (CPUC) has issued a proposed decision that could see the US state running three offshore wind solicitations to procure up to 7.6 GW of installed capacity. The first projects under the proposed procurement timeline would be in operation by 1 June 2035. The proposed decision, issued on 19 July, is […]