382 results found for 'haliade-x'

382 results found for 'haliade-x'
Order results by

A list of search results

  • 26 July 2024
    Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    More than a quarter of wind turbines at Dogger Bank A, the first phase of the UK’s 3.6 GW Dogger Bank Wind Farm, have been installed. So far, 27 of the 95 GE Haliade-X 13 MW wind turbines that Dogger Bank A will comprise are in place, according to information in Equinor’s results for the […]

  • 5 July 2024
    Business development, Industry, R&D, Research & Development, Technology

    The US-headquartered GE Vernova plans to install a prototype of its next-generation 15.5 MW Haliade-X offshore wind turbine in Gulen, Norway, following a NOK 331 million (approximately EUR 29 million) funding approval from Enova, a government-backed agency. The funds from Enova have been secured by Wergeland Group and Georgine Wind, which is owned by GE […]

  • 17 May 2024
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Dutch offshore wind foundation manufacturer, Sif, has started the production of monopile foundations for the third phase of the Dogger Bank Wind Farm in the UK, the world’s biggest offshore wind farm under construction. According to a trading update Sif issued on 17 May, the company — which is delivering foundations for all three phases […]

  • 27 March 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update, Wind Turbines

    The jack-up vessel Voltaire has installed twelve wind turbines at the Dogger Bank A offshore wind farm in the UK so far and is currently in Vlissingen, the Netherlands, where it will undergo scheduled maintenance and return to the UK project in May. This is according to a Notice of Operations from the project issued […]

  • 26 June 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The Vineyard Wind 1 project is now delivering more than 136 MW to the electric grid in Massachusetts, making it the largest operating offshore wind project in the US. Vineyard Wind 1, the first large-scale offshore wind project in the US, now has ten turbines in operation totalling approximately 136 MW, enough to power 64,000 […]

  • 9 April 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    The installation of the offshore substation topside and monopile foundations is about to commence at Dogger Bank B offshore wind farm, the second of the three 1.2 GW phases of the 3.6 GW Dogger Bank Wind Farm in the UK. Installation vessels Saipem 7000 and Seaway Strashnov are expected to arrive at the project site […]

  • 14 May 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Seaway7’s vessels, Seaway Strashnov and Seaway Alfa Lift, have commenced the installation of monopile foundations and transition pieces (TPs) for Dogger Bank B, the second phase of the 3.6 GW Dogger Bank Wind Farm in the UK, which is set to become the world’s largest offshore wind farm once in operation. The monopiles and TPs, […]

  • 14 August 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    RWE plans to participate in one of the upcoming offshore wind solicitations in New York with its 1,314 MW Community Offshore Wind project, one of the three cancelled earlier this year as GE Vernova dropped plans for the 18 MW Haliade-X wind turbine which was planned to be used in the projects. Community Offshore Wind […]

  • 25 July 2024
    Business & Finance, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The breakage of the blade on one of GE Vernova’s Haliade-X wind turbines at the Vineyard Wind 1 offshore wind farm in the US was caused by a manufacturing deviation, the company’s CEO Scott Strazik revealed during an earnings call on 24 July. Strazik also pointed out that a blade event that happened on a […]

  • 30 July 2024
    Cables, Grid Connection

    Tekmar Group has completed its role in the Dogger Bank A offshore wind farm by supplying essential cable protection systems (CPS) for the project’s inter-array cables. This month, Dogger Bank A, the first phase of the UK’s 3.6 GW Dogger Bank Wind Farm, achieved a significant milestone with the installation of all inter-array cables at […]

  • 17 April 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Vessels, Wind Farm Update

    Saipem, using its vessel Saipem 7000, has completed the installation of the offshore substation (OSS) at Dogger Bank B, the second phase of the 3.6 GW Dogger Bank Wind Farm in the UK, which is set to become the world’s largest offshore wind farm once in operation. Saipem 7000 arrived this month at the Dogger Bank […]

  • 23 August 2024
    Fixed-Bottom, Manufacturing, Supply Chain, Wind Farm Update, Wind Turbines

    This article was updated at 15:05 CET on 23 August 2024 with a statement from GE Vernova. One of the already installed wind turbine blades at Dogger Bank A offshore wind farm, currently under construction in the UK, has sustained damage and failed. The blade failure occurred on the morning of 22 August and, according […]

  • 29 May 2024
    Authorities, Business & Finance, Planning & Permitting

    Danish renewable energy developer Ørsted will pay New Jersey USD 125 million (approximately EUR 115 million) to settle claims over the company’s cancellation of two offshore wind farm projects, Ocean Wind 1 and Ocean Wind 2, last year. The state’s Board of Public Utilities (BPU) said the USD 125 million it will receive will be […]

