493 results found for 'hornsea two '

493 results found for 'hornsea two '
Order results by

A list of search results

  • 20 September 2024
    Vessels

    UK-based Tidal Transit has ordered two battery-ready crew transfer vessel (CTV) newbuilds from Singapore’s Penguin Shipyard, designed for the offshore wind sector. The CTVs will be fitted with Volvo Penta IPS30 propulsion – the same as is used in Tidal Transit’s eGinny 100 per cent electric retrofit project – for its fuel efficiency and readiness […]

  • 22 August 2024
    Contracts & Tenders, Foundations, Manufacturing, Supply Chain

    Heerema has commenced the construction of offshore substation jackets for the 2.9 GW Hornsea 3 wind farm in the UK, kicking off with a steel-cutting ceremony. On 20 August, the company held the first steel-cutting ceremony for the jackets at Heerema Vlissingen in the Netherlands. Ørsted, the developer of the Hornsea 3 offshore wind project, […]

  • 30 October 2024
    Business & Finance, Cables, Contracts & Tenders, Grid Connection, Supply Chain

    Ørsted has awarded Seaway7, part of the Subsea7 Group, a contract for the transport and installation (T&I) of the inter-array cables at the Hornsea 3 offshore wind project in the UK. Seaway7’s scope of work covers the transportation and installation of 192 66 kV inter-array cables, measuring approximately 500 kilometres in length, with offshore activities […]

  • 3 September 2024
    Authorities, Planning & Permitting

    Offshore wind developers have been awarded contracts for approximately 5.3 GW of capacity in the UK’s latest Contract for Difference (CfD) Allocation Round 6 (AR6). Ørsted received the largest CfD for offshore wind, securing 2.4 GW for the Hornsea 4 offshore wind project. The offshore wind farms awarded CfDs are the 288 MW Inch Cape […]

  • 30 October 2024
    Business & Finance, Project Updates, Wind Farm Update

    Global investment firm Brookfield has bought minority stakes in four UK offshore wind farms owned and operated by Ørsted for around GBP 1.75 billion (approximately EUR 2.1 billion). The buy-in, which Brookfield is pursuing through Brookfield Infrastructure Fund V, will see the investment firm acquiring 12.45 per cent in Hornsea 1, Hornsea 2, Walney Extension, […]

  • 3 September 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Foundations, Supply Chain

    Sif is in exclusive negotiations for a 140-kilotonne monopile foundation project for an offshore wind farm that was awarded a Contract for Difference (CfD) in the UK’s Allocation Round 6 (AR6), the Dutch company informed following the announcement of the AR6 results. “It is expected that a final contract will be reached before the end […]

  • 19 April 2024
    Authorities, Business & Finance, Planning & Permitting, Project Updates, Wind Farm Update

    The government of Norway has signed a two-way Contract for Difference (CfD) related to the offshore wind farm project in the Sørlige Nordsjø II zone with Ventyr Energi, the winner of the recently held auction. Ventyr Energi, a consortium of Parkwind and Ingka Investments, won the rights to develop the wind farm project at the […]

  • 20 March 2024
    Authorities, Business development, Planning & Permitting, Research & Development

    The Norwegian government has unveiled Ventyr Energi, a consortium of Parkwind and Ingka Investments, as the winner of the Sørlige Nordsjø II (Southern North Sea II) offshore wind auction round in Norway. The winning bid in the auction was NOK 1.15 (EUR 0.099) per kilowatt hour. “This is a milestone in the government’s offshore wind […]

  • 1 March 2024
    Business & Finance, Business development, Fixed-Bottom

    Ørsted has 6.7 GW of offshore wind under construction in 2024 across several projects worldwide, more than ever before in the company’s history, according to a recent newsletter from the global offshore wind developer. The capacity the company has under construction this year is significantly contributed by the Hornsea 3 offshore wind farm in the […]

  • 7 February 2024
    Business & Finance

    World’s leading offshore wind developer Ørsted has reported an operating profit (EBITDA) of DKK 18.7 billion (about EUR 2.5 billion) for 2023 and expects this year’s operating profit to be between DKK 23 billion and DKK 26 billion (approximately EUR 3 billion and EUR 3.4 billion). This is according to Ørsted’s 2023 annual results, which […]

  • 21 February 2024
    Business & Finance, Cables, Grid Connection, Manufacturing, Supply Chain

    Subsea power cable manufacturer NKT has reported a record-high order backlog for high-voltage cables for 2023, with 45 per cent of orders coming from offshore wind. At the end of last year, NKT’s order backlog was at EUR 10.8 billion, more than double the company saw at the end of 2022. In its full-year 2023 […]

  • 26 August 2020
    Grid Connection

    Cable pull-in for the Hornsea Two offshore wind farm’s export line has been completed at the project’s landfall site at Lincolnshire’s Horseshoe Point beach. The operation, carried out by Boskalis’ cable laying vessel Ndurance, involved installing 2.4 kilometres of cable under water and toward the connection point. “Thanks to the dedication of our contracted staff, […]

  • 5 July 2021
    Wind Farm Update

    DEME Offshore has installed the 100th monopile foundation at the 165-turbine Hornsea Two wind farm offshore the UK. DEME installed the first foundation at the site some 89 kilometres north-east of Grimsby in early October 2020. The monopile foundations are being loaded at and transported from the Buss Terminal Eemshaven in the Netherlands and installed at the […]

