477 results found for 'Moray East'

477 results found for 'Moray East'
Order results by

A list of search results

  • 15 July 2019
    Contracts & Tenders, Grid Connection

    Siemens has placed multi-million pound contracts with companies across the UK for the construction of the transmission infrastructure for the Moray East offshore wind farm. As the lead contractor for onshore transmission infrastructure construction works for the 950MW wind farm, Siemens has placed several subcontracts since work began in September 2018. BAM Nuttall has been […]

  • 6 June 2019
    Contracts & Tenders

    Denmark’s  Welcon has received an order from MHI Vestas to deliver tower sections for the 950MW Moray East wind farm offshore Scotland. In total, Welcon will manufacture and deliver 70 bottom sections, 34 middle sections and 34 top sections for the project. The sections are scheduled to be delivered from the fourth quarter of 2019 until […]

  • 7 February 2019
    Contracts & Tenders, Wind Farm Update

    Engie has signed a Power Purchase Agreement (PPA) with Moray Offshore Windfarm (East) Ltd to purchase 23.3% of the electricity generated from the 950MW Moray East wind farm. The PPA is for a 15-year period, starting from commercial operation of the wind farm which is scheduled to commence in 2022. Engie currently holds a 23.3% […]

  • 22 October 2021
    Operations & Maintenance, Wind Farm Update

    EDP has inaugurated the operations and maintenance center of the 950 MW Moray East offshore wind farm, which will now be controlled by this new infrastructure located in Fraserburgh Port, Scotland. This new operations and maintenance center will now manage this offshore wind farm, in particular by controlling the vessel ‘Alba’, which regularly spends two-week […]

  • 28 December 2020
    Wind Farm Update

    The 103rd and final jacket foundation has been installed at the Moray East offshore wind farm site in Scotland. The Seajacks Scylla jack-up vessel installed the first three-legged jacket in July. The wind farm’s three offshore transformer modules (OTMs), together with their three jacket foundations, have been in place since mid-September. DEME’s installation vessel Orion, initially scheduled to be […]

  • 15 January 2019
    Contracts & Tenders, Operations & Maintenance

    Utility ROV Services (URS) has won a contract to provide boulder relocation services on the 950MW Moray East offshore wind farm in the Scottish waters. The Fife-headquartered company plans to begin the work in the first quarter of the year using its load bearing ROV system UTROV. “This contract is a welcome start to 2019 for […]

  • 8 February 2019
    Business & Finance, Grid Connection, Wind Farm Update

    The TFKable Group has produced the first part of the 220kV onshore high-voltage cable for the Moray East offshore wind farm in the UK. According to the company, the 220kV cable is now ready to be delivered from its Bydgoszcz plant in Poland for the 950MW offshore wind project. TFKable and VolkerInfra won the contract to […]

  • 18 August 2020
    Grid Connection, Wind Farm Update

    The second offshore transformer module (OTM) of the Moray East wind farm is now at its designated location at the site off Scotland, according to the project’s Notice of Operations. OSP2, which was shipped out from Belgium on 30 June, was installed shortly after its jacket foundation and the OSP3 platform were put in place […]

  • 5 October 2020
    Wind Farm Update

    Smulders has sent off the final three upper jackets for the Moray East offshore wind farm from its yard in Hoboken, Belgium, to Newcastle upon Tyne. Smulders will deliver 55 turbine jacket foundations for the project, with the remaining 45 being delivered by Lamprell from its yards in the United Arab Emirates. The 55 jackets are […]

  • 22 December 2020
    Wind Farm Update

    Seajacks Scylla has installed 93 out of the 100 wind turbine jacket foundations at the Moray East wind farm off the Aberdeenshire coast in Scotland, the project’s latest Notice of Operations shows. The jack-up vessel is transporting the jacket foundations to the project site from Global Energy Group’s site in Nigg. The Seajacks Scylla installed […]

  • 27 May 2019
    Wind Farm Update

    The 950MW Moray East wind farm has entered the offshore construction phase with the start of piling operations earlier this month. The piling operations started on 19 May and are expected to take place over a period of approximately eleven months, a Notice of Operations said. Moray East contracted GeoSea NV Geotechnical & Offshore Solutions, […]

  • 17 June 2019
    Authorities, Wind Farm Update

    The Scottish Ministers have given marine consent for the construction and operation of the 850MW Moray West offshore wind project. This clears the way for the project to participate in the next Contracts for Difference (CfD) auction scheduled for this summer. If successful in the auction, the project could enter the construction phase in 2022. The […]