  • 30 April 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The installation of transition pieces (TPs) is about to commence at Vineyard Wind 1, America’s first large-scale offshore wind farm. Beginning next month, DEME Group’s jack-up vessel Sea Challenger will begin placing TPs at 17 monopile locations in lease area OCS-A 0501. The campaign will continue through June 2024. The units are being manufactured by […]

  • 14 August 2024
    Authorities, Fixed-Bottom, Project Updates, Wind Farm Update

    The US Bureau of Safety and Environmental Enforcement (BSEE) has allowed Vineyard Wind to resume certain limited additional activities at the Vineyard Wind 1 offshore wind farm site. These include the installation of towers and nacelles but not (yet) the installation of the wind turbine blades. BSEE issued an update to the Suspension Order the […]

  • 2 September 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The blade failure event at the Dogger Bank A offshore wind farm last month was not caused by an installation or manufacturing issue but happened during the commissioning process, according to an analysis conducted by GE Vernova. The blade failure occurred on the morning of 22 August and, according to an update from the Dogger […]

  • 1 August 2024
    Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Windar Renovables has manufactured and loaded the final batch of transition pieces (TPs) for the 806 MW Vineyard Wind 1 offshore wind farm in the United States. In 2019, Windar Renovables won a contract to manufacture, certify, assemble, inspect, store, and deliver TPs for the offshore wind project, being developed by Vineyard Wind, a joint […]

  • 16 July 2024
    Project Updates, Wind Farm Update

    NOTE: The article was updated on 19 July with more information about the GE Vernova turbine blade incident at the Vineyard Wind project.  A turbine blade at the Vineyard Wind 1 offshore wind farm in the US has been damaged, leading to an investigation by the blade’s manufacturer, GE Vernova. Vineyard Wind, a joint venture […]

  • 22 April 2024
    Authorities, Planning & Permitting, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The New York State Energy Research and Development Authority (NYSERDA) has cancelled three offshore wind projects with a combined capacity of over 4 GW due to ”technical and commercial complexities between provisional awardees and their partners”. In October 2023, NYSERDA provisionally awarded three offshore wind projects, subject to the successful conclusion of contract negotiations. These […]

  • 17 July 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Following a blade damage incident that took place on 13 July at its 800 MW offshore wind project in Massachusetts, Vineyard Wind has revealed that it is mobilising debris recovery teams on Nantucket. Vineyard Wind, a joint venture between Iberdrola’s US subsidiary Avangrid and Denmark’s Copenhagen Infrastructure Partners (CIP), announced on 16 July that it […]

  • 5 September 2024
    Business & Finance, Business development, Fixed-Bottom, Project Updates, Research & Development, Wind Farm Update

    Invenergy Wind Offshore (Invenergy) has requested a delay from the New Jersey Board of Public Utilities (NJBPU) until late December for its proposed 2.4 GW offshore wind project near Long Beach Island. In a July filing with the board, the company, which is developing the wind farm together with energyRe, cited challenges in finding a […]

  • 24 July 2024
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Delivery partners have completed the installation of over 328 kilometres of 66 kV inter-array cables for Dogger Bank A, the first phase of the UK’s Dogger Bank Wind Farm, marking the completion of all inter-array cable work for this phase. The 66 kV XLPE-insulated inter-array cables were manufactured by Hellenic Cables under a contract with […]

  • 18 July 2024
    Project Updates, Wind Farm Update

    The US Bureau of Safety and Environmental Enforcement (BSEE) has issued an order instructing Vineyard Wind to halt electricity production from all wind turbines following a blade failure incident on 13 July. The 800 MW Vineyard Wind offshore wind farm is planned to feature 62 GE Vernova’s Haliade-X 13 MW wind turbines, each with a […]

  • 23 February 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Vineyard Wind 1, America’s first large-scale offshore wind farm, has begun delivering energy to the New England grid from five of its planned 62 GE Haliade-X 13 MW wind turbines. The units are currently generating 68 MW of energy, enough to power 30,000 homes in Massachusetts, according to the developers of the project, Avangrid and […]

  • 13 August 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Vineyard Wind and GE Vernova have set out an action plan covering several main tasks following the blade incident at Vineyard Wind 1 offshore wind farm. The plan includes removing the remainder of the damaged blade on the turbine AW-38, continuing the collection of any debris, and resuming turbine installation and operations. The blade incident […]

  • 24 June 2024
    Business & Finance, Business development, Collaboration, Contracts & Tenders, Fixed-Bottom, Outlook & Strategy, Supply Chain

    OX2 and Varberg Energi have agreed in principle for Varberg Energi to procure renewable electricity from the Galene offshore wind farm located near Varberg, Sweden, as well as from OX2’s solar project in the vicinity. The long-term goal of the agreement is for the companies to enter into a Power Purchase Agreement (PPA) for the […]