World’s Most Powerful Wind Turbine to Debut Offshore Scotland

Contracts & Tenders

Siemens Gamesa has been awarded the firm order for the delivery of 60 units of its SG 14-222 DD offshore wind turbine at the Moray West offshore wind power project.

Siemens Gamesa/Illustration

The wind turbines will have a capacity of 14.7 MW each and utilize the PowerBoost feature.

A service agreement is included in the order for the 882 MW project located in Scotland’s Moray Firth.

Related Article

The project will feature strong content from the UK, with all 180 Siemens Gamesa B108 IntegralBlades to be produced at the company’s offshore blade factory in Hull, England, the turbine maker said.

”Siemens Gamesa has made the largest investments in the UK offshore wind supply chain, with our Hull facility as the centerpiece,” said Marc Becker, CEO of the Siemens Gamesa Offshore Business Unit.

”We’re proud to supply all 180 108 meter-long blades for the Moray West order from the expanded plant. As announced in August 2021, it will soon to be doubled in size compared to when it first opened. We continue to appreciate the support from the UK government in this development.”

A rapid deployment timeline targets the installation of the first machines in 2024, with first power being expected to be produced in 2024.

Related Article

”Successfully signing the firm order for Moray West serves to further cement Siemens Gamesa as the leader of the offshore revolution,” Becker said.

”We were heartened to be named preferred bidder by Moray West in October 2021 and are now even happier to see their confidence in us become reality today. We’re able to contribute to both combatting the climate emergency and develop the world’s largest offshore wind market simultaneously,”

The Moray West project will be located over 22 kilometres from the Moray Council coast in the northeast of Scotland.

The project will serve as the first serial installation of Siemens Gamesa’s 14 MW machine.

”Siemens Gamesa has a strong track record, and this model will allow the next progression in efficiency for offshore wind power generation,” Adam Morrison, Project Director for Moray West, said.

”We are particularly pleased that our early commitments to Siemens Gamesa will result in the first of the 108 m blades from the expanded Hull facility being used on Moray West. We look forward to working with Siemens Gamesa to ensure a smooth and safe installation programme from the Nigg pre-assembly port as we move towards generation from this major renewables project – stepping towards Net Zero, increasing energy security and lowering the cost of energy.”

More than 14 GW of firm orders, preferred supplier agreements, and preferred bidder agreements have been announced for the Siemens Gamesa 14 MW machine, including rotor variants of 222 and 236 metres, the turbine maker said.

Launched in 2020, the first prototype of the massive machine was installed in 2021 in Denmark.

Related Article

Moray West is developed and majority-owned by Ocean Winds, with Lithuania’s Ignitis Group holding a minority share in the project.

Follow offshoreWIND.biz on: