Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Contracts & Tenders›Iberdrola Starts Building Supply Chain for 3.1 GW East Anglia Hub
Contracts & Tenders

April 29, 2020 · about 6 years ago

Iberdrola Starts Building Supply Chain for 3.1 GW East Anglia Hub

Iberdrola has received bids from wind turbine suppliers and started activities to purchase electrical components for its East Anglia Hub offshore wind project. ScottishPower Renewables, Iberdrola’s UK company, has combined the East Anglia 1 North, East Anglia 2 and East Anglia 3 projects into one 3.

1 minutes read
  • LinkedIn
  • X
  • Email
An image mapping offshore locations of each of the East Anglia Hub three projects
ScottishPower Renewables

Iberdrola has received bids from wind turbine suppliers and started activities to purchase electrical components for its East Anglia Hub offshore wind project.

ScottishPower Renewables, Iberdrola’s UK company, has combined the East Anglia 1 North, East Anglia 2 and East Anglia 3 projects into one 3.1 GW development.

The 1.4 GW East Anglia Three already has planning consent, while the planning applications for the further 1.7 GW at East Anglia One North and East Anglia Two were submitted in October 2019.

According to information in Iberdrola’s Q1 2020 report, the main engineering, design and site investigation work for East Anglia Hub is now in the development stage.

ScottishPower Renewables aims to begin construction in 2022 and anticipates a four-year construction period to complete the entire project.

The overall investment required will be around £ 6.5 billion (approx. € 7.4 billion). The company plans to confirm the major suppliers until the end of September 2020.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Contracts & TendersWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Trump Administration Seeks Remand of COP Approval for Offshore Wind Farm Now in Final Commissioning Stage
  2. 2Ofgem to Launch Record Tender as UK Regulator Seeks Owner of Hornsea 3 Offshore Transmission Assets
  3. 3French Engineering Company Acquires Irish Sea Contractors to Expand Offshore Wind and Cable Services
  4. 4Pacifico Energy Launches Survey Campaign for 1.8 GW Offshore Wind Projects in Vietnam

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free