493 results found for 'Hornsea Two'

493 results found for 'Hornsea Two'
Order results by

A list of search results

  • 11 February 2021
    Wind Farm Update

    Around 20 per cent of foundations has been installed at the 1.4 GW Hornsea Two, which is soon to become the world’s largest offshore wind farm, Ørsted said. The export cable installation works are on schedule and turbine installation is set to commence in the second half of this year, the project’s owner and developer […]

  • 21 October 2021
    Wind Farm Update

    Ørsted’s 1,386 MW Hornsea Two offshore wind farm, soon to be the world’s largest, has reached several significant construction milestones, with more to come in the coming days. All of the wind farm’s turbine foundations have now been installed, as well as the project’s offshore substation at the North Sea site 89 kilometres off the […]

  • 9 August 2021
    Operations & Maintenance, Ports & Logistics, Vessels, Wind Farm Update

    Ørsted’s new service operations vessel (SOV) Wind of Hope has arrived in the Port of Grimsby in the UK to prepare for working out at sea on the world’s largest offshore wind farms. Up to 60 of Ørsted’s wind turbine technicians will call the 84-metre vessel home for two weeks at a time, whilst they […]

  • 9 August 2021
    Ports & Logistics, Wind Farm Update

    The Rostock-based EEW Special Pipe Constructions GmbH has loaded out the last five monopiles for Ørsted’s Hornsea Two offshore wind farm. The final five monopiles were loaded out at EEW SPC’s quay on 30 July. In the past eleven months, a total of 165 monopiles was loaded for the project by two self-geared vessels. The […]

  • 30 April 2020
    Grid Connection, Wind Farm Update

    ABB has delivered and installed three shunt reactors in the onshore substation of the Hornsea Project Two offshore wind farm in the UK. In April 2018, Ørsted and Balfour Beatty started the construction of the onshore substation in North Killingholme. The project’s 39km onshore cable route runs from Horseshoe Point, east of Tetney, to the […]

  • 26 April 2022
    Business & Finance, Grid Connection, Wind Farm Update

    NKT has commissioned the 220 kV HVAC export cable system connecting the 1.3 GW Hornsea Two offshore wind project to the UK grid. NKT manufactured the power cables for the project at its factory in Karlskrona, Sweden. The installation of the subsea cables was completed by the cable-laying vessel NKT Victoria. “Constructing a project of […]

  • 5 August 2020
    Wind Farm Update

    Per Aarsleff A/S has produced 89 out of the 165 concrete working platforms (CWPs) for Ørsted’s 1.4 GW Hornsea Project Two offshore wind farm. The CWPs are being built at Per Aarsleff’s concrete precast factory in Poland, Aarsleff BIZ, for Bladt Industries and EEW OSB, which are producing 135 and 30 transition pieces for the […]

  • 2 April 2019
    Contracts & Tenders

    Ørsted has contracted AMS Trenchless Specialists to conduct part of the onshore cable works for the Hornsea Project Two offshore wind farm in the UK. AMS Trenchless Specialists will conduct Horizontal Directional Drilling (HDD) at the landfall site in Horseshoe Point where the offshore cables meet the onshore cables under the more than GBP 1 million worth contract. Using […]

  • 5 December 2018

    Semco Maritime and ISC Consulting Engineers have completed the design of the offshore substation and the Reactive Compensation Station (RCS) for the Hornsea Project Two offshore wind farm.

  • 24 July 2019
    Contracts & Tenders, Grid Connection

    Seaway 7, a unit of Subsea 7, has won a contract for the installation of the inter-array grid cable system at the Hornsea Project Two offshore wind farm in the UK. In addition to the submarine cable installation works, Seaway 7 will undertake a pre-installation submarine cable route survey, perform pre-installation boulder clearance activities and […]

  • 6 November 2019
    Contracts & Tenders

    Ørsted has contracted LOC Group to carry out Marine Warranty Surveyor (MWS) services for the Hornsea Project Two offshore wind farm in the UK. Under the 18-month agreement, LOC London and LOC Singapore will execute all MWS work on the project’s substations. “Hornsea Two is a game-changing renewable energy project in terms of both scale […]

  • 12 September 2018
    Business & Finance

    Ørsted is holding a supply chain event for the Hornsea Project Two offshore wind project in the UK North Sea.

