149 results found for 'Greater Changhua 1 & 2a'

149 results found for 'Greater Changhua 1 & 2a'
Order results by

A list of search results

  • 5 May 2021
    Vessels, Wind Farm Update

    Heerema Marine Contractors’ (HMC) vessel Aegir has started installing jacket foundations at Ørsted’s Greater Changhua offshore wind project site in Taiwan. The vessel is currently installing the jacket for one of the two offshore substations of the Greater Changhua 1 and 2a offshore wind farms. Aegir, which had been undergoing an upgrade at Sembcorp in Singapore […]

  • 28 January 2022
    Ports & Logistics, Vessels, Wind Farm Update

    The jack-up vessel Seajacks Scylla has arrived in the Port of Taichung in Taiwan in preparation for the turbine installation work on the 900 MW Changhua 1 and 2a offshore wind farms. The installation work is expected to start as soon as a favourable window opens. Seajacks Scylla will transport and install 111 Siemens Gamesa 8MW turbines at […]

  • 27 January 2021
    Contracts & Tenders, Wind Farm Update

    Master Builders Solutions has won the grout supply contracts for the Formosa 2, the Changfang and Xidao, and the Greater Changhua 1 and 2a offshore wind projects in Taiwan. In total, Master Builders Solutions will be supplying MasterFlow 9500 and MasterFlow 9800 to 222 offshore foundations over the next three years. “2020 has been a […]

  • 9 August 2019
    Contracts & Tenders

    Heerema Marine Contractors (HMC) has secured a contract for the transport and installation of turbine foundations and the installation of offshore substations at the Greater Changhua 1 and 2a offshore wind projects in Taiwan. HMC will utilize its vessel Aegir for the transportation and installation of 111 turbine foundations and the installation of two offshore substations at […]

  • 16 July 2021
    Ports & Logistics, Vessels, Wind Farm Update

    Offshore construction is in full swing at Ørsted’s 900 MW Changhua 1 and 2a wind farm off Changhua County, Taiwan. The second of the two offshore substation jacket foundations has now been installed at the site. The first substation jacket was installed by Heerema Marine Contractors’ (HMC) vessel Aegir in early May. Ørsted has also […]

  • 11 June 2019
    Contracts & Tenders, Wind Farm Update

    Danish offshore wind developer Ørsted has signed contracts with South Korea’s Samkang M&T and Hyundai Steel Industries for the supply of jacket foundations for the 900MW Changhua 1 and 2a offshore wind project in Taiwan. Samkang M&T will manufacture and deliver 28 jacket foundations, and Hyundai Engineering & Steel Industries 27 units, according to Korean media. […]

  • 22 August 2019
    Contracts & Tenders, Wind Farm Update

    Seajacks International has won a contract by Ørsted for the transport and installation of turbines at the Greater Changhua 1 and 2a offshore wind projects in Taiwan. Seajacks is planning to use its jack-up vessel Seajacks Scylla for the transport and installation of 111 Siemens Gamesa 8MW turbines at the project site located 35-50km off the coast of […]

  • 9 February 2022
    Operations & Maintenance, Vessels, Wind Farm Update

    The first service operation vessel (SOV) built for the Asian offshore wind market completed six days of sea trials offshore Vietnam back in January. The SOV, to be named TSS Pioneer, is being built by Vard at the Vung Tau shipyard in Vietnam. The vessel will soon be delivered to Ta San Shang Marine, a […]

  • 31 January 2019
    Authorities, Wind Farm Update

    Taiwan’s Bureau of Energy has granted Ørsted the establishment permit for the 900MW Changhua 1 and 2a offshore wind project. In the coming weeks, Ørsted will work with the Taiwanese authorities and local stakeholders to reach other outstanding key project milestones, such as completing the supply chain plan and signing the power purchase agreement (PPA), […]

  • 10 September 2020
    Business & Finance

    Ørsted has appointed BNP Paribas, Cathay United Bank and CTBC Bank as Mandate Lead Arranger’s for a potential TWD denominated green bond issuance in Taiwan. The green bond, set to be issued in Q4 2020, represents Ørsted’s second green bond offering in Taiwan. Ørsted intends to issue the new green bonds for the purpose of […]

  • 30 April 2019
    Business & Finance, Wind Farm Update

    Ørsted has taken the final investment decision (FID) on the Changhua 1 and 2a offshore wind farm in Taiwan. Prior to the FID, Taiwan’s Ministry of Economic Affairs approved Ørsted’s local supply chain plan, and subsequently Ørsted has signed a power purchase agreement (PPA) with Taipower at the feed-in-tariff level announced on 30 January 2019. […]

  • 3 January 2019
    Authorities, Business & Finance, Contracts & Tenders, Wind Farm Update

    Ørsted will pause and revisit its project activities, the project timelines, and local commitments in Taiwan after not receiving an establishment permit in time to sign a 2018 power purchase agreement (PPA) with Taipower for the Changhua 1 and 2a projects.

  • 16 April 2020
    Contracts & Tenders

    China Shipbuilding Corporation Taiwan (CSBC) will manufacture 20 transition piece steel structures for Changhua 1 and 2a offshore wind project.

