Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Featured›Jacket Foundation for BorWin Kappa Offshore Converter Platform Loaded Out in UAE
Featured

February 9, 2026 · about 7 months ago

Jacket Foundation for BorWin Kappa Offshore Converter Platform Loaded Out in UAE

Mammoet has completed the transport, load-out and mooring of the jacket foundation for the BorWin kappa offshore converter platform at McDermott’s yard in Dubai, UAE. BorWin kappa is part of TenneT’s 980 MW BorWin6 offshore wind grid connection in the German North Sea. The Dutch company has been sel

2 minutes read
  • LinkedIn
  • X
  • Email
Jacket Foundation for BorWin Kappa Offshore Converter Platform Loaded Out in UAE
Mammoet

Mammoet has completed the transport, load-out and mooring of the jacket foundation for the BorWin kappa offshore converter platform at McDermott’s yard in Dubai, UAE. BorWin kappa is part of TenneT’s 980 MW BorWin6 offshore wind grid connection in the German North Sea.

The Dutch company has been selected as a subcontractor to provide jacking, transport and load-out services by McDermott, which was awarded the engineering, procurement, construction and installation (EPCI) scope for the BorWin6 topside and jacket in 2022.

Related Articles

Contracts & Tenders

McDermott and GEIRI/C-EPRI to Build Converter Platforms for BorWin6 Offshore Grid

3 min read

McDermott started building the offshore converter platform at its Jebel Ali yard in July 2023.

Related Articles

Grid Connection

Construction Starts on TenneT’s BorWin6 HVDC Converter Platform

2 min read

Mammoet transported the 5,461-tonne jacket foundation using 216 axle lines of self-propelled modular transporters (SPMTs) powered by four power pack units, while the company’s winches supported mooring management during quay activities.

The jacket and its pin piles have been secured for sailaway to Europe for the next phase of the project, according to Mammoet, which said the focus will now shift to the topside.

Later this year, Mammoet will complete the BorWin kappa topside jack-up and weighing, with the topside expected to weigh approximately 17,000 tonnes. For this operation, the company will use its Mega Jack System, which has been used for lifts in excess of 40,000 tonnes, and will prepare the topside for skidded loadout and sailaway later in the year.

“This jacket loadout is an important step for BorWin6 and it reflects the level of planning and control needed in a busy fabrication environment. As the project moves into its next phases, our team is now focused on preparing for the upcoming jack up, weighing and loadout of the topside later in 2026” , said Tom Brazier , Mammoet Project Manager.

Scheduled to go into operation in 2027, BorWin6 will collect three-phase current generated at the offshore wind farms, which will then be converted into direct current and transported to an onshore converter station located near Büttel, Germany.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

FeaturedHeadlinesGrid ConnectionOffshore PlatformsProject Updates

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1LD Armateurs Welcomes Multipurpose Support Vessel to Its Fleet
  2. 2NYK Line Orders Ulstein-Designed SOV at PaxOcean
  3. 3Bibby Marine Says eCSOV Can Cut Fuel Consumption by 40 Pct Before Offshore Charging Becomes Available
  4. 4Siemens Gamesa Charters Purus SOV for North Sea O&M Work

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free