154 results found for 'Orion'

154 results found for 'Orion'
Order results by

A list of search results

  • 18 April 2017
    Business & Finance, Technology, Vessels

    Finnish technology group Wärtsilä is to supply the engines and other propulsion machinery for Orion, DEME Group’s wind farm installation vessel being built at the Cosco shipyard in China.

  • 16 March 2022
    Business & Finance, Technology

    Dutch offshore access provider Ampelmann has sold the first W-type gangway to offshore shipping company Olympic Subsea ASA. The new motion compensation system will be permanently fixed on Olympic Orion in 2023 when the vessel is expected to be converted from a multi-purpose support vessel (MPSV) into a commissioning service operation vessel (CSOV). The W-type […]

  • 31 May 2019
    Vessels

    Dordrecht-based Safeway BV has won a contract to deliver its Osprey-type motion compensated offshore access system for DEME Offshore’s installation vessel Orion.   According to Safeway, the most unique feature of this custom made Safeway walk-to-work system is that the gangway is vertically integrated in a specially designed staircase, which means that the ‘plug and play’ […]

  • 25 June 2020
    Vessels, Wind Farm Update

    The Seajacks Scylla jack-up vessel will start installing jacket foundations at the Moray East offshore wind farm in July, according to a document listing vessels involved in the construction on Moray East project’s website, updated on 18 June. The vessel’s AIS data shows that Seajacks Scylla arrived at the Port of Nigg early in the […]

  • 7 July 2020
    Vessels, Wind Farm Update

    The first jacket foundation is now in place at the Moray East offshore wind farm in Scotland. DEME Offshore, in charge of the installation works, is currently using the Seajacks Scylla jack-up vessel to install the jackets. The 950 MW offshore wind project will comprise 100 MHI Vestas 9.5 MW wind turbines and three offshore substations, […]

  • 6 March 2015
    Vessels

    The operational management of the Acta Orion, the flagship of Den Helder based company Acta Marine, will be carried out by specialist ship managers SeaMar Services, also based in Den Helder. Both parties signed an agreement for a number of years. The Acta Orion, a 108m long and 16m wide wind farm support vessel, will […]

  • 20 April 2018
    Vessels

    Liebherr-MCCtec Rostock GmbH marked the production start of the HLC, Liebherr’s biggest offshore crane, which will be mounted on DEME Group’s Orion, a next-generation offshore installation vessel.

  • 29 September 2020
    Vessels

    Liebherr has started preparations for the recovery of its HLC 295000 offshore crane on board the Orion vessel, whose hook broke this May, leaving several people injured and damaging the crane and the vessel’s deck. The repair project, which will be completed in the course of 2021, is starting this month with crane salvage and […]

  • 28 February 2020
    Vessels

    The 145-metre main crane boom has been installed on DEME Group’s DP3 offshore installation vessel Orion at Liebherr’s facility in Rostock, Germany. The Liebherr HLC 295000 crane has a lifting capacity of 5,000 tonnes and an outreach of more 35 metres. It could lift nine fully loaded Airbus A380 aircraft in one go, DEME said. […]

  • 26 July 2022
    Vessels, Wind Farm Update

    DEME Offshore has completed the installation of the final XXL monopile at the 257 MW Arcadis Ost 1 offshore wind farm in the German Baltic Sea. This was the first project executed by DEME’s new floating installation vessel, Orion, which installed the foundations using its DP3 system. Manufactured by Steelwind in Germany, the 28 XXL […]

  • 28 April 2014
    R&D, Technology

    Orion Energy Centre (OEC) has recently completed a project for one of its first commercial customers, Resolute Marine Energy, Inc. (RME), a US-based wave technology developer with headquarters in Boston, Massachusetts.  OECs facilities and expertise will be used to carry out scale model wave tank testing on RMEs new ‘submerged flap wave energy converter’ – […]

  • 20 July 2017
    Vessels, Wind Farm Update

    Acta Marine informed today, 20 July, that its walk-to-work construction support vessel Acta Orion is providing accommodation and walk-to-work for Siemens on DONG Energy’s Race Bank offshore wind farm.

