Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›TenneT Updates Switchgear Tender
Business & Finance

April 14, 2016 · about 10 years ago

TenneT Updates Switchgear Tender

TenneT TSO has issued an amended call for tender for switchgears that will allow safe transfer of electricity from five offshore platforms to the company’s high voltage grid in the Netherlands. In the period between 2017 and 2023, TenneT expects to build the five offshore platforms for the connectio

1 minutes read
  • LinkedIn
  • X
  • Email

TenneT TSO has issued an amended call for tender for switchgears that will allow safe transfer of electricity from five offshore platforms to the company’s high voltage grid in the Netherlands.

In the period between 2017 and 2023, TenneT expects to build the five offshore platforms for the connection of offshore wind farms to the Dutch grid.

For the connection of the platforms to the grid, TenneT plans to equip five landstations with a total of ten 33 kV switchgears for indoor application.

Each switchgear should consist of a single busbar and four bays, and not six bays as announced initially. Each bay should have a circuit breaker, a combined disconnector/earthing switch and instrument transformers. TenneT changed the circuit breakers from withdrawable to fixed.

After selection of candidates, TenneT will directly start with the call for tender for the mentioned switchgears. The call for tender will result in a framework agreement for delivery and installation with one supplier for all needed swichgears in the mentioned period.

TenneT expects to order the first two switchgears in the first half of 2017.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Business & FinanceContracts & TendersGrid ConnectionTechnology

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1IFM Investors to Acquire Majority Stake in UK Port Operator ABP
  2. 2TenneT and NKT Jointly Explore Offshore Cable Decommissioning
  3. 3GEOxyz Conducting Seabed Survey at East Anglia Two Offshore Wind Site
  4. 4US Gov’t Seeks New Review of US Wind’s Maryland Project

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free