671 results found for 'Seaway7'

671 results found for 'Seaway7'
Order results by

A list of search results

  • 20 August 2017

    Oleg Strashnov Installs First Beatrice Jacket Foundation Seaway Heavy Lifting’s vessel Oleg Strashnov has installed the first of 86 jacket foundations on the 588MW Beatrice offshore wind farm in the Outer Moray Firth, Scotland. Boskalis Buys Gardline Group Royal Boskalis Westminster N.V. has acquired all shares of the UK-based Gardline Group. U.S. Oil & Gas […]

  • 30 November 2016

    BiFab’s Arnish facility began work on the transition pieces and piles for the Beatrice offshore wind farm in mid-October, increasing the workforce at the site by 71 people, according to SSE. Burntisland Fabrications (BiFab), a Fife based company with facilities at Burntisland, Methil and Arnish, won two multi-million pound contracts with Beatrice Offshore Wind Ltd’s […]

  • 11 March 2015
    Business & Finance, Environment, Technology

    ABS has granted approval in principle (AIP) to Maryland-based OTEC International LLC (OTI) for its 5–7 megawatt ocean thermal energy conversion (OTEC) Floating Power Plant (FPP). The FPP is designed to generate consistent electrical power for a commercial utility grid in the world’s tropical and sub-tropical zones. The FPP design uses seawater to turn solar […]

  • 15 May 2015
    Authorities, R&D, Technology

    The Peruvian Navy has officially signed off on permitting which grants US wave energy developer Atmocean a one-year license to demonstrate its wave energy technology in Ilo, a coastal city in southern Peru. Atmocean will deploy a system consisting of five connected seawater pumps by early June, leading to the potential installation of full commercial […]

  • 27 February 2018
    Grid Connection, Wind Farm Update

    STX France has transported the offshore substation jacket foundation for the Arkona offshore wind farm to a quay in the Saint-Nazaire Port, from where it will be placed on a barge and transported to the wind farm site in the German Baltic Sea.

  • 5 April 2017

    Granada Material Handling (GMH) recently delivered its 750th wind farm davit crane as part of its contract to supply 84 cranes to the Beatrice offshore wind farm project.

  • 18 September 2013

    Team Humber Marine Alliance (THMA) and Enterprise Europe Network (EEN) organised a visit to Denmark for a delegation of Humber companies working in the offshore wind supply chain, writes the Grimsby Telegraph. Around 20 businesses and organisations toured the main production facilities of Siemens Wind Power in Brande. Delegates also visited ‘Energy Metropolis’ Esbjerg, along […]

  • 9 March 2018
    Business & Finance

    Subsea 7 is bidding on a tender to provide and install foundations for the Dieppe et Le Tréport and Iles d’Yeu et de Noirmoutier offshore wind farms in France.

  • 16 January 2018
    Grid Connection, Operations & Maintenance, R&D, Vessels

    Tideway B.V., part of DEME Group, has shared a photo of the DP2 Accommodation and Walk-to-Work (W2W) vessel Normand Jarstein working on the 396MW Merkur offshore wind farm.

  • 22 July 2011
    Technology

    Heerema Fabrication in Zwijndrecht, a subsidiary of the Heerema Group, has given Siemens Water Technologies the order for the delivery of a Chloropac hypochlorite generator for seawater cooling. The order is worth over half a million Euros. The generator will be used at the North Sea platform DolWin1 and is the first Chloropac system to […]

  • 3 March 2022
    Wind Farm Update

    Ten out of the 114 Vestas V164-10.0 MW turbines have been installed at the 1.1 GW Seagreen offshore wind farm, Scotland’s largest and the world’s deepest fixed-bottom offshore wind farm. The first wind turbine was installed at the site some 27 kilometres off the Angus coast in early December. This marked the first time a […]

  • 28 February 2022
    Wind Farm Update

    Singapore-based marine and offshore engineering group Sembcorp Marine has manufactured the 15 wind turbine jacket foundations for the 376 MW Formosa 2 wind project offshore Taiwan. Five jacket foundations have since sailed away with the remaining awaiting client’s vessel availability, Sembcorp Marine said. Jan De Nul, the EPCI contractor for the project’s foundations and subsea […]

  • 17 December 2017
    Contracts & Tenders

    Oleg Strashnov to Stay on Beatrice Until New Year Seaway Heavy Lifting’s (SHL) vessel Oleg Strashnov – which left the Beatrice site after installing the 24th jacket foundation in late September and returned to the job in November – has put the 25th jacket in place and thus officially resumed the works after more than […]

