Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Dong Hires CMP to Install Berthing System
Business & Finance

November 17, 2014 · about 12 years ago

Dong Hires CMP to Install Berthing System

Dong awarded CMP a contract to construct & install a complete berthing system for the crew transfer vessels in Barrow in Furness. It included dredging, socketing piles into rock and construction of heavy concrete pontoons on site and the fabrication and installation of steel access platform and brid

1 minutes read
  • LinkedIn
  • X
  • Email

Dong awarded CMP a contract to construct & install a complete berthing system for the crew transfer vessels in Barrow in Furness.

It included dredging, socketing piles into rock and construction of heavy concrete pontoons on site and the fabrication and installation of steel access platform and bridge.

The pontoon facility was regularly tested close to its maximum design conditions on a number of occasions between December 2013 and February 2014.

Wind gusts of 45m/s (160km/hr) were recorded locally (12.2.14) and waves in excess of 1.2 metres approaching from the south have been observed at the pontoon berthing facility on a number of days.

On 3rd January 2014 the highest ever recorded water level was experienced at Barrow with a high tide of more than 11 metres bringing the water level close to the top of the quay edge and the decks of the pontoons close to 1 metre from the tops of the piles.

The pontoon and services facility has shown to perform without problems and as designed and provides a very safe and stable berthing facility for use by DONG vessels and personnel in all weather conditions.

[mappress mapid=”14789″]

Press release; Image: cmp

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Business & FinanceVessels

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1US Gets New Offshore Wind Farm as All Turbines Installed at 704 MW Revolution Wind
  2. 2Vietnam-Made Cable Layer Enters Into Service in Taiwan
  3. 3Germany’s 960 MW He Dreiht Offshore Wind Farm Inaugurated
  4. 4200th Vestas V236-15.0 MW Wind Turbine Installed Offshore

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free