Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Ports & Logistics›Bold Tern Completes Third Borkum Riffgrund 2 Run
Ports & Logistics

May 23, 2018 · about 8 years ago

Bold Tern Completes Third Borkum Riffgrund 2 Run

Fred. Olsen Windcarrier’s jack-up Bold Tern has loaded and transported the third set of MHI Vestas wind turbine components from the Port of Esbjerg in Denmark to the Borkum Riffgrund 2 wind farm in the German North Sea. The vessel has so far installed eight out of the 56 MHI Vestas 8MW turbines at t

1 minutes read
  • LinkedIn
  • X
  • Email

Fred. Olsen Windcarrier’s jack-up Bold Tern has loaded and transported the third set of MHI Vestas wind turbine components from the Port of Esbjerg in Denmark to the Borkum Riffgrund 2 wind farm in the German North Sea.

The vessel has so far installed eight out of the 56 MHI Vestas 8MW turbines at the site some 57 kilometres off the north-west coast of Germany.

The turbines are being installed on 36 monopile foundations and 20 suction bucket jacket foundations .

Back in April, Van Oord started installing the cables to connect the turbines to the offshore substation. The wind farm will also be connected to the nearby Borkum Riffgrund 1, as well as the DolWin3 converter platform.

Ørsted, the developer of the 450MW project, plans to officially inaugurate the wind farm in 2019.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Ports & LogisticsVesselsWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1US Gets New Offshore Wind Farm as All Turbines Installed at 704 MW Revolution Wind
  2. 2Vietnam-Made Cable Layer Enters Into Service in Taiwan
  3. 3Germany’s 960 MW He Dreiht Offshore Wind Farm Inaugurated
  4. 4200th Vestas V236-15.0 MW Wind Turbine Installed Offshore

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free