279 results found for 'Triton Knoll '

279 results found for 'Triton Knoll '
Order results by

A list of search results

  • 4 May 2020
    Contracts & Tenders

    Pegasus Welfare Solutions Ltd has secured a contract to supply welfare facilities for the Triton Knoll offshore wind project in the UK. The East of England-based company will deploy its Pegasus Multi-units onto both substations, which will allow welfare facilities to be maintained during installation and commissioning. “The award of the contract to Pegasus Welfare […]

  • 26 September 2019
    Grid Connection, Wind Farm Update

    Triton Knoll has given an update on the construction of the two offshore substations destined for the 860MW offshore wind project. According to Triton Knoll, a transition piece for the offshore substation has left the construction hall at Smulders’ Wallsend facility in the UK. The company has now commenced the offshore substation foundation work. Additionally, the […]

  • 11 June 2020
    Grid Connection, Wind Farm Update

    The topside for the Triton Knoll Offshore Substation Platform (OSP) East has left Vlissingen in the Netherlands and is en route to the installation site off Lincolnshire, UK. Once there, the topside will be lowered onto its monopile foundation by Seaway 7’s installation vessel Seaway Strashnov. Seaway Strashnov installed the Triton Knoll OSP West topside […]

  • 1 April 2019
    Contracts & Tenders

    SeaPlanner Ltd has won a contract to provide its SeaPlanner marine management system and SeaHub communications solutions to support the construction of the 857MW Triton Knoll offshore wind farm. The SeaPlanner will be deployed for use by the construction project team to coordinate all personnel and marine logistics for the 145 kilometre-square site located some 33 […]

  • 7 March 2016
    Grid Connection, Wind Farm Update

    The examination period for the proposed electrical infrastructure for the Triton Knoll offshore wind farm closed on 3 March, the UK Planning Inspectorate (PINS) reported, and the proposal is now in a decision stage.  There will now be a period of 3 months for the Examining Authority to consider and make a recommendation to the Secretary […]

  • 5 March 2013

    Plans for the electrical infrastructure which will transport electricity from the Triton Knoll Offshore Wind Farm to the national grid will be on display this week. Six days of public exhibitions on plans for RWE npower renewables’ Triton Knoll Offshore Wind Farm – which will be located approximately 20 miles off the Lincolnshire coast, will […]

  • 11 October 2017
    Business & Finance, Wind Farm Update

    Statkraft has continued executing its plan to exit offshore wind and has now sold its stake in the 860MW Triton Knoll project to innogy, thus making innogy the sole owner.

  • 5 December 2017
    R&D, Technology, Wind Farm Update

    Atkins is designing foundations for Triton Knoll’s 90 MHI Vestas V164-9.5MW turbines and two offshore substations, which have the potential to be lighter than any currently installed in comparable site conditions, the UK-based designer said.

  • 4 April 2017
    Business & Finance, Wind Farm Update

    Triton Knoll Offshore Wind Farm, a project company comprising innogy and Statkraft, has awarded Dalcour Maclaren with a contract for Land Agent services as preparation for the onshore construction are under way.

  • 22 March 2019
    Grid Connection, Wind Farm Update

    The first onshore electrical cables destined for the Triton Knoll offshore wind farm have rolled out from production and are heading towards the Port of Boston, the UK. The High Voltage Alternating Current (HVAC) cables will make up the onshore cable network, connecting power from the 860MW offshore wind farm to the new onshore substation […]

  • 14 May 2018
    Contracts & Tenders, Wind Farm Update

    Offshore Wind Consultants Limited (OWC) has secured a contract to provide project management services for innogy’s 860MW Triton Knoll offshore wind farm project.

