  • 13 January 2017
    Authorities, Technology, Wind Farm Update

    DONG Energy has received approval of an amended building consent from German authorities which allows 8MW turbines to be deployed at the 450MW Borkum Riffgrund 2 offshore wind farm. The original consent was granted in December 2011. The latest approval has been granted by the German consenting authority Bundesamt für Seeschifffahrt und Hydrographie (BSH). DONG Energy […]

  • 12 December 2017
    Business & Finance, Wind Farm Update

    After completing the transaction with Global Infrastructure Partners (GIP) for the sale of 50% of the Borkum Riffgrund 2 offshore wind farm yesterday, 11 December, Ørsted now expects its EBITDA in 2017 to materialise at some DKK 21 billion (approx. EUR 2.8 billion), compared to the previously guided range of DKK 19-21 billion.

  • 30 June 2016
    Vessels, Wind Farm Update

    Fred. Olsen Windcarrier will transport and install 56 MHI Vestas 8MW turbines at the Borkum Riffgrund 2 wind farm. The turbine installation is set to start in the second quarter of 2018. “This is our second contract signed with DONG Energy and our first project installing the Vestas 8MW turbines, it is an exciting project and one […]

  • 8 June 2018
    Ports & Logistics, Vessels, Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up Bold Tern is completing its fifth run on Ørsted ‘s Borkum Riffgrund 2 offshore wind farm and is currently installing the 19th MHI Vestas 8MW turbine at the site in the German North Sea.

  • 21 June 2018
    Operations & Maintenance, Ports & Logistics, Wind Farm Update

    Ørsted has opened a new facility in Norddeich, Germany, which will be used for the Borkum Riffgrund 2 project, currently under construction, as well as the developer’s future projects in the German North Sea.

  • 30 November 2017
    Contracts & Tenders, R&D, Wind Farm Update

    MacArtney has won a contract for the supply of two 150 kN and 200 kN electrical cable pulling winches for operation on the Borkum Riffgrund 2 offshore wind farm.

  • 14 June 2018
    Ports & Logistics, Wind Farm Update

    Poland’s ST3 Offshore has sent off the last shipment of suction bucket jacket foundations built for Ørsted’s Borkum Riffgrund 2 offshore wind farm in the German North Sea.

  • 27 February 2017
    Business & Finance, Grid Connection, Technology, Wind Farm Update

    Dutch offshore structures manufacturer HSM Offshore has contracted compatriot Heinen & Hopman to fabricate and install the HVAC (Heating, Ventilation and Air Conditioning) system for the 450MW Borkum Riffgrund 2 Offshore High Voltage Substation (OHVS) to be installed in the German North Sea in 2018.

  • 1 November 2018
    Wind Farm Update

    Ørsted is expecting a faster ramp-up of generation from the 450MW Borkum Riffgrund 2 offshore wind farm due to good progress on offshore construction which will be completed in the fourth quarter of 2018.

  • 31 May 2018
    Ports & Logistics, Vessels, Wind Farm Update

    Fred. Olsen Windcarrier has devised a solution which allows the jack-up Bold Tern to simultaneously perform bunkering and loading of wind turbine components for the Borkum Riffgrund 2 project at the Port of Esbjerg.

  • 31 July 2018
    Ports & Logistics, Vessels, Wind Farm Update

    GeoSea’s jack-up vessel Innovation has installed the last of the twenty suction bucket jacket foundations on Orsted’s 450MW Borkum Riffgrund 2 offshore wind farm in the German North Sea.

  • 30 April 2018
    Ports & Logistics, Vessels, Wind Farm Update

    GeoSea’s jack-up Innovation has arrived at Ørsted’s Borkum Riffgrund 2 wind farm in the German North Sea to install the first suction bucket jacket foundations.

  • 5 June 2018
    Wind Farm Update

    GeoSea’s jack-up vessel Innovation has installed the first out of a total of 20 suction bucket jacket foundations at Ørsted’s Borkum Riffgrund 2 offshore wind farm in the German North Sea.

