195 results found for 'formosa 2'

195 results found for 'formosa 2'
Order results by

A list of search results

  • 17 August 2020
    Contracts & Tenders, Grid Connection

    First Subsea has secured a contract by Jan De Nul to provide the cable protection system for the export and inter-array cables at the Formosa 2 offshore wind project in Taiwan. The order represents First Subsea’s second cable protection system award in Taiwan and follows last year’s cooperation with Jan De Nul at the Formosa 1 […]

  • 10 February 2020
    Wind Farm Update

    Dutch subsea survey specialist Deep BV is carrying out unexploded ordnance (UXO) geophysical survey at the Formosa 2 wind farm offshore Taiwan. The survey is being carried out at the potential locations of the wind turbines, the company said. Deep BV did similar work on the 128MW Formosa 1, Taiwan’s first commercial-scale offshore wind farm. […]

  • 16 June 2020
    Wind Farm Update

    EEW Group is producing the steel pipe components for the 47 jacket foundations to be installed on the Formosa 2 wind farm offshore Taiwan. The production of the steel pipes for the jackets started in January at EEW Korea, EEW KHPC, and EEW Malaysia and is expected to be completed in October 2020. With a […]

  • 18 May 2020
    Wind Farm Update

    EEW’s manufacturing facilities in Asia have produced half of the total of 188 pin piles for Taiwan’s Formosa 2 offshore wind farm. Formosa 2 will comprise 47 jacket foundations, with each jacket secured to the seabed with four pin piles. Each pin pile is up to 78.9 metres long, has an outside diameter of 2.4 metres, […]

  • 9 October 2019
    Business & Finance, Wind Farm Update

    JERA is set to acquire a 49% equity interest in the Formosa 2 offshore wind farm in Taiwan, the Japanese utility revealed shortly after it had secured joint control over the project with Macquarie and Swancor. Macquarie will hold a 26% stake and Swancor will hold 25% of the 376MW wind project located offshore Miaoli County in the Taiwan Strait. The […]

  • 5 November 2019
    Business & Finance

    UK Export Finance (UKEF) has provided an NT$ 9.2 billion (GBP 230 million) project finance guarantee to support the construction of the Formosa 2 offshore wind farm in Taiwan. As a result of the support, UK companies will be involved in the construction of the 376MW wind farm, helping unlock the export potential of the […]

  • 8 July 2022
    Business & Finance, Vessels, Wind Farm Update

    Saipem has reported that the company reached two important milestones in offshore wind this month following the installation of the offshore substation at the Saint-Brieuc wind farm site in France and the delivery of the final of its batch of jacket foundations for the Formosa 2 offshore wind farm in Taiwan. The transport and installation […]

  • 31 October 2019
    Contracts & Tenders, Wind Farm Update

    Jan De Nul has selected the suppliers of the jacket foundations and the accompanying pin piles for the 376MW Formosa 2 offshore wind farm in Taiwan. Jan De Nul is the EPCI contractor for the project’s foundations and subsea cables. Following the project financial close reached earlier this week, Jan De Nul awarded Saipem and Sembcorp […]

  • 22 September 2020
    Business & Finance, Wind Farm Update

    Swancor Renewable Energy has revealed plans to develop the 4.4 GW Formosa 4 offshore wind project off the Miaoli County in Taiwan. The portfolio would consist of three sites, including Formosa 4-1, Formosa 4-2 and Formosa 4-3, which would cover a large maritime area located 18 to 20km offshore. Swancor Renewable Energy said it had […]

  • 10 December 2020
    Contracts & Tenders, Wind Farm Update

    Siemens Gamesa has awarded FairWind with a contract to assist on pre-assembly work on offshore wind turbines for the Formosa 2 wind farm in Taiwan. FairWind will be responsible for the pre-assembly of the towers for 47 SGRE 8.0 MW wind turbines, scheduled to start in March 2021. “This is an important opportunity for FairWind […]

  • 26 August 2020
    Vessels, Wind Farm Update

    JIFMAR Offshore Services’ shallow draft DP1 workboat JIF Breizh has completed operations at the Formosa 2 offshore wind farm in Taiwan, under a contract with Jan De Nul. The vessel, which was contracted and transported to Taiwan earlier this year, worked on export cable pull-in landfall Horizontal Direction Drilling (HDD) operations for three months. Within […]

  • 21 September 2022
    Contracts & Tenders, Wind Farm Update

    EDS HV Group (EDS), a subsidiary of James Fisher Renewables (JF Renewables), has been awarded a multi-million-pound contract to provide high voltage support services at the Formosa 2 wind farm offshore Taiwan. EDS will support the management of the high voltage network and the electrical safety during the construction and commissioning phase of the project, […]

  • 17 June 2019
    Contracts & Tenders

    Siemens Gamesa has received a conditional order for the supply of turbines for the 376MW Formosa 2 offshore wind project in Taiwan. Siemens Gamesa will provide 47 of its SG8.0-167 DD turbines and is in charge of the full servicing for a period of 20 years, including the provision of spare parts and tools. The firm order is subject to […]

