offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
offshoreWIND.biz logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Authorities›50Hertz Advances with Ostwind 1 Cable Project
Authorities

May 8, 2015 · about 11 years ago

50Hertz Advances with Ostwind 1 Cable Project

50Hertz has reached another important milestone in the approval procedure for the Ostwind 1 offshore cable project. The public hearing for the submarine cable route in the Exclusive Economic Zone (EEZ) for the grid connection of the Westlich Adlergrund cluster (project Ostwind 1) was held last week.

2 minutes read
  • LinkedIn
  • X
  • Email

50Hertz has reached another important milestone in the approval procedure for the Ostwind 1 offshore cable project. The public hearing for the submarine cable route in the Exclusive Economic Zone (EEZ) for the grid connection of the Westlich Adlergrund cluster (project Ostwind 1) was held last week.

The competent authority for the approval of this route section is the Federal Maritime and Hydrographic Agency (BSH) in Hamburg. In the scope of the legally prescribed public participation procedure, the participants listened to the positions taken by more than 60 public agencies and discussed them under the guidance of the BSH. Following this hearing, the authority will work out the planning approval decision under the terms of the Offshore Installations Ordinance. 50Hertz expects the final decision in the summer of 2015 and hopes to commence preparations for the construction of the submarine cable route in the EEZ soon after.

Just as during the procedure with the Ministry of Energy of Mecklenburg-Western Pomerania, which is competent for the land route and the sea route in territorial waters, the majority of the positions concerned the environmental impact of the construction and operation of the power cables. Before the application documents were drawn up, 50Hertz performed a comprehensive scientific environmental study and drew up a matching route planning in order to minimise the effects of the project on the environment.

On 9 March 2015, 50Hertz received the planning approval decision for the onshore route from the Ministry of Energy of Mecklenburg-Western Pomerania. As a result, the construction of the project section right off the coast and on land can start as planned during the summer of this year. The Ministry of Energy announced that according to its current time schedule, the planning approval decision for the offshore route should be reached in June 2015.

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

AuthoritiesGrid Connection

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1DWT Returns to Riffgat Offshore Wind Farm
  2. 2Formosa 6 Offshore Wind Farm and Star Trade Enter Corporate Power Purchase Agreement
  3. 3TetraSpar Floater Completes Five-Year Testing Campaign Offshore Norway
  4. 4Standardization and Industrialization Could Cut Offshore Wind Costs in North Sea by 28% - Study

Daily offshore wind news in your mailbox.

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free