offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
offshoreWIND.biz logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Agreement on Compensation for Loss of Earnings from Fishing (Denmark)
Business & Finance

October 5, 2011 · about 15 years ago

Agreement on Compensation for Loss of Earnings from Fishing (Denmark)

DONG Energy has signed an agreement with the Danish Fishermen’s Association on compensation for loss of earnings from fishing in connection with the construction of Anholt Offshore Wind Farm. The working area will be cordoned off for unauthorised persons during the construction, and there will be no

1 minutes read
  • LinkedIn
  • X
  • Email

DONG Energy has signed an agreement with the Danish Fishermen’s Association on compensation for loss of earnings from fishing in connection with the construction of Anholt Offshore Wind Farm.

The working area will be cordoned off for unauthorised persons during the construction, and there will be no fishing in the area.

On completion of the wind farm in 2013, net fishing will be resumed, whereas trawling will still be prohibited in the area. The agreement on compensation will be effective during the entire lifetime of the wind farm.

About Anholt Offshore Wind Farm

The installed capacity of the offshore wind farm is to be 400MW corresponding to the power consumption of approx 400,000 households. The offshore wind farm is to produce its first power by the end of 2012.

DONG Energy had acquired the licence for utilising the wind power for 25 years and is to construct and operate the offshore wind farm. The Danish transmission system operator, Energinet.dk, is responsible for establishing an offshore substation, the export cable to shore and the connection to the main high-voltage power grid on land.

[mappress]

Source: dongenergy, October 05, 2011

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Business & FinanceWind Farm Update

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Young Oysters Deployed on Two North Sea Cable Crossings
  2. 2Pacifico Energy Unveils EUR 860+ Million Investment in Two Offshore Wind Projects in South Korea
  3. 3Fourth Vard-Built CSOV Joins Windward Offshore Fleet
  4. 4ABS to Support Japanese Company’s 18 MW Floating Wind Turbine Pilot in Brazil

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free