  • 3 July 2020
    Vessels

    A Pile Installation Frame (PIF) for Seaway Yudin’s pin-pile installation work in Taiwan has been loaded onto a vessel in the Port of Rotterdam, from where it will be transported to Taiwan, Seaway 7 said on social media. The company did not name the project for which the PIF is being transported. Seaway 7 has […]

  • 5 June 2020
    Wind Farm Update

    Jan De Nul has kicked off construction works in Taiwan for the 376 MW Formosa 2 offshore wind farm. Nearshore and onshore construction works have started at the landfall site in Miaoli County and Taichung port, Jan De Nul said. Offshore installation works will commence later this year. At the landfall site in Miaoli County, […]

  • 28 November 2019
    Contracts & Tenders

    Italian offshore energy contractor Saipem will manufacture and deliver 32 wind turbine jacket foundations for the 376MW Formosa 2 offshore wind farm in Taiwan. As reported earlier, Jan De Nul, the EPCI contractor for the project’s foundations and subsea cables, selected Saipem and Sembcorp to deliver the pile jacket foundations for the wind farm. At […]

  • 28 February 2022
    Wind Farm Update

    Singapore-based marine and offshore engineering group Sembcorp Marine has manufactured the 15 wind turbine jacket foundations for the 376 MW Formosa 2 wind project offshore Taiwan. Five jacket foundations have since sailed away with the remaining awaiting client’s vessel availability, Sembcorp Marine said. Jan De Nul, the EPCI contractor for the project’s foundations and subsea […]

  • 1 September 2022
    Wind Farm Update

    All 47 wind turbine jacket foundations and all subsea cables are now in place at the Formosa 2 offshore wind farm in Taiwan. The wind farm also has more than half of its wind turbines installed so far. The final jacket foundation was installed on 26 August, with the subsea cable works reaching completion on […]

  • 23 July 2021
    Grid Connection, Wind Farm Update

    Jan De Nul has completed the installation of all export cables for the 376 MW Formosa 2 offshore wind farm in Taiwan. The company installed four export cables with a total length of 34 kilometres using its cable laying vessel (CLV) Willem de Vlamingh, which was able to position itself close to the beach and […]

  • 5 July 2019
    Business & Finance, Contracts & Tenders

    Siemens Gamesa has signed a Memorandum of Understanding with Formosa Plastics Corporation for offshore wind in Taiwan. According to the company, the agreement adds up to a series of earlier agreements with local and international parties to promote a competitive supply chain. To remind, Siemens Gamesa inked the first local supply agreements in Taiwan last year by […]

  • 30 June 2022
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Japanese utility JERA and Corio Generation, the new specialist offshore wind business of Macquarie’s Green Investment Group (GIG), announced on 30 June that they were ready to bid for the third phase of Taiwan’s offshore wind zonal development with their Formosa 3 project. JERA and Corio (GIG at the time) have already partnered in Taiwan […]

  • 15 July 2022
    Vessels

    Australian marine services provider MMA Offshore has completed the conversion of its anchor handling tug supply (AHTS) vessel MMA Crystal and reflagged it to support the offshore renewable energy market in Taiwan. The AHTS, which already worked on an offshore wind project in Taiwan, having supported a pre-installation noise mitigation survey at Formosa 2 last year, has been […]

  • 9 March 2020
    Wind Farm Update

    JERA has reached an agreement with Macquarie’s Green Investment Group (GIG) and EnBW Energie Baden-Württemberg AG (EnBW) to join the development of the Formosa 3 offshore wind farm in Taiwan. JERA now holds 43.75% of the project, with GIG holding 31.25% and EnBW 25%, retaining material stakes and remaining committed to the ongoing development. The […]

  • 21 June 2019
    Business & Finance

    Taiwan’s Swancor is selling 100% of its shares in Swancor Renewable Energy Co. Ltd and its subsidiary Haineng Wind Power to ”European and American energy companies’‘. Swancor is selling 20 million shares at a price range of between USD 1.3 and USD 5.07 per share. The transaction could fetch between USD 26 million and USD […]

  • 24 June 2020
    Operations & Maintenance

    Specialist Marine Consultants (SMC) has been awarded two contracts by Ørsted for above-water structural inspection of the wind turbine foundations at the developer’s offshore wind farms in Germany and the UK. Ørsted has four operational offshore wind farms in Germany and eleven in the UK. SMC has not disclosed which, if not all, projects will […]

  • 23 July 2019
    Contracts & Tenders, Grid Connection

    LS Cable & System has secured a contract by Jan De Nul to supply submarine cables for an offshore wind project in Taiwan. Under the contract, the Korean cable manufacturer will supply 130km of submarine cable for the project located in Miaoli County, west Taiwan, by 2021. To remind, Jan De Nul is responsible for the design, […]