  • 6 September 2016

    Following today’s decision by the Secretary of State for Business, Energy and Industrial Strategy, Greg Clark, to grant consent for the electrical infrastructure for Triton Knoll offshore wind farm, RenewableUK highlighted the potential for job creation throughout the UK. The Triton Knoll offshore wind farm was consented in 2013. This means that the project now has […]

  • 3 November 2020
    Ports & Logistics, Wind Farm Update

    The first turbine blades to be installed on the Triton Knoll offshore wind farm have arrived at Able Seaton Port, the project’s construction port in Teesside. This marks the first time that Able Seaton Port is receiving offshore wind turbine components in its history, after a combined multi-million pound investment has helped transform the port […]

  • 2 October 2017
    Business & Finance, Grid Connection, Wind Farm Update

    Triton Knoll Offshore Wind Farm has selected Siemens Transmission and Distribution as the preferred supplier to engineer, procure, and construct both the onshore and offshore substations.

  • 4 February 2020
    Ports & Logistics

    Works on enabling Able Seaton Port for Triton Knoll wind turbine pre-assembly have begun, including preparing the existing site, establishing new drainage and upgrading the internal electricity supply.

  • 31 August 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Ørsted and innogy have entered a power purchase agreement (PPA) under which Ørsted will offtake 100% of the power generated by the Triton Knoll offshore wind farm, for which innogy has now reached financial close. 

  • 10 November 2016
    Authorities, Business & Finance, Wind Farm Update

    The developers of the 900MW Triton Knoll offshore wind farm have welcomed the UK government’s confirmation that the next Contracts for Difference (CfD) auction will open in April 2017, adding that the project is well prepared to submit a bid into the next auction and is in an excellent position to compete for a share of […]

  • 7 September 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Siemens Energy Management has received a firm order to design, supply and build the grid connection for the Triton Knoll offshore wind farm by German customer innogy SE.

  • 11 November 2016
    Environment, Grid Connection, R&D, Wind Farm Update

    Triton Knoll Offshore Wind Farm is due to begin a second round of site survey works in Lincolnshire next week, as it builds a detailed picture of local ground conditions at various locations along the entire 60km cable route. The survey results will be crucial to designing the best approach to the installation of the […]

  • 6 October 2020
    Ports & Logistics, Wind Farm Update

    The first turbine components for the Triton Knoll wind farm are expected to arrive at MHI Vestas’ logistics and pre-assembly hub in the Able Seaton Port in Hartlepool next month. MHI Vestas has now moved in to Able Seaton Port in preparation to start installing 90 of its V164-9.5 MW turbines at the site 32 […]

  • 10 November 2021
    Contracts & Tenders, Grid Connection

    A consortium of the London-based Equitix Limited and Japan’s TEPCO Power Grid has been selected as the preferred bidder for the offshore electricity transmission link connecting the 857 MW Triton Knoll wind farm to the UK grid. Valued at approximately GBP 577 million (EUR 675 million), the new offshore electricity transmission asset is comprised of […]

  • 13 January 2020
    Wind Farm Update

    STS Belgium is carrying out the cabling of the transition pieces for the Triton Knoll offshore wind project. STS is conducting the work at Smulders’ yard in Hoboken and at the Sif Maasvlakte terminal in Rotterdam, the Netherlands. To remind, Seaway 7’s installation vessel Seaway Strashnov arrived at the Triton Knoll offshore wind project site […]

  • 10 June 2020
    Grid Connection

    Rotech Subsea has completed a three-phase work scope at the Borssele and Triton Knoll offshore wind farms for a dredging specialist. Rotech provided its TRS1 and TRS1LD Jet Trenching tools to carry out pit clearing and cable lowering at the Borssele project in the Dutch North Sea, as well as grout bag and cable de-burial […]

  • 2 August 2017
    Grid Connection, R&D, Wind Farm Update

    Triton Knoll Offshore Wind Farm has begun an archaeological trial trenching campaign along the full route of the onshore export cable corridor in Lincolnshire.

  • 26 August 2020
    Wind Farm Update

    All turbine foundations and export cables have been installed at the Triton Knoll offshore wind farm in the UK. According to project developer RWE, the installation of the 90 monopile foundations and two lengths of 50km export cable was completed this week. Seaway 7’s Seaway Strashnov and DEME’s Innovation were in charge of installing the […]

  • 31 August 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    German-based offshore wind developer innogy has reached financial close for the 860MW Triton Knoll offshore wind farm in the UK, worth around GBP 2 billion, and moved the project towards construction that starts with the onshore electrical system in September.