Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Contracts & Tenders›Bladt Scores Hornsea Two Contract
Contracts & Tenders

June 3, 2019 · about 7 years ago

Bladt Scores Hornsea Two Contract

Ørsted has contracted Bladt Industries to produce 135 transition pieces for the Hornsea Project Two offshore wind farm in the UK. The fabrication of the transition pieces is planned to begin this year at Bladt’s site in Aalborg, Denmark, with delivery expected to take place from mid-2020 to mid-2021

1 minutes read
  • LinkedIn
  • X
  • Email

Ørsted has contracted Bladt Industries to produce 135 transition pieces for the Hornsea Project Two offshore wind farm in the UK.

The fabrication of the transition pieces is planned to begin this year at Bladt’s site in Aalborg, Denmark, with delivery expected to take place from mid-2020 to mid-2021.

“We are proud that Ørsted have trusted Bladt Industries as the fabricator for Hornsea Two,” said Klaus Steen Mortensen , CEO of Bladt Industries.

“This contract is not only one of the largest contracts Bladt Industries have been awarded, but fosters also strategic opportunities to further strengthen our relationship with Ørsted. A contract of this size will allow us to full scale utilize our new and lean production set-up.”

According to Chief Sales Officer Nils Overgaard, with this contract, Bladt will pass the track record of 2,000 foundations.

DEME Offshore will transport and install the project’s 165 foundations with its new DP3 offshore installation vessel Orion at the project site some 89km off the Yorkshire coast.

The 1.4GW Hornsea Two offshore wind farm will comprise 165 Siemens Gamesa 8.4MW turbines expected to be up and running by 2022.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Contracts & Tenders

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Njord Survey Inks Three-Year Agreement with RWE
  2. 2Jan De Nul Orders Another Newbuild Trenching Support Vessel
  3. 3DEHN Launches Digital Platform for Wind Turbine Lightning Monitoring
  4. 4Cadeler and Vattenfall to Explore Next-Gen Offshore Wind Major Component Exchange Solutions

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free