Offshore Wind
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Contracts & Tenders
  • Grid Connection
  • More news
JobsNewsletter
Offshore Wind logo

Your trusted source for global offshore wind news, part of the Navingo network.

Topics
  • Fixed-Bottom
  • Floating Wind
  • Grid Connection
  • Power-to-X
  • Supply Chain
Network
  • Offshore Wind
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Business & Finance›UK Proposes to Ease OFTO Rules on Four OWFs
Business & Finance

July 24, 2020 · about 6 years ago

UK Proposes to Ease OFTO Rules on Four OWFs

The UK Government has proposed to exempt Beatrice, Hornsea One, Rampion, and East Anglia One offshore wind farms from the requirement to hold a licence to transmit electricity, due to COVID-19-related delays in transferring their transmission assets. The four offshore wind farms, involved in the fif

1 minutes read
  • LinkedIn
  • X
  • Email
A photo of Rampion offshore substation
Rampion Offshore Wind Limited

The UK Government has proposed to exempt Beatrice, Hornsea One, Rampion, and East Anglia One offshore wind farms from the requirement to hold a licence to transmit electricity, due to COVID-19-related delays in transferring their transmission assets.

The four offshore wind farms, involved in the fifth and sixth tender rounds of the Offshore Transmission Owner (OFTO) regime, would otherwise be at risk of transmitting electricity unlawfully.

“The exemptions are being proposed on the basis that the delays caused by COVID-19 constitute exceptional circumstances”, the UK Department for Business, Energy & Industrial Strategy (BEIS) states in its consultation notice for the exemption order.

There would be a time limit, from three to twelve months, for each project to be allowed to operate without the licence, depending on how much the COVID-19 impacted each of them.

According to the UK OFTO regime, an offshore wind farm’s transmission assets should be transferred to an independent OFTO operator within 18 months after a project is completed. Within these 18 months, the OFTO tender process is taking place.

However, now the tender process for the fifth and sixth OFTO is impacted by the ongoing pandemic and restrictions, and is expected to be affected further.

Reach the Offshore Wind industry in one go!

Offshore Wind is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Wind on:

Filed under

Business & FinanceGrid Connection

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1French Engineering Company Acquires Irish Sea Contractors to Expand Offshore Wind and Cable Services
  2. 2Pacifico Energy Launches Survey Campaign for 1.8 GW Offshore Wind Projects in Vietnam
  3. 3Inter-Array Cable Installation About to Start at 2.9 GW UK Offshore Wind Farm
  4. 4Ørsted Orders Third Saab Seaeye Cougar ROV for Offshore Wind Operations

Daily Offshore Wind News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free