Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Ports & Logistics›MARIN, Deltares Test Transport & Installation of Gravity-Based Structures
Ports & Logistics

December 11, 2017 · about 8 years ago

MARIN, Deltares Test Transport & Installation of Gravity-Based Structures

Dutch research institutes MARIN and Deltares have completed a test campaign focused on the transport and installation of gravity-based structures (GBS) as part of the GBS WIND Joint Industry Project (JIP) launched in March 2017.

2 minutes read
  • LinkedIn
  • X
  • Email

Dutch research institutes MARIN and Deltares have completed a test campaign focused on the transport and installation of gravity-based structures (GBS) as part of the GBS WIND Joint Industry Project (JIP) launched in March 2017 .

Image: MARIN/ Deltares (cropped)

The two research institutes carried out the campaign to get a deeper insight into the motions of a gravity-based structure during transport and installation, which have not been well captured by standard design methods . In particular the nonlinear, viscous effects such as Vortex Induced Motion (VIM) and galloping have not been accurately computed, according to the researchers.

During more than 14 weeks of testing , MARIN and Deltares were using three model basins and were able to consider the full operation from port to fully ballast on the seabed.

“We have created a truly unique dataset which has given us a better understating of the dynamic behaviour of gravity based structures during transportation and installation. We have been able to investigate phenomena such as VIM during installation and to improve our numerical models. Previously this has not been possible to this level of detail,” said Dr. Bo Terp Paulsen , project manager Deltares.

During the project’s next phase , improved numerical models will be used to drive the simulators at MARIN and tug captains will be able to practice critical moments of the transportation and installation phases, giving valuable feedback to the engineers and designers who can then optimise future foundations for stability and safe marine operations.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Ports & LogisticsR&D

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1OEG to Supply Temporary Power for Hornsea 3 Offshore Wind Farm
  2. 2Bibby Marine Launches Battery-First eCSOV in Spain
  3. 3Ørsted to Buy Back Remaining Stake in Gunfleet Sands Offshore Wind Farm
  4. 4EDF Buys RWE’s Stake in 1.1 GW UK Offshore Wind Farm

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free