  • 18 November 2019
    Wind Farm Update

    Jan De Nul’s jack-up vessel Vole au vent has completed the installation of all monopile foundations at the Northwester 2 offshore wind project, a spokesperson from Parkwind told Offshore WIND. According to Parkwind, Vole au vent completed the installation of all 23 monopiles on 13 November and is currently preparing for the installation of turbines. […]

  • 3 May 2018
    Contracts & Tenders, Wind Farm Update

    Northwester NV, the developer of Belgian Northwester 2 offshore wind farm, has awarded Bladt Industries with an EPCI contract for the project’s offshore substation, under which Bladt – with its partners Semco Maritime and ISC – is in charge of designing, building and installing the substation. 

  • 14 May 2020
    Wind Farm Update

    The Northwester 2 offshore wind farm is fully operational, with all 23 MHI Vestas 9.5 MW turbines supplying power to the Belgian grid. Northwester 2 is the first to use the V164-9.5 MW turbines, the most powerful turbines to enter commercial operation to date, which now supply green energy via Elia’s Modular Offshore Grid (MOG). […]

  • 18 December 2019
    Wind Farm Update

    Jan De Nul’s jack-up vessel Vole au vent has installed the first turbine at the Northwester 2 offshore wind project in Belgium. Northwester 2 will comprise 23 MHI Vestas V164-9.5MW turbines, making it the first wind farm to feature this turbine model. According to MHI Vestas, all major turbine components have been assembled and pre-commissioned […]

  • 8 October 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Belgian offshore wind developer Northwester 2 has selected the French cable specialist Nexans to provide an export cable system for the 219MW Northwester 2 offshore wind farm.

  • 10 January 2020
    Vessels

    High Speed Transfers (HST) has taken over HST Euan, its fourth FCS 2710 class fast crew supply vessel, from Damen Shipyards. HST Euan, built by Damen Shipyards in Antalya, Turkey, is now ready for its voyage to Belgium, HST said. Once there, the vessel, and its sister HST Harri, will be deployed on the Northwester 2 […]

  • 30 August 2019
    Grid Connection, Wind Farm Update

    The 962-ton Northwester 2 offshore high voltage station has completed its journey from Aalborg, Denmark to the Port of Oostende in Belgium. The Port of Oostende will be a temporary home to the substation prior to the installation at the site some 48 kilometres north-west of Oostende. The substation’s journey from the Bladt Industries’ facilities […]

  • 26 August 2019
    Grid Connection, Wind Farm Update

    The offshore substation built for the Northwester 2 offshore wind farm has left Bladt Industries’ facility in Aalborg, Denmark, and is on its way towards the project site in Belgium. Bladt designed, built and assembled the substation with its partners Semco Maritime and ISC under a contract won in May last year. The 235t transformer was installed on […]

  • 8 October 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Northwester 2 has reached the official close of financial agreements with all key stakeholders and banks for the construction of the 219MW Northwester 2 offshore wind farm in the Belgian North Sea.

  • 5 October 2018
    Business & Finance, Wind Farm Update

    The European Investment Bank (EIB) will support the construction of the Northwester 2 wind farm off the Belgian coast with a loan of EUR 210 million.

  • 16 April 2019
    Grid Connection, Wind Farm Update

    Poland’s Mostostal Pomorze has loaded out the substation topside built for the Northwester 2 offshore wind farm in Gdansk. The load-out operations were performed on 13 and 14 of April. The topside is currently travelling to Aalborg in Denmark where Bladt Industries will continue working on it. In June 2018, Mostostal Pomorze signed a contract for prefabrication of […]

  • 31 January 2019
    Contracts & Tenders, Operations & Maintenance

    Tekmar Energy has secured a contract by Jan De Nul to provide its cable protection system (CPS) for the Northwester 2 offshore wind farm in Belgium. Under the agreement, Tekmar will supply its TekLink Mechanical Latch Generation 8 CPS for all of the project’s inter-array and export cables. The system will be produced at the company’s manufacturing […]

