Dogger Bank Transformers Start Rolling In

Grid Connection

The first of a number of transformers that will enable the transmission of renewable energy from the 3.6 GW Dogger Bank, the world’s largest offshore wind farm, has been delivered, SSE Renewables said.

SSE Renewables

The transformers will play an integral role in the operation of three onshore convertor stations in East Riding of Yorkshire and on Teesside, that will eventually convert the current from the wind farm for transmission via the national grid network to six million UK homes.

Source: SSE Renewables

This week the first transformer was successfully transported from Port of Hull to the first convertor station off the A1079 near Beverley in East Riding, where construction of a second convertor station is also underway by tier-one supplier Hitachi Energy.

Related Article

Three further deliveries are scheduled in East Riding on the mornings of 15, 22, and 29 May, with deliveries for the second East Riding convertor station taking place in 2023.

Heavy lift and transportation specialist Allelys was appointed by Hitachi Energy to carry out and oversee these latest deliveries.

”Successful delivery of the first transformer is an important milestone for our world-leading project,” Dogger Bank Wind Farm Transmission Package Manager Børge Angelfloss said.

”Our thanks go to all those involved in ensuring this happened safely, including the local highways authority and representatives from Humberside Police for their valuable expertise on the route between Port of Hull and our convertor station site.”

Hitachi Energy is due to start work on the third convertor station on Teesside later this year. The company is responsible for providing its high-voltage direct current (HVDC) Light® systems for all three phases of the wind farm, including the project’s three high-tech onshore convertor stations.

”Hitachi Energy is proud to be connecting the Dogger Bank Wind Farm to the energy grid using HVDC (high voltage direct current) technology,” Göran Isacsson, Project Director for Hitachi Energy, said.

”The delivery and installation of the transformers at the onshore converter stations we are building are important milestones for the project. We are pleased to have successfully achieved this first shipment and we thank the local authorities and community for their support and patience.”

Dogger Bank Wind Farm is being built in three 1.2 GW phases known as A, B, and C. The project is a joint venture between SSE Renewables (40 per cent), Equinor (40 per cent) and Eni Plenitude (20 per cent).  

It will be the first HVDC-connected wind farm in the UK, paving the way for other UK wind farms and suppliers to build on our experience transmitting renewable energy safely and efficiently across long distances while minimising potential losses, SSE Renewables said.

Last month, the Dogger Bank Wind Farm team officially marked the start of its offshore construction work with the installation of the first length of HVDC export cable off the Yorkshire coast.

Related Article

Tier one supplier NKT is leading the work to install the Dogger Bank A nearshore cable, that will connect the first phase of the windfarm more than 130 kilometres off the coast to a landfall point at Ulrome, in East Riding of Yorkshire.

The wind farm will feature GE Haliade-X 13 MW and 14 MW wind turbines scheduled to deliver first power in 2023 and be fully commissioned in 2026.

Follow offshoreWIND.biz on: