74 results found for 'kaskasi'

74 results found for 'kaskasi'
Order results by

A list of search results

  • 29 October 2024
    Environment, Fixed-Bottom, R&D

    RWE, together with its partners, has launched the Sustainable ecosystem approach in Monitoring the marine environment (SeaMe) project at its Kaskasi offshore wind farm off the German coast. The three-year project will be carried out in collaboration with the Helmholtz Institute for Functional Marine Biodiversity at the University of Oldenburg (HIFMB), the Alfred Wegener Institute […]

  • 3 October 2024
    Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    RWE has unveiled the first 108-metre turbine blade made at the Siemens Gamesa factory in Hull, which will be part of 100 wind turbines to be installed at the 1.4 GW Sofia offshore wind farm in the UK. Each of the 100 wind turbines, rated at 14 MW, will be equipped with 108-metre-long blades that […]

  • 22 October 2024
    Fixed-Bottom, Foundations, Ports & Logistics, Supply Chain

    The first batch of eight monopiles for RWE’s Thor offshore wind project, being built in the Danish North Sea, have been offloaded and stored at the base Port of Eemshaven in the Netherlands. Buss Terminal Eemshaven, part of the Hamburg-based terminal operator Buss Ports, provides storage space, heavy unloading equipment, and operators at the port […]

  • 8 May 2024
    Business & Finance, Grid Connection, Offshore Platforms

    German energy company RWE has signed framework agreements with Hitachi Energy and Aibel for the joint supply of three high-voltage direct current (HVDC) systems for the company’s offshore wind farms. The agreements are long-term as the secured HVDC systems are designated for offshore wind projects from RWE’s global development pipeline, which are planned to be […]

  • 20 March 2024
    Contracts & Tenders, Manufacturing, Supply Chain, Technology, Wind Turbines

    Taiwan-headquartered Swancor has signed a Letter of Intent with Siemens Gamesa to supply recyclable resins for the company’s recyclable wind turbine blades. Starting in 2026, all the resin supplied from Swancor to Siemens Gamesa will be recyclable, as per an update shared on social media by the German company. Siemens Gamesa said that the collaboration […]

  • 14 March 2024
    Business & Finance, Fixed-Bottom

    RWE has reported an adjusted EBITDA of nearly EUR 1.7 billion in its offshore wind segment for 2023, compared to EUR 1.4 billion for the previous fiscal year. The increase in earnings is due to the commissioning of new capacity and better wind conditions, according to the company. Electricity generation from renewable energy at RWE rose by […]

  • 19 February 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update

    RWE has signed six new Power Purchase Agreements (PPAs) with major German industrial customers for the supply of around 1,000 GW/h of green energy per year from its Kaskasi offshore wind farm, starting from 2026. PPAs have been signed between RWE Supply & Trading and DHL Group, Ensinger, Evonik, Infraserv Höchst, thyssenkrupp Steel Europe, and […]

  • 19 February 2024
    Business development, Collaboration, Floating Wind, Outlook & Strategy, R&D, Research & Development

    A business and academic consortium has kicked off collaboration on the future of floating offshore wind. The TAILWIND project, launched in January 2024, will deliver advanced station-keeping technologies, designed to maintain the position of floating offshore wind farms, according to NKT, which recently joined the consortium. NKT said that the integration of a dynamic cable […]

  • 29 January 2024
    Business & Finance, Project Updates, Wind Farm Update

    German logistics company DHL Group has signed a long-term power purchase agreement (PPA) with RWE Supply & Trading for electricity generated at the 342 MW Kaskasi offshore wind farm, located in the German North Sea. Under the ten-year agreement, DHL will be offtaking around 104 GWh of electricity produced by Kaskasi per year, starting in […]

  • 30 November 2020
    R&D, Technology, Wind Farm Update

    German energy company RWE will introduce the so-called ‘collared monopiles’ on the Kaskasi offshore wind farm in the German North Sea. Designed based on an RWE patent, the collars will be installed around three monopile foundations at seabed level. According to RWE, the new foundation technology will provide additional support for lateral loading, increase the […]

  • 27 May 2022
    Environment, R&D, Technology, Wind Farm Update

    Siemens Gamesa is currently producing the first recyclable blades to be installed on an offshore wind farm at its factory in Hull, the UK. The wind turbine manufacturer described the RecycleBlade as the world’s first wind turbine blade ready for commercial use offshore that can be recycled at the end of its lifecycle. The RecyclableBlade […]

  • 27 April 2018
    Authorities, Business & Finance, Contracts & Tenders, Wind Farm Update

    Germany’s Bundesnetzagentur has awarded innogy SE with the rights to build and operate the 325MW Kaskasi offshore wind farm in the German North Sea.