  • 7 November 2018
    Contracts & Tenders, Wind Farm Update

    MHI Vestas Offshore Wind and Parkwind have confirmed the firm order for the supply and installation of 23 V164-9.5 MW turbines for the Northwester 2 wind farm offshore Belgium. Installation is scheduled to begin in late 2019, MHI Vestas said. Northwester 2 in Belgium will be the world’s first offshore wind park to feature the V164-9.5 MW […]

  • 21 November 2017
    Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

    Parkwind has issued a tender seeking companies to design, build, install and commission the offshore high voltage substation (OHVS) for its Northwester 2 wind farm in the Belgian North Sea.

  • 23 April 2019
    Grid Connection, Wind Farm Update

    Bladt Industries has installed the transformer on the offshore substation built for the Northwester 2 offshore wind farm in Belgium. According to the Danish company, three cranes were necessary for the installation of the 235t transformer on the substation. To remind, the substation topside began its journey towards Bladt’s premises in Aalborg from Mostostal Pomorze in […]

  • 29 August 2018
    Business & Finance, Wind Farm Update

    As of 24 August, Japan-based Sumitomo Corporation holds a 30% stake in the Northwester 2 offshore wind project, developed by Parkwind in the Belgian sector of the North Sea. 

  • 24 November 2017
    Business & Finance, Contracts & Tenders, Grid Connection, Ports & Logistics, Wind Farm Update

    Belgian offshore wind developer Parkwind is looking for a provider of an export cable for the 228MW Northwester 2 wind farm in the Belgian North Sea.

  • 19 July 2019
    Wind Farm Update

    Offshore wind developer Parkwind and marine contractor Jan De Nul have kicked off offshore seabed preparation works in the Belgian North Sea for the 219MW Northwester 2 wind farm. Jan De Nul has just finished the offshore scour protection works on the wind farm’s 23 turbine locations. At each location, the subsea rock installation vessel Simon […]

  • 7 August 2018
    Grid Connection, Wind Farm Update

    Northwester NV has awarded Norddeutsche Seekabelwerke GmbH (NSW) with a contract to deliver a submarine inter-array power cable system for the Northwester 2 offshore wind farm in the Belgian North Sea.

  • 19 April 2018
    Business & Finance, Wind Farm Update

    Belgian offshore wind developer Parkwind has applied for funding from the European Investment Bank (EIB) for its Northwester 2 offshore wind farm in the Belgian North Sea.

  • 10 July 2018
    Authorities, Business & Finance, Wind Farm Update

    Belgium’s Parkwind and Summit Tailwind Belgium, part of the Sumitomo Corporation, have submitted a notification of concentration to the European Commission for the acquisition of the joint control over Northwester 2.

  • 27 October 2017
    Business & Finance, Wind Farm Update

    Following the support scheme agreement reached today (27 October) with Belgian government for its Northwester 2 offshore wind farm, Parkwind announced it will now accelerate project development activities and prepare for financial close in 2018.

  • 25 April 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Belgian offshore wind developer Parkwind has selected MHI Vestas 9.5MW wind turbines for the Northwester 2 offshore wind farm.

  • 31 July 2018
    Authorities, Business & Finance

    The European Commission has approved the acquisition of joint control by Parkwind and Summit Tailwind Belgium over Northwester 2, a project company holding a 224MW concession in the Belgian North Sea.

  • 6 July 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Bladt Industries has signed two contracts with Jan de Nul and Parkwind, under which the foundation manufacturer will deliver 23 monopiles and transition pieces for Northwester 2 wind turbines, and one monopile and transition piece for the project’s substation.

  • 6 November 2019
    Business & Finance

    Northwester 2 turbines will be secured to their foundations with super duplex fasteners designed to be maintenance-free throughout the 27-year turbine design life. The stainless studs, nuts and washers for the 219MW Belgian offshore wind farm have been delivered to Bladt Industries by Swedish manufacturer BUMAX under a SEK 1.7 million (approx. EUR 160,000) contract. […]