145 results found for 'Formosa 1 Phase 1'

145 results found for 'Formosa 1 Phase 1'
Order results by

A list of search results

  • 16 January 2019
    Business & Finance, Contracts & Tenders, Operations & Maintenance

    FairWind has signed a Letter of Intent with Siemens Gamesa to collaborate on turbine pre-assembly for the Formosa 1 Phase 2 offshore wind project in Taiwan. Under the agreement, FairWind will hire and train Taiwanese technicians to prepare them for the pre-assembly operations, which are scheduled to begin in the spring this year. The training […]

  • 8 June 2018
    Business & Finance, Wind Farm Update

    Formosa 1, Taiwan’s first offshore wind farm, has reached financial close.

  • 29 October 2019
    Wind Farm Update

    Taiwan’s Formosa 2 offshore wind farm has reached financial close, Macquarie’s Green Investment Group (GIG) said. Formosa 2 has been jointly developed by Macquarie Capital (75%) and Swancor Renewable Energy (25%). GIG will now play a role in delivering the project through its construction phase. The 376MW offshore wind project located off the coast of Miaoli […]

  • 19 February 2019
    Operations & Maintenance, Wind Farm Update

    Siemens Gamesa has started producing the blades for the Formosa 1 Phase 2 offshore wind project in Taiwan. The company said the blades were cast at its Aalborg factory in Denmark using Swancor resin and hardener. Siemens Gamesa won the contract to supply 20 SWT-6.0-154 turbines, which will produce a capacity of 120MW, for the project in April last […]

  • 9 July 2019
    Contracts & Tenders, Vessels

    CWind Taiwan has secured two crew transfer vessel (CTV) charters for the Formosa 1 Phase 2 offshore wind farm in Taiwan. CWind Taiwan secured a 90-day extension with Formosa Offshore Wind for the Taiwan-flagged Ocean Surveyor 3 in support of the project’s ongoing phase 1 maintenance requirements. The second contract was secured with Jan De Nul for […]

  • 29 May 2019
    Grid Connection

    The installation of inter-array cables at the Formosa 1 Phase 2 offshore wind farm in Taiwan is scheduled to begin in June. Jan De Nul’s cable laying vessel Willem de Vlamingh will carry out the installation of 20 cables at the project site from 1 June to 30 September. The Luxembourg-based company is in charge of the design, procurement and […]

  • 17 June 2019
    Contracts & Tenders

    Jan De Nul has secured the engineering, procurement, construction and installation contract (EPCI) for foundations and subsea cables at the Formosa 2 offshore wind project in Taiwan. Jan De Nul Group is responsible for the design, fabrication and installation of the jacket foundations, as well as for the design, supply and installation of subsea cables […]

  • 29 October 2019
    Wind Farm Update

    Jan De Nul has completed the EPCI scope for foundations, power cables, and scour protection on the Formosa 1 (Phase 2) offshore wind farm in Taiwan. Jan De Nul engineered, procured, and installed twenty offshore wind turbine foundations consisting of a monopile and transition piece with a grouted connection. Around the monopile foundations, 56,000 tonnes […]

  • 2 March 2017
    Authorities, Business & Finance, Wind Farm Update

    The European Commission has approved, under the EU Merger Regulation, the proposed acquisition of joint control over Formosa 1 International Investment of Taiwan by DONG Energy, Australia’s Macquarie and Swancor Holding of Taiwan.

  • 12 December 2018
    Authorities, Business & Finance, Wind Farm Update

    Swancor has signed a power purchase agreement (PPA) with Taipower for the Formosa 2 offshore wind farm.

  • 20 March 2019
    Operations & Maintenance, Technology

    SeaRoc has secured a contract to supply its marine management system SeaPlanner to support the construction of the Formosa 1 Phase 2 offshore wind project in Taiwan. The deal comes as part of SeaRoc’s strategic partnership with Specialist Marine Consultants (SMC), which is delivering marine coordination services for the 120MW project. SMC will be responsible for […]

  • 19 December 2016
    Wind Farm Update

    IHC IQIP today informed its S-2000 Hydrohammer was used to install two monopiles for the first two Formosa 1 offshore wind turbines in Taiwan.  The company delivered the S-2000 Hydroammer with a 5.5m pile sleeve to Jiangsu Longyuan Zhenhua Marine Engineering Co. Ltd, which carried out the installation of foundations for the project, developed by Swancor/Formosa Wind Power […]

  • 9 July 2019
    Contracts & Tenders, Vessels

    Seajacks International has conditionally been awarded a contract with Siemens Gamesa for the transport and installation of wind turbines at the Formosa 2 offshore wind farm in Taiwan. The 376MW Formosa 2, developed by Macquarie Capital and Swancor Renewable Energy, will consist of 47 SG 8.0 – 167 offshore wind turbines. Installation is scheduled for […]