  • 8 December 2014

    In August Dudgeon Offshore Wind Limited, a joint venture of Statoil and Statkraft, announced it had awarded a contract to Siemens for the supply of 67 turbines for their 402MW Dudgeon Offshore Wind Farm. Siemens will be providing their SWT-6.0-1 54 6MW turbine. This was soon after followed by thecontract for the grid connection. Siemens […]

  • 10 February 2022
    Business & Finance, R&D, Technology

    Researchers at the University of Malta have kicked off research to assess how the significant amounts of CO2 available from carbon capture and storage (CCS) facilities may support offshore energy storage systems co-located within the same footprint of wind farms. The Investigating the thermal performance of Subsea Energy Storage Accumulators with a 2-Phase Fluid Transition […]

  • 11 May 2020
    Ports & Logistics, Wind Farm Update

    Jan De Nul will set up a logistics and operations hub for the 376 MW Formosa 2 offshore wind farm project in the Port of Taichung, Taiwan. Jan De Nul and a subsidiary of the Taiwan International Port Corporation (TIPC) signed a lease and operating agreement covering a total of around 15 hectares of land. […]

  • 15 May 2017
    Wind Farm Update

    On 11 May, Seaway Heavy Lifting (SHL) installed the 11th set of jacket foundation piles at the Beatrice offshore wind farm in Outer Moray Firth.

  • 18 April 2017
    Grid Connection, Vessels, Wind Farm Update

    Siem Offshore Contractors has completed pre-construction boulder removal works on the 588MW Beatrice offshore wind farm in the Outer Moray Firth, Scotland. According to a Notice of Operations, issued by Beatrice Offshore Windfarm Limited (BOWL), Siem N-Sea completed the boulder removal works along parts of the array cable routes and at various foundation locations on 12 April. The vessel deployed a […]

  • 25 December 2015
    Business & Finance, Grid Connection, Operations & Maintenance, R&D, Technology, Training & Education, Vessels, Wind Farm Update

    As the year draws to a close, Offshore WIND staff bring a reminder of interviews which caught our readers’ attention the most in 2015! GE Has the World’s 2nd Largest Order Backlog Offshore WIND has spoken to Anders Søe-Jensen, CEO of GE’s offshore wind unit, at the EWEA 2015 event in Paris, where the company introduced […]

  • 10 September 2017

    Ireland Reveals Big Offshore Wind Plans Ireland’s state owned electricity company Electricity Supply Board (ESB) is seeking expressions of interest for the provision of renewable energy marine services related to offshore wind farms. World’s First Offshore Wind Farm Disappears from Horizon (Video) DONG Energy has completed the decommissioning of the world’s first offshore wind farm, the […]

  • 6 July 2022
    Contracts & Tenders, Wind Farm Update

    Endiprev has started working on the 342 MW Kaskasi offshore wind farm in Germany under a contract with Siemens Gamesa, the project’s wind turbine supplier. Throughout the next six months, Endiprev will perform installation and finishing works for Siemens Gamesa on the Kaskasi offshore wind farm, located in the German North Sea, 35 kilometres north of […]

  • 10 February 2021
    Contracts & Tenders, Ports & Logistics, Wind Farm Update

    Global Energy Group’s (GEG) Port of Nigg has been selected as the marshalling, storage and logistics base for 114 wind turbine foundations for the 1,075 MW Seagreen offshore wind farm. GEG has been awarded a contract for the project by Seaway 7, the EPCI contractor for Seagreen’s foundations and inter-array cables, on behalf of the […]

  • 10 November 2020
    Wind Farm Update

    Haizea Wind has so far sent off 20 out of the total 32 transition piece (TP) barrels for the Taiwanese Formosa 2 offshore wind farm from Spain to Indonesia. On 28 September, the company completed the delivery of the first batch of four TPs to Saipem by shipping them to the Karimun Yard in Indonesia. […]

  • 10 July 2018
    Contracts & Tenders, Wind Farm Update

    The NHV Group has secured a contract with Siemens Gamesa to provide helicopter services in support of the construction of the Beatrice offshore wind farm in Scotland.

  • 3 April 2018
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s (SHL) vessel Stanislav Yudin has been deployed on the jacket installation at the Beatrice offshore wind farm as the heavy lift vessel Oleg Strashnov left the site to handle the substation installation at the Arkona offshore wind farm in the German part of the Baltic Sea.

  • 12 January 2018
    Operations & Maintenance, Vessels

    Our latest photo of the day shows Seacat Services’ crew transfer vessel (CTV) Seacat Volunteer picking up technicians from the substation at Ørsted’s 573MW Race Bank offshore wind farm located off the North Norfolk coast, UK.