  • 28 February 2020
    Wind Farm Update

    EEW Offshore Structures Britain (EEW OSB) has upended the first transition piece for the Hornsea Two offshore wind project in the UK. In June 2019, Ørsted placed an order with EEW Special Pipe Constructions for 30 transition pieces for the 1.4GW project. The remaining 135 transition pieces will be manufactured and delivered by Denmark’s Bladt Industries. EEW […]

  • 21 August 2015
    Business & Finance, Wind Farm Update

    Today, DONG Energy acquired the Hornsea Zone and the project rights to Hornsea Project Two and Three, which have the potential of 3 gigawatts (GW) of offshore wind capacity. This follows DONG Energy’s acquisition of Hornsea Project One, a 1,200 megawatt (MW) offshore wind project in the Round 3, which was announced in February 2015. […]

  • 10 August 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    The UK founded infrastructure group Balfour Beatty has secured a contract to build the onshore substation for Ørsted’s Hornsea Project Two offshore wind project on the East coast of England.

  • 6 July 2018
    Wind Farm Update

    Fugro has commenced marine site characterisation work at the Hornsea Project Two offshore wind farm site under a contract with Ørsted for geotechnical site investigation, which follows earlier contracts for geophysical investigation services at the site.

  • 18 January 2019
    Business & Finance

    Ørsted is holding a series of community information events about the onshore cable route for the Hornsea Project Two offshore wind project in the UK. According to the Danish company, the aim of the events is that local people in North East Lincolnshire and East Lindsey find our more about the onshore cabling works for the […]

  • 17 August 2020
    Wind Farm Update

    EEW Offshore Structures Britain (EEW OSB) has loaded out its first batch of transition pieces (TPs) for the Hornsea Project Two offshore wind farm in the UK. The company will deliver 30 transition pieces for the project. Hornsea Two will comprise 165 Siemens Gamesa 8 MW turbines on monopile foundations, and an offshore substation and a reactive […]

  • 20 May 2020
    Technology

    Boskalis has taken delivery of a purpose-built pre-lay plough from Soil Machine Dynamics Ltd (SMD) for use at Ørsted’s Hornsea Two offshore wind project in the UK. Boskalis will use the Megalodon plough to install 380km of export cables which will connect the project’s offshore substation to the onshore substation in Killingholme, Lincolnshire. According to […]

  • 8 June 2020
    Contracts & Tenders

    Spectrum Geosurvey has secured a construction survey support contract for Ørsted’s Hornsea Two offshore wind project in the UK. Under the two-year contract, Spectrum will provide on-demand geophysical survey capacity for the wind farm. “We are delighted to secure another long-term contract allowing us to further invest in new technology and our highly skilled workforce,” […]

  • 15 February 2018
    Authorities, Business & Finance, Grid Connection, Wind Farm Update

    Ørsted has sent an application to the UK’s Planning Inspectorate to reduce the maximum number of offshore HVAC collector substations permitted under the Hornsea Project Two Development Consent Order (DCO).

  • 11 August 2022
    Business & Finance, Wind Farm Update

    All wind turbines have been fully commissioned and are commercially operational at the 1.3 GW Hornsea Two in the UK which will soon become the world’s biggest single operational offshore wind farm. The project’s owner and developer, Ørsted, expects the wind farm to be fully commissioned later this month, after the remaining reliability runs are […]

  • 11 July 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    ABB has won orders worth over USD 150 million from Danish energy company Ørsted to supply a range of technologies that will help integrate and transmit energy from the Hornsea Project Two offshore wind farm to the UK grid.

  • 8 September 2020
    Wind Farm Update

    The first six transition pieces for the Hornsea Two offshore wind project have arrived from the UK at the Buss Terminal in Eemshaven, Netherlands. Over the next months, Buss will receive a total of 165 foundation sets, which will be handled and stored at the terminal. The foundations will then be loaded onto DEME Group’s […]

  • 26 January 2021
    Vessels, Wind Farm Update

    Ørsted is set to welcome three new hybrid crew transfer vessels (CTVs) to assist with the construction at the Hornsea Two offshore wind farm. Northern Offshore Services (N-O-S) will take delivery of its 39m Energizer in the spring and MHO-Co is due to deliver its two 35m CTVs in the summer. The vessels will be […]

  • 3 September 2019
    Ports & Logistics, Wind Farm Update

    Ørsted has officially opened the Hornsea Two Offshore Construction Base (HTOCB) at Humberside Airport in Lincolnshire. The building, formerly a police station at the airport, will now house around 30 Ørsted employees who will be working around the clock to construct the 1.4GW wind farm. Hornsea Two, located 89 kilometres off the Yorkshire Coast, will […]