Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farm Update›First Jacket Foundation Installed at East Anglia One
Wind Farm Update

June 12, 2018 · about 8 years ago

First Jacket Foundation Installed at East Anglia One

Van Oord has installed the first jacket foundation at the East Anglia One offshore wind farm located in the UK North Sea.

2 minutes read
  • LinkedIn
  • X
  • Email

Van Oord has installed the first jacket foundation at the East Anglia One offshore wind farm located in the UK North Sea.

The Dutch company has recently chartered Boskalis’s new self-propelled DP2 crane vessel Bokalift 1 for the installation of foundations and pinpiles, while the main installation vessel Sejacks Scylla is expected to begin working on the wind farm at the end of July or the beginning of August.

According to Van Oord, the East Anglia One project will have the largest number of three-legged foundations ever installed on a wind farm, located at depths of down to 55m in the southern North Sea.

“This project makes our expertise in the installation of foundations even broader. So far only a handful of wind farms have been constructed on jacket foundations. Their number will increase in the years ahead because the ideal locations for wind farms built on monopiles – shallow waters with a relatively flat, firm seabed – are filling up fast,” said Daan Makkink , Project Director.

ScottishPower Renewables, the owner of the wind farm, selected Van Oord last year as the lead contractor in charge of transport and installation of the turbine foundations, including logistics and deployment of the equipment.

For the 102-turbine project, 60 jacket foundations and pinpiles are being fabricated by Lamprell at its Jebel Ali and Sharjah yards in the UAE, with the Spanish Navantia and Windar providing the remaining 42 jackets and accompanying pinpiles.

Located 45km offshore Lowestoft, the 714MW East Anglia One wind farm will comprise 7MW Siemens Gamesa turbines expected to be fully operational in 2020.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Wind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Ørsted Opens EUR 26+ Million Tender for Birds & Bats Monitoring at Polish Offshore Wind Farms
  2. 2First Turbine Up at Vietnam's 128 MW Nearshore Wind Farm
  3. 3Gennaker Offshore Substation Jackets Loaded Out in Netherlands
  4. 4Alternative Approach to Turbine Bearing Maintenance Tested at Ormonde Offshore Wind Farm

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free