    Cemre Shipyard has launched the first of the three service operation vessels (SOVs) currently under construction for MHI Vestas and Esvagt at its yard in Turkey. The vessels are of the Havyard 831 L SOV design and will service the Borssele III and IV offshore wind farm in the Netherlands, the Triton Knoll wind farm […]

  • 14 September 2022
    Grid Connection, Wind Farm Update

    Rotech Subsea has completed “challenging” cable de-burial, cut and recovery works at the Triton Knoll offshore wind project in the UK for a dredging and marine contractor. The Aberdeen-based company deployed its RS2-3 Hybrid controlled flow excavation (CFE) tool to complete the de-burial of approximately 500 metres of cable, with its RSG-C tool completing the […]

  • 9 April 2012
    Grid Connection

    The latest move of Triton Knoll wind farm developer, RWE npower renewables, to carry out “non-intrusive ecological surveys” has raised concerns, Lincolnshire reports. In January, the company changed their initial plans for connecting a 1,2 GW wind farm to the grid trough a 50 mile network of pylons across East Lindsey. The National Grid gave […]

  • 25 September 2017
    Grid Connection, Wind Farm Update

    VBMS has signed an EUR 80 million Preferred Supplier and Early Works Agreement for the Triton Knoll offshore wind farm. The Boskalis subsidiary, together with NKT Cables, is in charge of the supply and installation of export and inter-array cables.

  • 31 May 2019
    Contracts & Tenders

    Ordtek has secured a contract to provide specialist unexploded ordnance (UXO) risk management advice prior to the construction of the Triton Knoll offshore wind farm. The UK-based company has already provided research on the military history of the area for naval conflicts, aerial bombing and munition dumping sites. Additionally, Ordtek completed a geophysical data interpretation of the […]

  • 16 April 2018
    Ports & Logistics, Vessels, Wind Farm Update

    Fugro’s geotechnical drill vessel Fugro Scout has completed a three-week programme of test drilling at the locations of the 90 turbine foundations and two offshore substations on the 860MW Triton Knoll offshore wind farm.

  • 30 November 2015

    The Triton Knoll offshore wind project in East Lincolnshire could have impact on 200 farmers, according to land and property advisors Strutt & Parker. Alice Mesney from the company’s Stamford office said: “Underground cables will be required to carry electricity from offshore wind turbines to the National Grid. This involves laying six cable ducts over a […]

  • 6 February 2013
    Grid Connection

    The creation of hundreds of jobs and production of huge amounts of home grown renewable energy is one step closer today as RWE npower renewables makes a series of announcements about the Triton Knoll Offshore Wind Farm. The company, one of the UK’s leading renewable energy developers, is announcing a consultation on the wind farm’s […]

  • 19 January 2011

    THE CONTROVERSIAL proposal to build an electrical substation in East Lindsey connecting to the giant Triton Knoll Offshore Wind Farm off… (louthleader) [mappress] Source: louthleader, January 19, 2011

  • 2 April 2013

    RWE npower renewables have announced they will be hosting an additional opportunity for local residents to find out more about plans for the electrical system for the Triton Knoll Offshore Wind Farm. A public exhibition will be held for all those interested in finding out more on Saturday 13th April at Hale Magna Village Hall […]

  • 15 June 2011
    Business & Finance

    THE fate of a controversial proposal to build the world’s biggest offshore wind farm at Triton Knoll, 20 miles off Mablethorpe’s coast … [mappress mapid=”3997″] Source: louthleader, June 15, 2011;

  • 16 June 2020
    Grid Connection, Wind Farm Update

    The second offshore substation platform (OSP) has been installed at the 857 MW Triton Knoll wind farm offshore Lincolnshire, the UK. The installation of OSP East, the last of the project’s two OSPs, was carried out by Seaway Strashnov overnight on Monday 15 June. “This is an important step in ensuring we remain on track, […]

  • 21 May 2014
    Authorities, Business & Finance, Grid Connection, Wind Farm Update

    Triton Knoll Offshore Wind Farm developer, RWE, voiced its disappointment at the Lincolnshire County Council’s letter to the UK Department of Energy and Climate Change (DECC). “Lincolnshire County Council (LCC) have suggested that RWE Innogy UK has approached the community consultation for this project with ‘incomplete information’, despite agreeing a revised timetable with RWE Innogy […]

