369 results found for 'port of esbjerg'

369 results found for 'port of esbjerg'
Order results by

A list of search results

  • 5 October 2017
    Ports & Logistics

    MHI Vestas today (5 October) informed that it officially opened the Power Converter Modules (PCM) factory at the Port of Esbjerg, adding that the assembly of PCMs for its V164 offshore wind turbine has begun.

  • 15 May 2017
    Contracts & Tenders, Technology

    MHI Vestas has started constructing a power converter module (PCM) assembly and storage facility at the Port of Esbjerg with the hiring ramp-up to fill the positions at the new plant expected for this fall.

  • 10 January 2019
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Brave Tern has loaded the last turbines for the Horns Rev 3 offshore wind farm at the Port of Esbjerg in Denmark. The vessel loaded the final batch of the MHI Vestas units on 10 January and is now set to head towards the project site 25-40km west of Houstrup Strand on […]

  • 23 January 2018
    Ports & Logistics

    Blue Water Shipping (BWS) has put into operation a new 116,000m² multiterminal in the East Port area of the Port of Esbjerg in Denmark, boosting its capabilities to accommodate RoRo vessel traffic, which has increased at the port with the wind turbine industry’s use of RoRo vessels and more operations by the existing RoRo customers.

  • 17 March 2016
    Ports & Logistics

    MHI Vestas Offshore Wind has leased additional area at the Port of Esbjerg to accommodate pre-assembly and shipment of offshore wind turbine components. The company moved into the new East Port in 2013, and carried out five projects from the facility since then. With growing operations, MHI Vestas decided to double its lease at the port. The total space […]

  • 4 December 2012
    Ports & Logistics

    A2SEA’s newly build Sea Installer calls into the Port of Esbjerg around the 6 December. Around New Year the ship will be sailing with two 6MW Siemens test mills to be installed at Gunfleet Sands. Hereafter the Sea Installer will work at the Anholt project where A2SEA then will have four vessels working with installation. […]

  • 2 December 2016
    Ports & Logistics, Vessels

    Today, the Port of Esbjerg is hosting Siemens Wind Power’s official presentation of its first customised “roll on/roll off ” (RoRo) transport vessel, Rotra Vente. “We look forward to seeing the vessels frequently at the Port, where we are currently building two new RoRo ramps and expanding our piers to accommodate even more vessels,” the Port […]

  • 14 May 2020
    Business & Finance, Ports & Logistics

    Nordic infrastructure fund Infranode is preparing an investment of up to DKK 1 billion (circa EUR 134 million) for new infrastructure facilities at the Danish port of Esbjerg which will be used for the offshore wind industry. The investment will go into port facilities for storage, preassembly and manufacturing of components for offshore wind turbines. […]

  • 28 December 2011
    Ports & Logistics

    On 25 December MPI Discovery arrived at the Port of Esbjerg, where it will load wind turbines for the World’s largest offshore wind farm – London Array. Blue Water Shipping is agent on behalf of MPI Offshore, and is responsible for the loading of the wind turbines for London Array – all together 175 turbines […]

  • 5 March 2020
    Ports & Logistics

    Ørsted is building a new 3,000m2 central warehouse at a disused DFDS terminal in Port Esbjerg, Denmark. Slated for completion this summer, the facility will be used for main components for the wind turbine industry, such as gearboxes, generators, and transformers. ”We need more space for our operations going forward, and Port Esbjerg was an […]

  • 24 October 2017
    Business & Finance, Ports & Logistics

    Following the completion of the works on the expansion at the Port of Esbjerg, the port took over the new harbour area in mid-October. 

