offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
offshoreWIND.biz logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›News›The Netherlands: Verbrugge Terminals Loads Out Five Global Tech I Tripods
News

October 29, 2013 · about 13 years ago

The Netherlands: Verbrugge Terminals Loads Out Five Global Tech I Tripods

On Saturday October 18th Verbrugge Terminals in the Port of Vlissingen and its partner Sarens successfully completed the load-out of five tripods for the German offshore wind farm Global Tech I. The consortium Iemants N.V. and Eiffage Construction Métallique S.A.S were responsible for the load-out,

1 minutes read
  • LinkedIn
  • X
  • Email

On Saturday October 18th Verbrugge Terminals in the Port of Vlissingen and its partner Sarens successfully completed the load-out of five tripods for the German offshore wind farm Global Tech I.

The consortium Iemants N.V. and Eiffage Construction Métallique S.A.S were responsible for the load-out, including stability engineering of the tripods and engineering of the transport support structures.

The final assembly of these five tripods, as part of the Global Tech I contract with the consortium Iemants N.V. and Eiffage Construction Métallique S.A.S., was constructed in Vlissingen, whilst Verbrugge – Sarens provided the logistical support.

Verbrugge – Sarens offered Iemants the proper infrastructural conditions and handling experience required for this project. With its ample capacity of over 180 hectares and over 3.000m of heavy duty quay side, Verbrugge expects to continue to perform an important role as assembly location and marshalling harbour for the offshore (wind) industry in the years to come.

Global Tech I is presently expected to be fully operational in the summer of 2014 and with a total of 80 5-MW turbines will provide sufficient environmentally-friendly electricity to power an equivalent of 445.000 households with an average power demand of 3.130 kilowatt hours per year.

[mappress]

Press release, October 29, 2013; Image: verbrugge

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

News

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Gennaker Offshore Wind Farm Reaches Financial Close
  2. 2Half of Turbines at Dieppe–Le Tréport Offshore Wind Farm In Place
  3. 3Gondan Launches Østensjø Rederi's Ocean Energy Support Vessel
  4. 4New Boskalis Rock Installation Vessel Starts Work Offshore Poland

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free