Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›News›Windfarm Update: Global Tech I
News

November 24, 2014 · about 12 years ago

Windfarm Update: Global Tech I

At the end of August the construction of the 400MW Global Tech I wind farm was completed with the installation of the last of the 80 Areva M5000-11 6 turbines. The construction has been within budget. Global Tech I is located approximately 180km northwest of Bremerhaven, in the German North Sea in w

1 minutes read
  • LinkedIn
  • X
  • Email

At the end of August the construction of the 400MW Global Tech I wind farm was completed with the installation of the last of the 80 Areva M5000-11 6 turbines.

The construction has been within budget. Global Tech I is located approximately 180km northwest of Bremerhaven, in the German North Sea in water depths of 40m. The project is owned by Global Tech I Offshore Wind GmbH who gained approval for the project from the Federal Maritime and Hydrographie Agency (BSH) in 2006. First main construction activities started in August 2012 with the preparations for the installation of the tripod foundations. The offshore substation was installed in May 2013.

Transmission grid operator TenneT wants to commence with test operation of the grid connection via BorWin beta and the interplay of the overall system of connection and wind farm during the fourth quarter this year. During this test phase the wind turbines will contribute small portions of electricity to the grid.

The regular grid connection is expected to be available in early 2015. The wind farm will then be feeding enough energy into the national grid to annually supply 445,000 households with electricity. 38 persons are working around the clock on the Global Tech I substation. From a control station at the company’s headquarterin Hamburg the wind farm will be monitored.

Image: globaltech

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

News

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1GS Entec Completes Monopile Factory in Korea
  2. 2PGE and Ørsted Add BGB Group to Baltica 2 Offshore Wind Team
  3. 3Fugro Wins UXO Survey Contract for German Offshore Grid Connections
  4. 4Seaway7 Completes Inter-Array Cable Installation at East Anglia Three Offshore Wind Farm

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free