Final Rampion Foundation Piled into Seabed

Vessels

Jack-up vessels MPI Discovery and Pacific Orca have completed the installation of 116 turbine foundations at the 400MW Rampion wind farm off Sussex, E.ON reports.

MPI Discovery. Source: MPI Offshore

The installation has been completed on schedule, E.ON said.

Work to install the first foundations began in early February and was put on hold, as planned, during the Black Bream spawning season between mid-April and July.

Since then the two jack-up vessels have worked to install the foundations using a 1,000 tonne crane to lift each foundation upright before lowering and piling it into the seabed with a hydraulic hammer.

The yellow transition pieces have also been fitted onto the foundations and sit approximately 20 metres above sea level ready to hold the turbines.

Over the next few months the team will make the final preparations for the installation of MHI Vestas 3.45MW turbines, due to commence in spring and continue throughout 2017.

Work will also continue to progress on the offshore cabling and substation, E.ON said.

“We’re pleased and proud to have reached this project milestone and we appreciate the patience of local residents whilst these major works have taken place,” Chris Tomlinson, E.ON Development and Stakeholder Manager for the Rampion Offshore Wind Farm, said.

“Despite the adverse weather at the start of the year, the good autumnal weather conditions have enabled us to finish this phase of work ahead of winter, which is testament to the commitment of the construction team. We now look forward to starting the turbine installations in the spring, which will see the wind farm really begin to take shape as the 116 turbines are gradually installed throughout next year.”

The GBP 1.3 billion Rampion is being built 13km off the Sussex coast by E.ON, the UK Green Investment Bank plc and Canadian energy company Enbridge. The project is due to be completed and fully operational in 2018.