Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Ports & Logistics›ALE and Giant Taiwan Team Up on Formosa
Ports & Logistics

August 19, 2019 · about 7 years ago

ALE and Giant Taiwan Team Up on Formosa

Heavy lift specialist ALE and Giant Taiwan have undertaken a joint venture to provide the onshore handling, transportation, and storage of wind turbine foundations for phase 2 of Taiwan’s Formosa 1 wind farm project. This phase is seeing 20 Siemens Gamesa 6MW wind turbines installed 6 kilometres off

2 minutes read
  • LinkedIn
  • X
  • Email

Heavy lift specialist ALE and Giant Taiwan have undertaken a joint venture to provide the onshore handling, transportation, and storage of wind turbine foundations for phase 2 of Taiwan’s Formosa 1 wind farm project.

This phase is seeing 20 Siemens Gamesa 6MW wind turbines installed 6 kilometres off Miaoli County in the Taiwan Strait, raising its power generation capability from its current 8MW to 128MW.

ALE – Giant’s scope in the project included, among others, the transportation and load-out of monopiles from their point of fabrication in Rostock, Germany, the development of earthquake-resilient storage facilities at the Port of Taichung, Taiwan, and the load-in of both monopiles and transition pieces there.

These items are currently in the process of installation by the offshore vessel Seaway Yudin.

“By establishing ALE – Giant we have fast tracked our localization and have been able to offer ALE’s world class services, safety and quality standards while being seen as a local partner from day one,” Chris Schraa, director of ALE Taiwan, said.

The total project is scheduled to have a duration of eight months. The Formosa 1 Phase 2 offshore wind farm is expected to be fully built by the end of the year and fully operational in 2020.

Yannick Sel , director of Global Strategic Sales, said: “This is truly a winning combination in which ALE brings its knowledge built up in the offshore wind industry in Europe and Giant complements it with valuable local connections and expertise.”

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Ports & LogisticsWind Farm Update

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1200th Vestas V236-15.0 MW Wind Turbine Installed Offshore
  2. 2Neptun Werft-Smulders Joint Venture Secures Second 2 GW Converter Platform Contract from 50Hertz
  3. 3First Data from ‘Most Ecological Offshore Wind Farm’ Made Publicly Available
  4. 4EEW SPC to Supply TP-Less Monopiles for First Phase of CIP and Vattenfall’s Zeevonk Project

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free