  • 5 March 2018
    Ports & Logistics, Vessels, Wind Farm Update

    Jan De Nul’s wind turbine installation vessel Vole au vent has left the port of Eemshaven loaded with the first set of monopiles and transition pieces to be installed on the 450MW Borkum Riffgrund 2 wind farm in the German North Sea.

  • 1 December 2017
    Contracts & Tenders, Vessels, Wind Farm Update

    MHI Vestas Offshore Wind has awarded Vroon’s VOS Start with a contract to support the commissioning phase of the Borkum Riffgrund 2 offshore wind farm from spring 2018.

  • 1 March 2018
    Operations & Maintenance, Ports & Logistics, Wind Farm Update

    ST3 Offshore has sent off a barge carrying the first three jackets for Ørsted’s Borkum Riffgrund 2 offshore wind farm from its serial manufacturing plant in Stettin, Poland, to Cuxhaven, Germany.

  • 23 February 2018
    Ports & Logistics, Vessels

    Jan De Nul’s wind farm installation vessel Vole au vent arrived in the Port of Eemshaven last week to be equipped with a hydraulic pile hammer and a noise mitigation system ahead of foundation installation works on the Borkum Riffgrund 2 offshore wind farm.

  • 16 February 2018
    Ports & Logistics, Vessels, Wind Farm Update

    Jan De Nul’s jack-up vessel Vole au vent has left a shipyard in Poland where the vessel underwent certain modifications to the layout of the deck and is now ready for the Borkum Riffgrund 2 offshore wind farm project.

  • 9 March 2018
    Ports & Logistics

    Heli Service’s first flight for Ørsted’s 450MW Borkum Riffgrund 2 offshore wind farm departed on 8 March. The first flight left to the jack-up vessel Vole au vent carrying employees of Ørsted and the vessel provider Jan de Nul. Following a tender process in 2017, the two companies signed a contract for the transport of passengers, […]

  • 12 August 2022
    Business & Finance, Wind Farm Update

    Keppel Corporation Limited and Keppel Infrastructure Fund Management are jointly investing EUR 305 million to acquire a 50.01 per cent stake in a special purpose vehicle that holds 50 per cent of the Borkum Riffgrund 2 offshore wind farm in the German North Sea. The special purpose vehicle is currently wholly owned by Gulf International […]

  • 3 September 2018
    Vessels, Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up installation vessel Bold Tern installed the final MHI Vestas 8MW turbine on Ørsted’s Borkum Riffgrund 2 wind farm on Friday, 31 August, completing the project ahead of schedule.

  • 23 August 2018
    Technology, Wind Farm Update

    The Norwegian Geotechnical Institute (NGI) has designed and installed Structural Health Monitoring (SHM) systems on two of 20 suction bucket jackets at Ørsted’s Borkum Riffgrund 2 offshore wind farm.

  • 16 May 2017
    Business & Finance, Operations & Maintenance, Wind Farm Update

    DONG Energy has once again selected the Papenburg-based Johann Bunte Bauunternehmung as the general contractor on the project to expand the existing offshore wind farm operations and maintenance (O&M) centre in Norden-Norddeich, Germany.

  • 11 June 2018
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Bold Tern has installed the first MHI Vestas 8MW turbine on a suction bucket jacket foundation at the Borkum Riffgrund 2 offshore wind farm.

  • 2 March 2018
    Ports & Logistics, Wind Farm Update

    The barges and coasters carrying jacket foundations and suction buckets to be installed on Ørsted’s Borkum Riffgrund 2 wind farm in the German North Sea have started arriving at the port of Cuxhaven.

  • 13 January 2017
    Business & Finance, Wind Farm Update

    Following the approval from the German consenting authority ‘Bundesamt für Seeschifffahrt und Hydrographie’ (BSH), DONG Energy placed an order with MHI Vestas Offshore Wind for the 450MW Borkum Riffgrund 2 project, marking the largest ever order for the wind turbine manufacturer.