122 results found for 'hollandse kust alpha'

122 results found for 'hollandse kust alpha'
Order results by

A list of search results

  • 18 October 2024
    Cables, Contracts & Tenders, Grid Connection, Operations & Maintenance, Supply Chain

    Dutch offshore transmission system operator (TSO) TenneT has opened an application period for a EUR 3 million tender for surveys of cables installed in the Dutch sector of the North Sea. Work will start in 2025 and will be performed on the export cables at the Borssele and the Hollandse Kust offshore wind farm zones […]

  • 21 June 2024
    Cables, Grid Connection

    Boskalis’ cable-laying vessel Giant 7 has commenced with the installation of the second and final nearshore export cable for TenneT’s 700 MW Hollandse Kust (west Beta) project in the Netherlands. Following the successful installation of the first cable by Boskalis’ Giant 7 barge, work on the second cable is now in progress. Boskalis’ cable-laying vessel, […]

  • 2 August 2024
    Cables, Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    Boskalis, an offshore construction company, has completed the connection of all export cables and platforms for the offshore wind farm being developed by RWE in the Dutch North Sea. Off the coast of the Netherlands, Boskalis connected all the export cables the company recently installed for the shore connection that TenneT is providing for RWE’s […]

  • 20 May 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The jacket foundation for the Hollandse Kust West Beta substation has left the Smulders yard in Vlissingen, the Netherlands, and is now being transported to the offshore wind farm site, approximately 53 kilometres off the coast of Egmond aan Zee. On 16 May, the 49-metres-high jacket left the yard in Vlissingen, after Smulders completed the […]

  • 21 May 2024
    Cables, Grid Connection, Offshore Platforms

    The first of two export cables for TenneT’s Hollandse Kust (west Beta) offshore grid connection has been pulled underneath the dunes at Velsen, the Netherlands. In the coming days, the consortium between Boskalis and Orient Cable will bury this 220 kV AC cable into the seabed. Boskalis’ cable-laying vessel Giant 7 will be utilized for […]

  • 12 June 2024
    Fixed-Bottom, Green Hydrogen, Power-to-X, Project Updates, Wind Farm Update

    The joint venture between Vattenfall and Copenhagen Infrastructure Partners (CIP), which has been awarded the 2 GW IJmuiden Ver Beta offshore wind area in the Netherlands, will also build a floating solar farm within the offshore project site and install a large-scale electrolyser in the Port of Rotterdam to use the electricity generated at IJmuiden […]

  • 25 October 2024
    Business & Finance, Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Supply Chain

    DEME has been awarded a contract to carry out the transport and installation of inter-array cables and secondary steel for the 800 MW OranjeWind offshore wind farm in the Netherlands. Scheduled to start in the second half of 2026, DEME will deploy offshore and cable installation vessels, a hopper dredger and a fallpipe vessel, as […]

  • 8 May 2024
    Foundations, Grid Connection, Offshore Platforms, Project Updates, Supply Chain, Wind Farm Update

    Smulders has completed the loadout of the jacket foundation and the piles for the Hollandse Kust West Beta offshore substation in the Netherlands. On 25 April, the piles, fabricated by the Dutch company Sif, were loaded out in Vlissingen, the Netherlands. With a total weight of 900 tonnes and a length of up to 79 […]

  • 29 April 2024
    Authorities, Planning & Permitting

    The Netherlands’ previous goal to achieve 21 GW of offshore wind capacity by the end of 2031 has been postponed by one year, now targeting achievement by 2032. On 25 April, the office of the Ministry of Economic Affairs and Climate sent a letter to the parliament on the progress of the 2030 Offshore Wind […]

  • 28 March 2024
    Authorities, Business & Finance, Business development, Planning & Permitting, Research & Development

    Vattenfall has decided to enter a bid for the sites, Alpha and Beta, of the 4 GW IJmuiden Ver offshore wind tender in the Netherlands. Located 62 kilometres off the west coast of the Netherlands, the IJmuiden Ver Wind Farm Zone contains three sites, with IJmuiden Ver Gamma, the third site, expected to be put […]

  • 11 January 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The grid connection for Hollandse Kust (west) Alpha is ready for commissioning after receiving the grid readiness certificate three months ahead of schedule. Now that Hollandse Kust (west) Alpha has received the certificate, the wind farm operator Ecowende, a joint venture of Shell and Eneco, can connect the turbines for its 760 MW Hollandse Kust […]

  • 18 February 2021
    Contracts & Tenders, Grid Connection, Wind Farm Update

    DEME Offshore has secured a contract for the transport and installation of substations for the Hollandse Kust Noord and Hollandse Kust West Alpha offshore wind farms in the Netherlands. Under the contract awarded by the joint venture ENGIE Solutions-Iemants, DEME will also supply and install scour protection for the two substations. Installation of the scour […]

  • 7 September 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Offshore grid operator TenneT has selected the Van Oord-Hellenic Cables consortium to connect the Hollandse Kust (South) Alpha and Beta offshore platforms to the Dutch onshore grid.