  • 24 September 2019
    Business & Finance

    Waves Group is currently providing marine warranty surveyor services at the Formosa 1 Phase 2 offshore wind farm in Taiwan. The UK-based company is in charge of providing the marine warranty surveyor services for the installation of turbines, foundations, and infield and export cables. According to Waves Group, the contract began in October last year and will […]

  • 29 October 2019
    Contracts & Tenders, Wind Farm Update

    Siemens Gamesa has received a firm order for the 376MW Formosa 2 offshore wind farm project in Taiwan from partners Macquarie’s Green Investment Group and Swancor Renewable Energy. The project, located in Miaoli county, will consist of 47 units of the SG 8.0-167 DD offshore wind turbine and construction is expected to begin in 2020. The wind […]

  • 7 October 2015
    Vessels, Wind Farm Update

    A2SEA has signed a contract to install two foundations and two Siemens 4MW turbines on the Taiwanese project Formosa 1, developed by Swancor/Formosa Wind Power CO., Ltd. The foundations and turbines will be installed from June 2016 by the vessel M/V TORBEN, formerly known as Friedrich Ernestine, owned by RWE. A2SEA will be responsible for ship management […]

  • 25 December 2020
    Contracts & Tenders, Operations & Maintenance

    South Korean autonomous drone solutions provider Nearthlab has completed a turbine inspection at the Formosa 1 Phase 2 wind farm offshore Taiwan. In partnership with Siemens Gamesa Renewable Energy and Formosa I Wind Power, Nearthlab performed the inspection on the wind farm’s Siemens Gamesa 6 MW wind turbines. Drone inspection has become a favorable option […]

  • 6 November 2018
    Business & Finance, Contracts & Tenders, Ports & Logistics, Wind Farm Update

    Jan De Nul has signed a Memorandum of Understanding (MoU) with the Taiwan International Ports Corporation (TIPC) to establish a logistics hub at the Taichung Port for the Formosa 1 Phase 2 project.

  • 5 July 2019
    Business & Finance, Contracts & Tenders

    Siemens Gamesa has signed a Memorandum of Understanding with Formosa Plastics Corporation for offshore wind in Taiwan. According to the company, the agreement adds up to a series of earlier agreements with local and international parties to promote a competitive supply chain. To remind, Siemens Gamesa inked the first local supply agreements in Taiwan last year by […]

  • 6 January 2016
    Operations & Maintenance, Vessels, Wind Farm Update

    A2SEA is currently planning the installation of two foundations and two Siemens 4MW turbines on the Taiwanese project Formosa 1, scheduled to start in June 2016. The foundations and turbines will be installed by M/V Torben, formerly known as Friedrich Ernestine. A2SEA is operating the vessel under a bareboat charter with a team of A2SEA crew. […]

  • 22 February 2019
    Contracts & Tenders, Grid Connection, Wind Farm Update

    UK-based Correll Services Ltd has secured a contract to provide subsea and land cable termination and testing works on the Formosa 1 Phase 2 offshore wind farm in Taiwan. The contract has been awarded by Formosa 1 project turnkey contractor Jan De Nul Group. Correll Services – a specialist in high voltage, low voltage and fibre […]

  • 26 June 2018
    Contracts & Tenders

    EEW SPC and Jan de Nul have signed a contract for the production of 20 monopile foundations for the Formosa 1 Phase 2 offshore wind farm in Taiwan. 

  • 20 August 2018
    Contracts & Tenders, Operations & Maintenance

    The Thailand-based oil & gas company CUEL Limited has secured a contract with Jan De Nul for the fabrication and supply of 20 transition pieces for the Formosa 1 Phase 2 project in Taiwan, marking its first offshore wind contract.

  • 20 August 2019
    Wind Farm Update

    Jan De Nul has completed the installation of all 20 turbine foundations at the Formosa 1 Phase 2 offshore wind farm in Taiwan. Seaway Yudin began installing the foundations at the beginning of June at the project site some 6km off the west coast of the Miaoli district in the Taiwan Strait. Germany’s EEW SPC produced the monopiles and Thailand’s CUEL Limited manufactured […]

  • 20 June 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    UK-based JDR Cable Systems has been selected by Jan De Nul Group to manufacture and supply inter-array, export and land cables for Taiwan’s Formosa 1 development.

  • 2 May 2018
    Contracts & Tenders, Vessels, Wind Farm Update

    Seajacks has won a contract from Siemens Gamesa to install 20 6MW turbines at the Formosa 1 Phase 2 offshore wind farm in Taiwan.