  • 20 November 2020
    Business & Finance, Contracts & Tenders

    The Osprey Group has won a contract to provide handling and storage services for the spare export cable for the Moray East offshore wind farm. Under the contract, the company will receive and store approximately 2,500 metres of subsea cable and approximately 1,500 metres of HDD cable to be received from NKT’s cable laying vessel […]

  • 26 May 2021
    Contracts & Tenders, Vessels

    The Island Crown vessel has started working at the Moray East offshore wind farm site, providing accommodation and walk-to-work (W2W) services during the project construction activities. Island Crown has joined the fleet of vessels deployed on the project after Moray Offshore Windfarm (East) Ltd (MOWEL) awarded Island Offshore with a contract for offshore accommodation and […]

  • 27 October 2017
    Contracts & Tenders, Wind Farm Update

    GeoSea has signed an agreement with Moray Offshore Windfarm (East) Ltd for the supply and installation of turbine and substation foundations, as well as the transport and installation of three offshore substation platforms for the 950MW Moray East offshore wind farm off Scotland.

  • 24 November 2020
    Wind Farm Update

    Seajacks Scylla has 28 jacket foundations to install at the Moray East offshore wind farm, before it wraps up one of the biggest offshore construction works on the project. Only this month (November 2020), the vessel has put in place 18 jackets, so the foundation installation is expected to be completed in January, weather permitting, […]

  • 29 December 2020
    Vessels, Wind Farm Update

    Wind turbine installation at the Moray East offshore wind farm is scheduled to start in the first days of the next year, around 5 January. The wind turbines will be installed by the Bold Tern jack-up vessel, with the commissioning work to be done from Acta Centaurus, supported by two crew transfer vessels, HST Harri […]

  • 10 August 2020
    Grid Connection, Wind Farm Update

    The first of the three Offshore Transformer Modules (OTMs), ME OSP 3, has been installed at the 950 MW Moray East wind farm offshore Scotland. Siemens Energy shipped out the wind farm’s first OTM, ME OSP 2, for offshore installation on 30 June. This OTM will be installed later this week, a spokesperson for DEME […]

  • 6 September 2021
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Blue Tern has seven more Vestas 9.5 MW units to install at the 100-turbine Moray East offshore wind farm in Scotland. The first wind turbines were installed at the project site some 22 kilometres off Aberdeenshire in January by the installation vessel Bold Tern, which left the site in May […]

  • 2 March 2023
    Business & Finance, Wind Farm Update

    Japan’s Inpex Corporation has acquired a 16.7 per cent stake in the 950 MW Moray East offshore wind farm. Moray East is located approximately 22 kilometers off the Moray East coast of Scotland in the United Kingdom. The wind farm has been in operation since April 2022. The acquisition was enabled through an agreement between […]

  • 7 June 2019
    Ports & Logistics

    DEME Offshore has selected Global Energy Group to provide the Port of Nigg as a staging port for the Moray East offshore wind farm. Under the contract, the Port of Nigg will be used for receiving the completed turbine jacket foundations destined for the 950MW project. “Using Nigg for jackets complements our previous announcement of the Port […]

  • 7 December 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Siemens has selected Smulders to build the three Offshore Transformer Modules (OTMs) for the 950MW Moray East offshore wind farm.

  • 13 November 2020
    Authorities, Contracts & Tenders, Grid Connection

    Ofgem will open a tender round for the offshore transmission licences for the Moray East and Triton Knoll offshore wind farms on 30 November. The authority issued a notice on 12 November, informing that the projects fulfilled all necessary conditions in accordance with regulation, including the submitted requests for qualifying projects, received payments and security […]

  • 17 April 2019
    Contracts & Tenders

    The UK-based Granada Material Handling has secured a contract to provide 100 davit crane units for the turbine jacket foundations of the Moray East offshore wind project. Granada is in charge of designing, manufacturing and commissioning Python crane units that will be fitted to each of the project’s 100 jacket foundation platforms. According to the company, each […]

  • 6 May 2021
    Vessels, Wind Farm Update

    32 out of the 100 Vestas V164-9.5MW wind turbines have been installed at the 950 MW Moray East wind farm offshore Scotland. The wind turbine installation is being carried out by Fred. Olsen Windcarrier’s jack-up vessel Bold Tern. The first turbines were installed some 22 kilometres off the Aberdeenshire coast during the second half of […]

  • 7 April 2021
    Contracts & Tenders, Wind Farm Update

    RES has won a contract to provide control point, balancing, and asset monitoring services during commissioning and early operations at the 950 MW Moray East wind farm offshore Scotland. RES’ 24/7/365 Control Centre, based in Glasgow, will work as the interface between Moray East and National Grid to support the energisation of 100 turbines at […]