  • 28 March 2022
    Contracts & Tenders, Vessels, Wind Farm Update

    The 1,400-tonne offshore substation topside has been installed on its monopile foundation at the 342 MW Kaskasi offshore wind farm in the German North Sea, RWE, the owner and developer of the project, said. The topside was installed by the heavy lift, DP 2 installation vessel Gulliver, operated by DEME’s subsidiary Scaldis Salvage & Marine […]

  • 22 November 2022
    Wind Farm Update

    The last of the total of 38 wind turbines at RWE’s Kaskasi offshore wind farm in Germany has been installed and more than two thirds of the turbines are now feeding electricity into the grid. Kaskasi is expected to be operational by the end of the year, as of when the 342 MW offshore wind […]

  • 15 June 2021
    Grid Connection, Wind Farm Update

    A 1,400-ton Kaskasi offshore substation topside has arrived from Poland to Bladt Industry’s site in Aalborg, Denmark for further outfitting with the electrical equipment. Energomontaż-Północ Gdynia (EPG) shipped out the topside from the Port of Gdynia on 1 June. The unit arrived in Aalborg last week, Bladt Industries said. RWE’s Kaskasi offshore wind farm, also […]

  • 18 December 2020
    Authorities, Wind Farm Update

    German Federal Maritime and Hydrographic Agency (BSH) has granted planning permission for the 342 MW Kaskasi offshore wind farm (officially known as Kaskasi II). Kaskasi II is the first offshore wind farm in Germany to receive planning permission under the new offshore wind law (WindSeeG), following participation in the auction held under the so-called interim […]

  • 9 February 2021
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Tekmar Energy Limited has secured a contract award to supply its TekLink® Cable Protection Systems (CPS) for the Kaskasi offshore wind farm in Germany. Owned and developed by RWE, the Kaskasi offshore wind farm is a 342 MW wind project located in the German North Sea. Construction work will start in the third quarter of […]

  • 14 July 2022
    Grid Connection, Wind Farm Update

    TenneT has connected RWE’s Kaskasi II offshore wind farm to the HelWin Beta platfrom, the heart of the HelWin2 high-voltage direct current (HVDC) offshore grid connection in the German North Sea. Kaskasi II, located 35 kilometres north of the island of Heligoland, is currently under construction with the wind turbine installation work to commence soon. […]

  • 8 June 2022
    R&D, Technology, Wind Farm Update

    For the first time ever in the renewables industry, special collars were installed around the monopile foundation at the seabed level on RWE’s Kaskasi wind farm offshore Germany. The ‘collared monopile’ is a design based on a RWE patent. The new technology is expected to provide additional support for lateral loading, increase the bearing capacity […]

  • 5 April 2023
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Lidl and Kaufland, the retail divisions of the German Schwarz Group, have signed a long-term power purchase agreement (PPA) with RWE Supply & Trading for the Kaskasi offshore wind farm, located in the German North Sea. Under the ten-year agreement, Lidl and Kaufland will be offtaking approximately 250 GWh of renewable electricity produced by Kaskasi […]

  • 10 April 2020
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Dutch cable manufacturer Twentsche Kabel Fabriek (TKF) has revealed further details about the company’s scope of work on the 342 MW Kaskasi offshore wind project. As reported earlier, Seaway 7 awarded TKF with a contract to deliver 33 kV inter-array cables for the wind farm. Under the contract, TKF will manufacture and deliver 52 kilometres […]

  • 3 March 2021
    Contracts & Tenders, Wind Farm Update

    Dutch cable manufacturer Twentsche Kabel Fabriek (TKF) has awarded Vos Prodect Innovations with a contract to deliver Cable Hang-Off Systems for the Kaskasi offshore wind farm in the German North Sea. VPI’s Cable Hang-Off System (HOS) will be used in the installation of 38 Siemens Gamesa SG 8.0-167 DD Flex offshore wind turbines on the […]

  • 6 May 2021
    R&D, Technology, Wind Farm Update

    RWE Renewables, itap, BioConsult SH, the University of Stuttgart, and Technische Universität Berlin are to research an innovative vibratory pile driving technique at RWE’s Kaskasi offshore wind farm. The new method for installing foundations is said to have the potential to significantly reduce underwater noise emissions and installation times. The research project is funded by […]

  • 28 April 2022
    Wind Farm Update

    Seaway 7 has installed all of the monopile foundations within its scope of work for the Kaskasi offshore wind farm and DEME Offshore just announced that its part of the project is progressing and that 22 monopiles are now installed at the 38-turbine offshore wind farm. “Seaway Strashnov completed the monopile installation on the Kaskasi […]

  • 14 February 2020
    Contracts & Tenders, Grid Connection

    TenneT has issued a call for tenders for the turnkey construction of two AC grid connection systems to connect the 342MW Kaskasi II and the 242MW Gode Wind 3 wind farms in the German North Sea to the associated HVDC sea stations. The scope comprises all works, from design, to manufacturing, delivery, and installation, up […]

  • 12 August 2020
    Contracts & Tenders

    Bladt Industries has selected Energomontaż-Północ Gdynia (EPG) as a subcontractor for the prefabrication of the offshore substation topside and sea fastening for the Kaskasi offshore wind project in Germany. The Polish company started the production of steel structure in July in Gdynia. Bladt is in charge of the construction of the offshore substation, including the […]