  • 17 March 2021
    Ports & Logistics, Wind Farm Update

    The first wind turbine tower section built for the 900 MW Greater Changhua 1 and 2a offshore wind farm has arrived at the Port of Taichung, Taiwan, Ørsted, the developer of the project, said. This is the first of 333 tower sections in total that are being manufactured locally by the consortium of CS Wind […]

  • 21 April 2020
    Wind Farm Update

    Heerema Fabrication Group is set to manufacture the pre-piling template for the Greater Changhua offshore wind project in Taiwan. The template, which will enable Heerema Marine Contractors to install the piles accurately, consists of three pile sleeves connected by framing, including hydraulically adjustable pile guides and mudmats. Heerema Vlissingen will fabricate the steel structure and […]

  • 31 March 2023
    Business & Finance, Wind Farm Update

    Ørsted has taken the final investment decision (FID) on the 920 MW Greater Changhua 2b and 4 offshore wind farms in Taiwan, moving them into the construction stage. Onshore work and fabrication of components will start this year and the project construction is scheduled to be completed by the end of 2025. The project is […]

  • 27 April 2023
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Ørsted has awarded Taiwan Cogeneration Corporation (TCC) a contract to build the onshore substation for the 920 MW Greater Changhua 2b and 4 offshore wind farms. The contract award follows Ørsted’s final investment decision on the offshore wind farms last month. Under the contract, Star Energy Corporation (SEC), 100 per cent owned by TCC, will […]

  • 21 January 2019
    Business & Finance, Contracts & Tenders

    Ørsted has suspended the execution of contracts with Taiwan Cogeneration Corporation, China Steel Corporation (CSC) and Century Iron and Steel Industrial (CISI) for the developer’s offshore wind projects in Taiwan, Taiwanese media reports. OffshoreWIND.biz has contacted Ørsted to confirm this, with the company yet to respond. The suspended contracts were already ongoing, while for those that […]

  • 20 June 2019
    Business & Finance, Wind Farm Update

    Ørsted has signed a guaranteed five-year syndicated green revolving loan facility for its Greater Changhua offshore wind projects in Taiwan. The NTD 25 billion (circa EUR 714.3 million) green facility attracted 15 banks to join in less than two months, which represents the first time local state-owned banks are involved in financing offshore wind projects, Ørsted said. Ørsted will now […]

  • 22 April 2020
    Contracts & Tenders

    Pulse Structural Monitoring has won a contract to provide digital structural monitoring and insight services and equipment for Ørsted’s Greater Changhua offshore wind project in Taiwan. Pulse is in charge of providing the design, fabrication, yard installation and commissioning of the monitoring instrumentation on three wind turbine foundations. The Acteon company said it will supply […]

  • 13 May 2019
    Grid Connection, Wind Farm Update

    Singapore-based Keppel FELS Ltd has secured a contract from Ørsted to provide two offshore substations for the Greater Changhua wind sites in Taiwan. Valued at more than SGD 150 million (around EUR 98 million), the contract comprises detailed engineering, procurement, construction, testing and commissioning for two 600MW substations. It excludes certain electrical components to be […]

  • 17 May 2023
    Contracts & Tenders, Wind Farm Update

    Ørsted has signed a contract with South Korea’s HSG Sungdong Shipbuilding for the supply of foundations for the 920 MW Greater Changhua 2b & 4 offshore wind farms in Taiwan. Ørsted signed the contract with HSG Sungdong, worth hundreds of billions of Korean won, in the presence of the Danish Ambassador Svend Olling, Ørsted Korea […]

  • 2 August 2023
    Contracts & Tenders, Operations & Maintenance, Wind Farm Update

    Mammoet-Giant Taiwan, a joint venture between the Dutch company Mammoet and Taiwanese Giant Heavy Machinery Service, has been picked by Ørsted Taiwan to provide essential support for the 920 MW Greater Changhua 2b and 4 offshore wind farms. The joint venture has been entrusted with the marshalling and lifting activities for 66 suction bucket jackets. […]

  • 2 October 2020
    Vessels

    Vard Electro has selected Corvus Energy to supply lithium-ion battery-based Energy Storage System (ESS) for the service operations vessel (SOV) being built for Ørsted’s Greater Changhua 1 and 2a wind farms in Taiwan. The SOV is of VARD 4 19 design developed for the complicated and harsh environment in the Taiwan Strait. Currently under construction […]

  • 3 May 2023
    Business & Finance

    World’s leading offshore wind developer, Ørsted, has reported DKK 6.9 billion (EUR 926 million) operating profit (EBITDA) for the first quarter of 2023, DKK 2.5 billion less compared to the same period a year earlier. EBITDA excluding new partnerships in Q1 2023 was DKK 0.9 billion lower than Q1 2022, as Q1 2022 was positively […]

  • 30 January 2019
    Authorities, Contracts & Tenders, Wind Farm Update

    The 900MW Changhua 1 and 2a offshore wind projects will move forward, Ørsted said in response to the announced 6% Feed-in-Tariff reduction, but the final investment decision depends on the outcome of supply contract renegotiations and relevant project milestones being achieved in time to keep the projects on track for commissioning in 2021. Developers who sign their […]