20 results found for 'seagreen 1A'

20 results found for 'seagreen 1A'
Order results by

A list of search results

  • 27 March 2024
    Business & Finance, Contracts & Tenders, Operations & Maintenance, Supply Chain

    UK-based Ventus Energy has been awarded a contract by SSE Renewables to provide maintenance work on transmission assets for the Seagreen offshore wind farm in Scotland. Throughout the duration of the contract, the company will operate across primary and secondary equipment at the wind farm’s offshore and onshore substations. In addition to substation asset maintenance, […]

  • 12 March 2024
    Business development, Fixed-Bottom, Project Updates, Research & Development, Wind Farm Update

    The first geotechnical seabed surveys for TotalEnergies and SSE Renewables’ 500 MW Seagreen 1A offshore wind farm in Scotland have been completed. Phase two of the geotechnical works is expected to commence later this year and should take around two weeks to complete. Seagreen 1A lies adjacent to the existing 1,075 MW Seagreen project and […]

  • 18 March 2021
    Authorities, Wind Farm Update

    Seagreen 1A Limited has submitted applications to Scottish authorities for onshore and offshore works related to the Seagreen 1A offshore wind project. The applications were sent to East Lothian Council for onshore works and Marine Scotland for offshore works. The applications for Seagreen 1A have been lodged following online consultation, in line with Scottish Government […]

  • 19 August 2021
    Authorities, Grid Connection, Wind Farm Update

    East Lothian Council planning officers have recommended for approval the Seagreen 1A onshore proposals at Cockenzie. The applications were submitted earlier this year to East Lothian Council for onshore works and Marine Scotland for offshore works. No local representations had been received against the plans, the project’s developer said. The project infrastructure is located in […]

  • 13 December 2021
    Authorities, Wind Farm Update

    Scottish Government Ministers have approved the Marine Licence application for the 36-turbine Seagreen 1A offshore wind proposal being brought forward by SSE Renewables and TotalEnergies. The Marine Licence covers the offshore elements of the project, including an export cable approximately 110 kilometres in length, to connect the project to the grid at Cockenzie in East […]

  • 7 June 2022
    Contracts & Tenders, Wind Farm Update

    Seagreen 1 Limited has selected Seaway 7, the Renewables & Heavy Lifting business unit of Subsea 7, as a preferred supplier for the Seagreen 1A wind project offshore Scotland, with the final contract expected to be valued between USD 500 million and USD 750 million. Seagreen 1A lies adjacent to the existing Seagreen project that […]

  • 14 January 2021
    Business & Finance, Wind Farm Update

    Seagreen 1A Ltd. is seeking feedback on the onshore and offshore grid connection proposals related to the remaining 36 turbines to be installed at the Seagreen offshore wind project. The company is undertaking pre-application consultation ahead of potentially submitting applications to East Lothian Council and Marine Scotland for the onshore and offshore elements to allow […]

  • 19 January 2021
    Wind Farm Update

    MMT has commenced the geophysical survey of the export cable route at the Seagreen 1A offshore wind project in Scotland. The team began the operations earlier this week onboard offshore survey vessel Franklin and will later be adjoined by a shallow draft vessel to perform the nearshore and intertidal parts of the survey. The export […]

  • 1 June 2023
    Wind Farm Update

    100 out of 114 Vestas V164-10 MW wind turbines have been installed at what will be Scotland’s largest offshore wind farm – Seagreen – off the coast of Angus. According to AIS, Cadeler’s wind farm installation vessel Wind Orca is at the offshore construction site 27 kilometres from the coast of Angus where it will […]

  • 12 October 2022
    Wind Farm Update

    Cadeler’s wind farm installation vessel Wind Orca has hit the halfway mark on the Seagreen offshore wind farm in Scotland, where 57 out of the 114 Vestas 10 MW wind turbines have now been installed. The first wind turbine was installed in early December 2021 by the Wind Osprey vessel, which was replaced by its sister vessel […]

  • 14 February 2023
    Contracts & Tenders

    Seaway 7, the Renewables & Heavy Lifting business unit of Subsea 7, has been awarded a contract worth between USD 300 million and USD 500 million for an undisclosed offshore wind farm project. Under the contract, Seaway 7 will be responsible for the transportation and installation of inner-array and export power cables, and respective cable […]

  • 22 December 2022
    Wind Farm Update

    The final jacket foundation for the Seagreen 1 offshore wind farm has arrived in Port of Nigg, from where the foundations are being installed by Seaway 7. It took a total of 23 shipments to deliver the 114 jackets to the Port of Nigg, which was achieved through collaboration between Seaway7, SSE Renewables, COSCO, Global […]

  • 16 February 2023
    Wind Farm Update

    Seagreen offshore wind farm has entered the final phases of work after the remaining eight three-legged jacket foundations were loaded onto barges at Global Energy Group’s Port of Nigg in the Highlands of Scotland. Global Port Services, part of Global Energy Group, fulfilled the storage, marshalling, and logistics contracts for the 114 95-metre tall jacket […]

  • 11 July 2023
    Wind Farm Update

    Seaway7 has completed the full engineering, procurement, construction, and installation (EPCI) cables scope on the Seagreen wind farm offshore Scotland, a joint venture project between SSE Renewables and TotalEnergies. The inter-array cable team completed the termination and testing last weekend and the trenching was completed yesterday, said Seaway7. This follows less than six weeks after […]

  • 16 June 2022
    Contracts & Tenders, Wind Farm Update

    Seaway 7 ASA, part of the Subsea 7 Group, has signed a letter of exclusivity, and is finalising a preferred bidder supply chain agreement with ScottishPower Renewables for the East Anglia THREE offshore wind project in the UK. East Anglia THREE is located approximately 70 kilometres from shore in the Southern North Sea and is […]

  • 17 April 2023
    Wind Farm Update

    Seaway7 has installed the final wind turbine foundation on Seagreen Offshore Wind Farm, off the coast of Angus, Scotland, concluding the 18-month installation campaign. The 114th jacket foundation was successfully installed late afternoon on Thursday, 13 April, by the Saipem 7000 crane vessel, which was used to lift each of the 2,000-tonne foundations into place. […]

  • 12 April 2023
    Wind Farm Update

    The world’s deepest fixed-bottom wind turbine foundation has been installed at what will be Scotland’s largest offshore wind farm – Seagreen – off the coast of Angus. On Friday, 7 April, the jacket foundation was transported to the project site on a barge operated by the main contractor, Seaway 7, where it was met by […]

  • 27 July 2021
    Wind Farm Update

    A geotechnical survey is set to begin along the proposed export cable route at the Seagreen Phase 1A offshore wind farm. The survey vessel Northern Ocean will conduct the seabed cone penetration tests and vibro core sampling within the export cable area and the Seagreen array site boundary. The survey is expected to start on […]

  • 5 July 2021
    Wind Farm Update

    A shallow geotechnical survey is about to begin within the export cable area at the Seagreen Phase 1A wind farm offshore Scotland. The survey is scheduled to take place from 7 July to 11 July near the shoreline at Cockenzie in the Firth of Forth. The survey vessel Pulsar will conduct the shallow geotechnical survey […]

  • 22 December 2022
    Wind Farm Update

    SSE Renewables submitted the application for the 4.1 GW Berwick Bank offshore wind project to Marine Scotland on 9 December, kicking off the consent process with the Scottish Ministers. According to the developer, the project’s site in the Firth of Forth is the only remaining fixed-bottom site in Scotland that could bring forward this kind […]