Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Contracts & Tenders›Mick George Moving Earth for Triton Knoll
Contracts & Tenders

December 14, 2018 · about 7 years ago

Mick George Moving Earth for Triton Knoll

Construction specialist Mick George Ltd has been appointed on behalf of J. Murphy and Sons Ltd to complete earthworks at the main onshore cable site for the Triton Knoll wind farm offshore Lincolnshire, UK.

1 minutes read
  • LinkedIn
  • X
  • Email

Construction specialist Mick George Ltd has been appointed on behalf of J. Murphy and Sons Ltd to complete earthworks at the main onshore cable site for the Triton Knoll wind farm offshore Lincolnshire, UK.

The firm will be stripping the easement where the cables will be placed for this 860MW project.

The Triton Knoll project involves the installation of more than 57km of underground high-voltage electrical export cable in Lincolnshire.

The route starts at the landfall location north of Anderby Creek, where the onshore and offshore cables connect. It runs to a new substation being constructed near Bicker, and then to the existing National Grid Bicker Fen Substation where the electricity from the offshore wind farm will ultimately connect into the grid.

More than 300 individual directional drills – a record for a UK infrastructure project – will ensure the onshore cables can be installed without obstructing any roads, highways, rivers or drains, the company said.

Although the two-year onshore construction programme is underway , offshore activities are not expected to begin until late 2019. First energy generation could be as early as 2021.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Contracts & TendersGrid ConnectionWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1First Data from ‘Most Ecological Offshore Wind Farm’ Made Publicly Available
  2. 2EEW SPC to Supply TP-Less Monopiles for First Phase of CIP and Vattenfall’s Zeevonk Project
  3. 3Vineyard Wind, GE Vernova Settle Dispute; GE Withdraws Termination Notice
  4. 4Ørsted Opens EUR 26+ Million Tender for Birds & Bats Monitoring at Polish Offshore Wind Farms

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free