Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›Boskalis, VolkerWessels Bag EUR 500 Mln Veja Mate Job
Business & Finance

June 30, 2015 · about 11 years ago

Boskalis, VolkerWessels Bag EUR 500 Mln Veja Mate Job

Royal Boskalis Westminster N.V and VolkerWessels (Volker Stevin International) have been awarded a contract by Veja Mate Offshore Project GmbH for the Veja Mate offshore wind farm in the German section of the North Sea. Both companies have a 50% share in the contract worth approximately EUR 500 mill

1 minutes read
  • LinkedIn
  • X
  • Email

Royal Boskalis Westminster N.V and VolkerWessels (Volker Stevin International) have been awarded a contract by Veja Mate Offshore Project GmbH for the Veja Mate offshore wind farm in the German section of the North Sea.

Both companies have a 50% share in the contract worth approximately EUR 500 million, which covers the design, procurement, fabrication, supply, transportation, installation and testing of sixty seven foundations for the offshore wind project.

Each of the wind turbine foundations consists of an XXL monopile fabricated in Rostock (Germany) and a transition piece fabricated in Aalborg (Denmark). Following the transport from the fabrication sites to the wind farm, the monopiles will be installed with a purpose-built jack-up installation vessel supplemented by VolkerWessels and Boskalis shared equipment after which the transition pieces will be installed and flange-bolted to the monopiles.

The monopiles for the Veja Mate offshore wind farm weigh approximately 1300 tonnes and have a diameter of 7.8 meters. Volker Stevin International is responsible for the design and engineering of the permanent works and the handling tools during transport and installation of the foundations.

The fabrication works will commence in the third quarter of 2015 and offshore installation works will commence in the first quarter of 2016 with completion expected at the end of 2016.

Image: Boskalis (Illustration)

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Business & FinanceWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Ampelmann Completes Cargo Drone Campaign at Triton Knoll Offshore Wind Farm
  2. 2ACOUSTISCAN: Acoustic Partial Discharge Monitoring Strengthens Offshore Wind Reliability
  3. 3ABL to Support Marine Operations at Gennaker Offshore Wind Farm
  4. 4Dong Fang Offshore Takes Delivery of First Newbuild SOV, Adds New Vessel Order with Vard

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free