Iberdrola Starts Building Supply Chain for 3.1 GW East Anglia Hub

Contracts & Tenders

Iberdrola has received bids from wind turbine suppliers and started activities to purchase electrical components for its East Anglia Hub offshore wind project.

ScottishPower Renewables
An image mapping offshore locations of each of the East Anglia Hub three projects
ScottishPower Renewables

ScottishPower Renewables, Iberdrola’s UK company, has combined the East Anglia 1 North, East Anglia 2 and East Anglia 3 projects into one 3.1 GW development.

The 1.4 GW East Anglia Three already has planning consent, while the planning applications for the further 1.7 GW at East Anglia One North and East Anglia Two were submitted in October 2019.

According to information in Iberdrola’s Q1 2020 report, the main engineering, design and site investigation work for East Anglia Hub is now in the development stage.

ScottishPower Renewables aims to begin construction in 2022 and anticipates a four-year construction period to complete the entire project.

The overall investment required will be around £ 6.5 billion (approx. € 7.4 billion). The company plans to confirm the major suppliers until the end of September 2020.