Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid Connection›EOWDC Delivers First Power
Grid Connection

July 2, 2018 · about 8 years ago

EOWDC Delivers First Power

Vattenfall’s 93.2MW European Offshore Wind Deployment Centre (EOWDC) has generated its first power.

1 minutes read
  • LinkedIn
  • X
  • Email

Vattenfall’s 93.2MW European Offshore Wind Deployment Centre (EOWDC) has generated its first power.

The first out of a total of 11 recently installed turbines exported the first power to the National Grid on 1 July via 66kV subsea cabling.

This is the first time cabling of this capacity has been installed on a commercial offshore wind project in Scotland, Vattenfall said, emphasizing that in comparison to conventional 33kV cabling, less inter-array cabling is required leading to reduced construction cost.

“We have overcome major engineering and technical challenges to achieve first power on the cutting edge EOWDC thanks to the collective expertise of Vattenfall, and our contractors MHI Vestas, Boskalis and Murphy. Our priority now is to fully commission the windfarm safely throughout the summer,” Adam Ezzamel , Vattenfall’s EOWDC Project Director, said.

“First power from EOWDC reinforces North-east Scotland’s status as Europe’s energy capital and will help establish the region as an international centre for offshore wind generation.”

According to the Swedish energy company, over 21km of cabling has been installed from the offshore wind project in the Aberdeen Bay to Blackdog Substation.

EOWDC, also known as Aberdeen Offshore Wind Farm, comprises nine MHI Vestas 8.4MW turbines and two MHI Vestas turbines with a record-breaking capacity of 8.8MW.

Apart from generating electricity, the wind farm will be a centre for testing and developing new technologies for offshore wind power.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Grid ConnectionWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1US Gets New Offshore Wind Farm as All Turbines Installed at 704 MW Revolution Wind
  2. 2Vietnam-Made Cable Layer Enters Into Service in Taiwan
  3. 3Germany’s 960 MW He Dreiht Offshore Wind Farm Inaugurated
  4. 4200th Vestas V236-15.0 MW Wind Turbine Installed Offshore

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free