  • 24 June 2013
    Business & Finance, Ports & Logistics

    The Port of Esbjerg’s new Østhavn (“East Harbour”) opened on Friday, 21 June. This 650,000 square metre expansion of the harbour will consolidate Esbjerg’s position as the leading North Sea port for the wind turbine industry and increase its potential to develop and grow other business areas. The opening ceremony was attended by the Danish […]

  • 18 July 2022
    Contracts & Tenders, Ports & Logistics

    Danish Port of Esbjerg has ordered a second Liebherr LHM 800 crane capable of lifting next-generation offshore wind turbines. The Port of Esbjerg received the first LHM 800 crane in 2019, while the second one is expected to be delivered in 2023. The LHM 800 crane, which has a lifting capacity of 308 tonnes, is […]

  • 18 July 2018
    Ports & Logistics, Vessels, Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up Brave Tern has left the Port of Esbjerg in Denmark loaded with the first four wind turbines to be installed on Vattenfall’s Horns Rev 3 offshore wind farm in the Danish North Sea.

  • 2 October 2017
    Wind Farm Update

    The first monopile foundations have been scheduled for shipping from the Port of Esbjerg to the site of Vattenfall’s 400MW Horns Rev 3 offshore wind farm on 9 October.

  • 13 November 2017
    Vessels, Wind Farm Update

    Components for the first Siemens 7MW wind turbine to be installed at Nissum Bredning are expected to sail out of the Port of Esbjerg late tonight, 13 November, onboard the Osprey Valiant barge. 

  • 19 September 2017
    Vessels

    MPI Offshore’s wind turbine installation vessel MPI Adventure has left the Port of Esbjerg, Denmark, with a final set of turbine components to be installed on the 400MW Rampion offshore wind farm.

  • 5 August 2016
    Vessels, Wind Farm Update

    Denmark’s Port of Esbjerg is currently a proverbial beehive of activity as major offshore wind turbine makers are working on a number of projects located in the North Sea and the English Channel. The photo above was taken on August 02 and gives an overview of the installation projects currently being carried out at the port. Siemens Wind […]

  • 21 October 2022
    Ports & Logistics

    Port of Esbjerg has started construction on a new warehouse facility that will be used for the offshore wind industry with Siemens Gamesa being its first tenant. The new warehouse will expand the port’s storage and assembly facilities to handle ever-growing components used in the offshore wind market. The 6,200-square-metre hall with a height of […]

  • 5 April 2017
    Ports & Logistics, Wind Farm Update

    The Port of Esbjerg informed via social media that it is preparing to handle the components of the Horns Rev 3 offshore wind farm in Denmark.

  • 5 April 2019
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Brave Tern has departed the Port of Esbjerg carrying the first turbines destined for the EnBW Hohe See offshore wind farm in Germany. According to the Danish port, the 132m long vessel sailed out yesterday morning with the first batch of Siemens Gamesa 7MW turbines. Fred. Olsen Windcarrier won the contract for the transport and […]

  • 7 April 2016
    Grid Connection

    The jacket construction and the topside built for the Horns Rev C offshore substation have reached the Port of Esbjerg, from where the pieces will be shipped to the installation site some 20 kilometers off the Danish North Sea coast by the end of this week, weather permitting. The installation of the two pieces is expected to start […]

  • 2 July 2018

    The Port of Esbjerg posted a photo on its social media pages on 2 July, showing 20 wind turbine towers for Borkum Riffgrund II and 14 towers for Horns Rev 3 waiting at the port to be loaded onto vessels and then installed at their respective sites in Germany and Denmark.

  • 18 May 2018
    Ports & Logistics, Vessels, Wind Farm Update

    Swire Blue Ocean’s jack-up Pacific Orca has arrived in the Port of Esbjerg to load the last four MHI Vestas turbines for Vattenfall’s European Offshore Wind Deployment Centre (EOWDC) in the Aberdeen Bay.

  • 7 January 2013
    Ports & Logistics

    Four of the largest wind turbine installation vessels in the world are currently positioned in the Port of Esbjerg, where Blue Water Shipping is acting as agent and handling stevedore assignments. “Sea Installer” is the latest new-build vessel from A2SEA which recently arrived from China to Esbjerg, to be prepared for its first assignment in […]

  • 16 May 2018
    Vessels

    Wind farm installation vessel Seajacks Scylla has arrived at the Port of Esbjerg, Denmark, to undergo demobilization.