  • 21 September 2021
    Grid Connection

    Waves Group Ltd has secured the contract to carry out Marine Warranty Surveyor (MWS) services for the installation of TenneT’s Hollandse Kust Noord and West Alpha export power cables.  The agreement will see Waves Group provide MWS services during the installation of the Hollandse Kust Noord and Hollandse Kust West Alpha export cables, with installation […]

  • 6 January 2020
    Contracts & Tenders, Grid Connection

    TenneT has awarded RPS Energy Ltd with a contract to provide unexploded ordnance (UXO) consultancy services covering zones in the Dutch North Sea identified in the Offshore Wind Energy Roadmap 2030. The tender covers six offshore wind zones, the 700MW Hollandse Kust Noord, the 700MW Hollandse Kust (west) Alpha, the 700MW Hollandse Kust (west) Beta, […]

  • 13 November 2019
    Grid Connection

    Dutch transmission system operator TenneT TSO B.V. has issued a tender for offshore unexploded ordnance (UXO) survey, identification and clearance at the zones identified in the Offshore Wind Energy Roadmap 2030. The tender covers the 700MW Hollandse Kust Noord, the 700MW Hollandse Kust (west) Alpha, the 700MW Hollandse Kust (west) Beta, the 700MW Ten noorden […]

  • 18 September 2019
    Contracts & Tenders, Grid Connection

    Dutch transmission system operator TenneT TSO B.V. has issued a tender seeking unexploded ordnance (UXO) consultancy services covering zones in the Dutch North Sea identified in the Offshore Wind Energy Roadmap 2030. As the designated offshore grid operator for the future wind farms, TenneT is responsible for the engineering, procurement, installation, construction, and operation of the […]

  • 28 November 2019
    Contracts & Tenders, Grid Connection

    Van Oord-Cablel Hellenic Cables consortium has awarded First Subsea with a contract to supply a cable protection system (CPS) for the Hollandse Kust (zuid) export cables, and a cross over protection for TenneT’s Net op zee Hollandse Kust (zuid). Under the contract, First Subsea will engineer, test, and supply a CPS for the protection of […]

  • 25 March 2022
    Grid Connection, Vessels, Wind Farm Update

    Boskalis has completed the transport of the Hollandse Kust Zuid (HKZ) Beta substation topside from Dubai to Rotterdam using its semi-submersible heavy transport vessel Mighty Servant 3. The HKZ Beta topside is scheduled to be installed in the Hollandse Kust Zuid wind farm zone in the Dutch North Sea in the coming days. According to […]

  • 21 February 2022
    Grid Connection, Wind Farm Update

    The second offshore transformer station topside for the grid connection of the 1.5 GW Hollandse Kust Zuid offshore wind project has set sail from the Drydocks World Dubai’s fabrication facility in the United Arab Emirates. In charge of the weighing, transport and load-out of the 700 MW, 3,950-tonne Hollandse Kust Zuid Beta topside is the […]

  • 20 September 2019
    Contracts & Tenders

    TenneT TSO has issued a tender seeking non-UXO offshore route survey services covering zones in the Dutch North Sea identified in the Offshore Wind Energy Roadmap 2030. The tender covers the 700MW Hollandse Kust (west) Beta, the 700MW Ten noorden van de Waddeneilanden, the 2GW IJmuiden Ver Alpha, and the 2GW IJmuiden Ver Beta offshore wind farm zones. […]

  • 12 January 2022
    Contracts & Tenders

    Energy logistics provider Peterson is supporting the offshore installation of the two 700 MW transformer platforms for TenneT’s Hollandse Kust Zuid (HKZ) offshore grid connection under a logistics contract with Petrofac. HKZ Alpha, the first of the two offshore substations that will connect Vattenfall’s 1.5 GW Hollandse Kust Zuid offshore wind farm to the Dutch grid, was installed […]

  • 31 January 2022
    Authorities, Vessels

    A rudderless cargo ship is drifting around the Hollandse Kust Zuid offshore wind farm in the Dutch North Sea following a collision with an oil and chemicals tanker in heavy seas in the anchorage area near IJmuiden on Monday, 31 January, the Dutch Coastguard said. In one of its most recent updates on the incident, […]

  • 28 January 2019
    Authorities, Environment, Grid Connection

    The Netherlands commission for environmental assessment has issued a positive recommendation on the Environmental Impact Report of the Hollandse Kust (noord) and the Hollandse Kust (west Alpha) grid connections. Pondera Consult, together with Arcadis, provided the EIR and the necessary studies. The Hollandse Kust (noord) wind farm will be located about 18.5 kilometers offshore. The Hollandse […]

  • 24 March 2022
    Grid Connection, Wind Farm Update

    The installation of the Hollandse Kust Zuid Beta offshore substation topside will not be affected by the damage the substation’s jacket foundation suffered in a recent collision with a cargo ship, TenneT said. As reported, the cargo ship Julietta D collided with the substation jacket and a turbine foundation at the Hollandse Kust Zuid wind […]

  • 25 September 2020
    Grid Connection

    The joint venture between ENGIE Solutions and Iemants, a subsidiary of Smulders, has cut the first steel for the topside of the offshore transformer station for the Hollandse Kust Noord wind farm zone in the Netherlands. The joint venture partners, together with TenneT representatives, officially marked the beginning of works at a steel cutting ceremony […]