  • 29 March 2021
    Wind Farm Update

    Sembcorp Marine has contracted Palfinger to provide cranes for the offshore substation and the reactive compensation station to be installed at Ørsted’s 1.4 GW Hornsea Two wind farm offshore the UK. Palfinger will equip the offshore substation with one telescopic crane (DKT400), two davit cranes (PF17000), and the reactive compensation station with one stiff-boom crane […]

  • 3 March 2020
    Contracts & Tenders, Wind Farm Update

    Jumbo Shipping has secured a contract with DEME Offshore for the transport of foundations for the Hornsea Two offshore wind project. Jumbo will transport 165 monopiles from Rostock, Germany, and 135 transition pieces from Aalborg, Denmark, to Eemshaven, the Netherlands, with a K3000 class vessel. Additionally, the company will undertake the project management for the […]

  • 16 April 2020
    Contracts & Tenders, Wind Farm Update

    FairWind has a won a contract by Bladt Industries to install the electrical scope on 135 transition pieces for the Hornsea Two offshore wind project in the UK. FairWind’s scope of work is full electrical installation, including light study design of cable support system, as well as installing all components and free issued items from […]

  • 2 August 2019
    Contracts & Tenders, Wind Farm Update

    Tekmar Energy has signed a contract with Ørsted to provide Cable Protection Systems for the 1.4GW Hornsea Two offshore wind farm. Tekmar will provide their patented Tekmar Cable Protection System (CPS) TekLink® Mechanical Latch for the wind farm, which when constructed will become the world’s largest offshore wind farm. The contract is valued in excess […]

  • 2 October 2020
    Wind Farm Update

    The jacket foundation for the offshore substation at the Hornsea Two offshore wind project in the UK has been installed. The installation of the 4,800-tonne jacket marks the start of the project’s offshore construction. Six weeks ago, 10,000 tonnes of steel framework for the pin piles, reactor compensation and offshore substation jackets sailed from Batam, Indonesia, towards […]

  • 9 October 2020
    Wind Farm Update

    The first out of the total of 165 monopile foundations has been installed at the Hornsea Two offshore wind farm site in the UK, according to social media updates from Ørsted. The milestone comes around a week after the jacket foundation for the wind farm’s offshore substation was installed. DEME’s jack-up vessel Innovation has been […]

  • 17 May 2019
    Contracts & Tenders, Wind Farm Update

    DEME Offshore has won contracts to transport and install foundations and wind turbines on Ørsted’s 1.4GW Hornsea Two offshore wind farm in the UK. The Hornsea Two offshore wind farm is located approximately 89 kilometres off the Yorkshire coast and will comprise 165  Siemens Gamesa 8.4MW wind turbines installed on monopile foundations. DEME Offshore will transport […]

  • 4 March 2021
    Contracts & Tenders, Wind Farm Update

    Manor Renewable Energy (MRE) has signed a major contract with Ørsted to supply power to the Hornsea Two offshore wind project in the UK. MRE will provide the full temporary power solution, service technicians, and both crew transfer and walk-to-work vessels, during the construction phase of the 1.4 GW offshore wind farm. “When the company […]

  • 3 June 2019
    Contracts & Tenders

    Ørsted has contracted Bladt Industries to produce 135 transition pieces for the Hornsea Project Two offshore wind farm in the UK. The fabrication of the transition pieces is planned to begin this year at Bladt’s site in Aalborg, Denmark, with delivery expected to take place from mid-2020 to mid-2021. “We are proud that Ørsted have trusted Bladt Industries as […]

  • 10 September 2021
    Contracts & Tenders, Operations & Maintenance

    Manor Renewable Energy (MRE) has signed a contract to charter a new build crew transfer vessel from WEM Marine LTD to support its work supplying temporary power solution at the 1.4 GW Hornsea Two offshore wind farm. WEM Marine LTD’s vessel, the WEM3, joined MRE on Hornsea Two in July 2021. The WEM3 is a […]

  • 4 January 2021
    Grid Connection, Wind Farm Update

    VolkerInfra has completed the onshore cable installation for the Hornsea Two offshore wind project in the UK. VolkerInfra installed a total of 350 km of cable over 39 km of Lincolnshire land, reaching from the wind farm’s landfall point at Horseshoe Point to North Killingholme. Reinstatement works are expected to continue on the ground until […]

  • 20 November 2019
    Contracts & Tenders

    EEW Group has contracted Hutchinson Engineering Ltd for the fabrication and on-site assembly of Suspended Internal Platforms (SIPs) for the Hornsea Two offshore wind project. The Cheshire-based company is in charge of providing 30 SIPs, each weighing 10t and towering 12m high, that will be suspended inside the transition pieces. In June, Ørsted, the developer […]

  • 17 December 2015
    Authorities, Wind Farm Update

    The UK Planning Inspectorate closed the examination period for the Hornsea Two offshore wind project yesterday. The Examining Authority now has 3 months to consider the project and make a recommendation to the Secretary of State, who will then have further 3 months to make the decision. Hornsea Project Two, located approximately 89km off the Yorkshire coast, will […]