  • 22 June 2020
    Operations & Maintenance, Wind Farm Update

    The construction of the operations and maintenance base for the Triton Knoll offshore wind farm has been completed. UK-based contractor Tolent handed over the base at Grimsby’s Royal Dock this week, innogy said. Once fully fitted out, the O&M facility will accommodate a team of technicians and support staff responsible for maintaining the offshore wind farm […]

  • 11 July 2013
    Wind Farm Update

    RWE npower renewables welcomes today’s announcement that consent has been awarded for the turbines at Triton Knoll Offshore Wind Farm. The Secretary of State for Energy and Climate Change has granted consent for up to 288 offshore wind turbines to be located off the East Coast of England. The project has an installed capacity of […]

  • 9 March 2020
    Business & Finance

    Innogy has chartered the service operations vessel (SOV) Esvagt Froude to provide offshore accommodation to the construction management team working on the Triton Knoll wind farm located off the Lincolnshire coast, UK. This is the first time for innogy to established its team offshore rather than at an onshore location. Esvagt Froude has already made […]

  • 24 June 2020
    Operations & Maintenance

    Specialist Marine Consultants (SMC) has been awarded two contracts by Ørsted for above-water structural inspection of the wind turbine foundations at the developer’s offshore wind farms in Germany and the UK. Ørsted has four operational offshore wind farms in Germany and eleven in the UK. SMC has not disclosed which, if not all, projects will […]

  • 17 December 2018
    Business & Finance

    Triton Knoll Offshore Wind Farm Ltd is consulting on the draft Decommissioning Programme for the 860MW offshore wind project prior to submission to the UK Department of Business, Energy and Industrial Strategy (BEIS).

  • 18 February 2013
    Authorities, Grid Connection

    After the RWE npower renewables released their plans on connection of their Triton Knoll Offshore Wind Farm to the grid, they have hit an obstacle. Mark Simmonds, Member of Parliament (MP) for Boston and Skegness, thinks that these plans are „unsuitable“, as he believes that the wind farm should be located appropriately and have local […]

  • 19 October 2018
    Authorities, Contracts & Tenders, Wind Farm Update

    The three offshore wind projects selected in the UK’s second Contracts for Difference (CfD) allocation round have passed their 12-month milestone requirement, Low Carbon Contracts Company (LCCC) said.

  • 5 November 2017

    Most read news published by Offshore WIND in the past week.

  • 6 February 2017
    Contracts & Tenders, Environment, Grid Connection, R&D, Wind Farm Update

    Developers of the 900MW Triton Knoll offshore wind farm will host several invite-only site visits over the next few weeks for contractors hoping to win the main installation contract for the project’s underground onshore export cable. The sessions will provide an opportunity for prospective contractors to fully understand the overall site, ensuring their final contract tender offers […]

  • 27 March 2013

    A consultation being undertaken by RWE npower renewables on the options for locating the onshore electrical system for the Triton Knoll offshore wind farm has been extended following requests from the public. The renewable energy company is demonstrating that the consultation is still very much alive by sending out hundreds of additional copies of the […]

  • 2 April 2020
    Environment

    Seiche Environmental has been appointed to monitor and manage the safety of marine mammals at the Triton Knoll offshore wind project site in the UK. Seiche Environmental stated it is in charge of implementing important mitigation measures at the site offshore Lincolnshire, despite it already being assessed as having low potential for marine mammal presence. […]

  • 1 June 2020

    Orion’s Heavy Lift Crane Collapses – Video A heavy-lift crane installed on the offshore installation vessel Orion has collapsed while undergoing load tests at the Liebherr construction yard in Rostock, Germany. Siemens Gamesa Cranks It Up to 15 MW with Offshore Behemoth Siemens Gamesa has launched a new SG 14-222 DD offshore Direct Drive wind […]

  • 31 March 2014
    Environment, Grid Connection, Technology

    Ellis has designed an entirely new product in response to a cabling requirement from one of the biggest names in global business, Siemens. Triton is a two-in-one cable guide and clamp that was developed by Ellis following a call to assist in the installation, and subsequent restraining, of seven large diameter high voltage (HV) cables […]