Scour Protection Work Begins at Aberdeen Bay OWF

Vessels

Boskalis’ fallpipe vessel (FPV) Rockpiper is carrying out scour protection works at the Aberdeen Bay Offshore Wind Farm. According to a notice to mariners, Rockpiper will be working at the project site for three weeks and was scheduled to start on 28 October.

Image source: Boskalis (cropped)

The eleven wind turbine positions at Vattenfall’s offshore wind farm – also known as the European Offshore Wind Deployment Centre (EOWDC) – will all have scour protection in place before the foundations are installed.

Boskalis is the overall Tier 1 supplier of the project’s offshore balance of plant (BoP) work for the construction and installation (EPCI) of the offshore infrastructure including the foundations and cabling.

Subsequently, Boskalis awarded Smulders Project a contract for manufacturing and assembling suction bucket jacket foundations for EOWDC. The foundations are expected to be installed in January 2018, followed by the installation of the 66kV inter-array cables and the export cable, supplied by JDR.

The foundations will support eleven MHI Vestas 8.4MW turbines, scheduled for installation in March 2018.

J. Murphy & Sons is the EPC contractor for the onshore substation and associated cabling work.

Offshore WIND Staff