  • 28 March 2018
    Contracts & Tenders, Operations & Maintenance, Vessels, Wind Farm Update

    Acta Marine has won a contract to assist Tideway B.V. with its cable pull in and testing and termination campaign on the Merkur offshore wind farm in the German North Sea. Under the contract, Acta Marine will charter its walk-to-work (W2W) construction support vessel Acta Orion, which will be performing accommodation and W2W services on the […]

  • 24 May 2019
    Vessels

    Norwegian ship operator Olympic Subsea has entered into an agreement with Adwen GmbH, a subsidiary of Siemens Gamesa, for the vessel Olympic Orion. The contract period is firm for six months with further options. The contract commencement is in the second quarter of 2019. Olympic Subsea did not disclose any further contract details. ”We see it […]

  • 16 August 2022
    Grid Connection, Vessels

    DEME’s vessel Orion has begun the installation of the jacket foundation for the Hollandse Kust West Alpha platform in the Dutch sector of the North Sea. The jacket set sail from the Port of Vlissingen to the offshore construction site on 14 August, a few weeks after the load out at the Heerema Fabrication Group […]

  • 30 May 2022
    Vessels, Wind Farm Update

    The installation of 28 XXL monopiles for 27 wind turbines and one substation of the Arcadis Ost 1 offshore wind farm is about to begin as DEME Offshore’s installation vessel Orion has arrived at the Port of Roenne, the project’s storage and marshaling port. According to available AIS data, Orion arrived at the port this […]

  • 11 February 2022
    Vessels

    The US crew transfer vessel (CTV) owner and operator American Offshore Services (A-O-S) has entered into a strategic partnership with Orion Infrastructure Capital to build what are said to be “state-of-the-art CTVs designed to transport technicians and materials in varied offshore conditions”. Under the arrangement, Orion will provide financing to build a series of CTVs […]

  • 9 June 2022
    Wind Farm Update

    DEME Offshore’s installation vessel Orion has installed the first of 28 monopile foundations at the Arcadis Ost 1 offshore wind farm in the German Baltic Sea. Manufactured by Steelwind in Germany, the foundation will carry the wind farm’s substation. It has a length of 110 metres, a diameter of 9.5 metres, and a weight of […]

  • 1 January 2021
    Business & Finance, Jobs & Recruitment, Technology, Vessels, Wind Farm Update

    The offshore wind sector was busy throughout the last year and we saw more than a few big news. In this article, our editorial team brings a list of those that were most read on OffshoreWIND.biz in 2020. Orion’s Heavy Lift Crane Collapses – Video A heavy-lift crane installed on the offshore installation vessel Orion […]

  • 30 May 2023
    Vessels

    Monopile installation work has started at the Vineyard Wind 1 site offshore Massachusetts, the first large-scale offshore wind farm in the US and the Americas. DEME’s installation vessel Orion which, according to AIS data available online, will reach the project site today (30 May), will install the first six monopiles and accompanying transition pieces (TPs) […]

  • 28 May 2015
    Technology, Vessels

    ACO Marine has won an order to supply its new range Clarimar MF wastewater treatment system for installation aboard Acta Orion, the wind farm support vessel (WFSV) under construction for Acta Marine at the Partner Stocznia shipyard in Police, Poland. Acta Orion will be the first reference for ACO Marine’s next generation sewage treatment system, […]

  • 19 June 2015
    Vessels

    Norwegian supplier of modern offshore support vessels, Simon Møkster Shipping, has been awarded a contract with Acta Marine Offshore. According to the company, Stril Server was awarded a ten weeks contract with 5×1 weeks options. The vessel will start working in the Dutch sector in early August. Stril Server will act as a forerunner for […]

  • 28 February 2020
    Wind Farm Update

    EEW Offshore Structures Britain (EEW OSB) has upended the first transition piece for the Hornsea Two offshore wind project in the UK. In June 2019, Ørsted placed an order with EEW Special Pipe Constructions for 30 transition pieces for the 1.4GW project. The remaining 135 transition pieces will be manufactured and delivered by Denmark’s Bladt Industries. EEW […]

  • 8 April 2019
    Vessels

    Acta Marine’s offshore wind service vessel Acta Centaurus left Ulstein Verft in Norway on Saturday, 6 April, to start her sea trials. The tests carried out so far have been successful, according to Ulstein’s project manager. The 93-metre vessel has a 3,200t load capacity, a 6m draft, and will provide accommodation for up to 120 persons. The […]

  • 28 December 2020
    Wind Farm Update

    The 103rd and final jacket foundation has been installed at the Moray East offshore wind farm site in Scotland. The Seajacks Scylla jack-up vessel installed the first three-legged jacket in July. The wind farm’s three offshore transformer modules (OTMs), together with their three jacket foundations, have been in place since mid-September. DEME’s installation vessel Orion, initially scheduled to be […]

  • 26 July 2023
    Wind Farm Update

    DEME’s specialised floating installation vessel Orion has installed the offshore substation for the 800 MW Vineyard Wind 1 wind farm, a first in the US, said the Belgium-based company. With a weight of more than 3,500 tonnes, this was the single heaviest lift of the entire construction campaign, according to Vineyard Wind, a joint venture between […]