Half of the monopile foundations are now in place at the Thor offshore wind farm site, as Jan De Nul’s heavy-lift vessel Les Alizés installed the 36th of the project’s total 72 monopiles on 15 July.
Featured
about 1 year ago
Half of Monopile Foundations In Place at Thor Offshore Wind Farm
Half of the monopile foundations are now in place at the Thor offshore wind farm site, as Jan De Nul’s heavy-lift vessel Les Alizés installed the 36th of the project’s total 72 monopiles on 15 July. “With Thor we are constructing Denmark’s largest offshore wind farm to date. Reaching halfway in the